Krishna P. Singh Technology Campus, 1 Holtec Blvd., Camden, NJ 08104 Telephone (856) 797-0900 Fax (856) 797-0909 HDI-OC-21-071 Page 1 of 2 August 16, 2021 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Oyster Creek Nuclear Generating Station Renewed Facility License No. DPR-16 NRC Docket No. 50-219
Subject:
Notification of Removal of Participation in Security Advisory 07-01
References:
[1]
Security Advisory 07-01, Revision 1, from U.S. Nuclear Regulatory Commission, Voluntary Use of Authentication Codes to Validate Caller Identification During Threats and Physical Attacks, June 25, 2007 (ML070790129)
[2]
Letter from Michael P. Gallagher, Exelon Generation Company, LLC to U.S.
Nuclear Regulatory Commission - Certification of Permanent Removal of Fuel from the Reactor Vessel for Oyster Creek Nuclear Power Station, dated September 25, 2018 (ML18268A258)
[3]
Letter from Andrea L. Sterdis, Holtec Decommissioning International, LLC to U.S.
Nuclear Regulatory Commission - Oyster Creek Registration of Spent Fuel Cask Use and Notification of all Spent Fuel Assemblies from the Spent Fuel Pool. Dated May 25, 2021 (ML21145A261)
This letter is to inform the United States Nuclear Regulatory Commission (USNRC) that, as of August 16.
2021, Oyster Creek Nuclear Generating Station (OCNGS) is formally removing the site from voluntary participation in the guidelines put forth in Reference 1. The additional actions necessary to determine notification validity did impact functions that were necessary in an operating plant scenario. However, with the plant in a permanently defueled state and all fuel stored on the Independent Spent Fuel Storage Installation (ISFSI) pad, time critical actions no longer exist at the site for such an event and, as such, participation in this voluntary program is no longer necessary. OCNGS previously documented that all fuel has been permanently removed from the Reactor Vessel in Reference 2 and relocation of all spent fuel to the ISFSI storage facility in Reference 3.
Should you have any questions or require further information, please contact me at (856) 797-0900, x3813.
Respectfully, Andrea L. Sterdis HDI VP Regulatory and Environmental Affairs Holtec Decommissioning International, LLC Digitally signed by Andrea Sterdis DN: cn=Andrea Sterdis, c=US, o=Holtec Decommissioning International, ou=HDI, email=a.sterdis@holtec.com Date: 2021.08.16 14:40:29 -04'00' Andrea Sterdis
Krishna P. Singh Technology Campus, 1 Holtec Blvd., Camden, NJ 08104 Telephone (856) 797-0900 Fax (856) 797-0909 HDI-OC-21-071 Page 2 of 2 cc:
NRC Regional Administrator, Region 1 NRC NMSS Project Manager - Oyster Creek Nuclear Generating Station NRC Region 1, Lead Inspector - Oyster Creek Nuclear Generating Station Assistant Commissioner, Air Quality, Energy and Sustainability, NJ DEP Assistant Director Radiation Protection Element, NJ Bureau of Nuclear Engineering