Category:Letter type:ND
MONTHYEARND-24-0103, Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2024-04-26026 April 2024 Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-24-0114, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-04-0101 April 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-24-0046, (Vegp), Unit 3, Condition Prohibited by Technical Specification Limiting Condition of Operation 3.1.6 Control Bank Overlap Limits Exceeded Due to Inadequate Procedure Guidance2024-03-18018 March 2024 (Vegp), Unit 3, Condition Prohibited by Technical Specification Limiting Condition of Operation 3.1.6 Control Bank Overlap Limits Exceeded Due to Inadequate Procedure Guidance ND-24-0059, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-03-0404 March 2024 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0693, Combined License (COL) License Condition 2.D.(4)(d) Completion of Initial Criticality and Low-Power Tests2024-02-15015 February 2024 Combined License (COL) License Condition 2.D.(4)(d) Completion of Initial Criticality and Low-Power Tests ND-23-0690, Combined License (COL) License Condition 2.D.(3)(e) Completion of Pre-Critical Tests2024-02-0808 February 2024 Combined License (COL) License Condition 2.D.(3)(e) Completion of Pre-Critical Tests ND-24-0019, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-02-0101 February 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0912, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2024-01-0202 January 2024 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0881, Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-12-0404 December 2023 Submittal of Vogtle Electric Generating Plant (Vegp), Unit 4, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0817, Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a)2023-11-17017 November 2023 Report of UFSAR Chapter 14 Changes to the Initial Test Program in Accordance with License Condition 2.D.(7)(a) ND-23-0823, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-11-0303 November 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0723, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-10-0404 October 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0697, Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-09-0505 September 2023 Submittal of Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0669, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule2023-08-0707 August 2023 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule ND-23-0205, Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests2023-07-28028 July 2023 Combined License (COL) License Condition 2.D.(5)(d) Completion of Power Ascension Tests ND-23-0608, ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72) ND-23-0618, Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797)2023-07-20020 July 2023 Resubmittal of ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.07c.ii.a (Index Number 797) ND-23-0609, Notification of Completion of All ITAAC2023-07-20020 July 2023 Notification of Completion of All ITAAC ND-23-0607, ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13) ND-22-0796, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813)2023-07-20020 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.08 (Index Number 813) ND-23-0459, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04d (Index Number 587) ND-23-0162, ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165)2023-07-19019 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.05a.i (Index Number 165) ND-23-0575, ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.01.04e (Index Number 588) ND-23-0439, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07a.i (Index Number 265) ND-23-0552, Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624)2023-07-18018 July 2023 Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Unit 4, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02c (Index Number 624) ND-23-0483, ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4)2023-07-18018 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4) ND-23-0586, ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159)2023-07-17017 July 2023 ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159) ND-23-0610, ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603)2023-07-17017 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.03.04c (Index Number 603) ND-23-0573, ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of 2.4.02.02a (Index Number 497) ND-23-0406, ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498)2023-07-16016 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.4.02.02b (Index Number 498) ND-22-0816, ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19)2023-07-15015 July 2023 ITAAC Closure Notification of Completion of ITAAC 2.1.02.05a (Index Number 19) ND-23-0603, ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 3.5.00.06 (Index Number 831) ND-23-0446, ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.12a.iii (Index Number 250) ND-23-0594, ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.05.02.ii (Index Number 629) ND-23-0601, ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.7.05.02.i (Index Number 719) ND-23-0606, ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.04.02.i (Index Number 557) ND-23-0499, ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.14 (Index Number 700) ND-23-0476, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355)2023-07-15015 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355) ND-23-0588, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78) ND-23-0121, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.07 (Index Number 667) ND-23-0122, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.08a (Index Number 668) ND-23-0597, ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.5.02.06a.ii (Index Number 530) ND-23-0002, ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270)2023-07-14014 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.05.07c (Index Number 270) ND-23-0543, ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.6.04.02a (Index Number 622) ND-23-0394, ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.02.03a (Index Number 703) ND-23-0461, ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.13a (Index Number 652) ND-22-0980, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.06.i (Index Number 75) ND-23-0111, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646) ND-23-0587, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595)2023-07-13013 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595) ND-23-0589, ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601)2023-07-12012 July 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.03.04a (Index Number 601) 2024-04-26
[Table view] Category:Report
MONTHYEARML24297A6482024-10-23023 October 2024 5 to the Updated Final Safety Analysis Report, Technical Specification Bases Changes, Technical Requirements Manual Changes, Summary Report and Revised NRC Commitments Report ML23325A2022024-01-16016 January 2024 CFR Part 52 Construction Lessons-Learned Report NL-23-0926, Correction of Technical Specification Typographical Error2024-01-12012 January 2024 Correction of Technical Specification Typographical Error ML24004A2192024-01-0808 January 2024 Construction Reactor Oversight Process Performance Metric Report for Calendar Year 2023 ND-23-0025, Compliance with Order EA-12-0492023-08-21021 August 2023 Compliance with Order EA-12-049 ML22348A0932023-07-28028 July 2023 Finding That the Acceptance Criteria in the Combined License Are Met ML22348A0882023-07-25025 July 2023 VEGP Unit 4 - 103g - Basis Document ML23184A0472023-07-0303 July 2023 Dashboard Report 7-3-2023 ML23156A1882023-06-0505 June 2023 Construction Reactor Oversight Process Resources Report June 5, 2023 ML23121A0392023-05-0101 May 2023 Dashboard Report 5-1-2023 ML23003A0412023-01-0303 January 2023 Construction Reactor Oversight Process Resources Report January 3, 2023 ND-22-0817, Enclosures 1 and 2: Proposed Alternative Inspection Requirements for Steam Generator Nozzle to Reactor Coolant Pump Casing Welds and Alternative for Use of Code Case 648-2 for Inservice Inspection2022-11-0404 November 2022 Enclosures 1 and 2: Proposed Alternative Inspection Requirements for Steam Generator Nozzle to Reactor Coolant Pump Casing Welds and Alternative for Use of Code Case 648-2 for Inservice Inspection ND-22-0831, Comments on AP1000 Standard Technical Specifications (STS) – Draft NUREG-2194, Revision 12022-10-31031 October 2022 Comments on AP1000 Standard Technical Specifications (STS) – Draft NUREG-2194, Revision 1 ML22278A0382022-10-0505 October 2022 Dashboard Report 10-5-2022 ML22215A0962022-08-0303 August 2022 Construction Reactor Oversight Process Resources Report August 3, 2022 ML20290A2762022-08-0101 August 2022 10CFR52.103(g) Basis Document ML22214A0072022-08-0101 August 2022 Archives NL-22-0510, Plants Units 1 and 2, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20212022-07-14014 July 2022 Plants Units 1 and 2, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2021 ML22179A1462022-06-15015 June 2022 Tier 1, Revision 10, Updated Through 04/22/2022 ML22159A1712022-06-0808 June 2022 Construction Reactor Oversight Process Resources Report June 8, 2022 ML22131A0502022-05-11011 May 2022 Construction Reactor Oversight Process Resources Report May 11, 2022 ML22089A0412022-03-30030 March 2022 Construction Reactor Oversight Process Resources Report March 30 2022 ND-22-0003, Report of 10 CFR 50.59 Changes, Tests, and Experiments and 10 CFR 52 Appendix D Departure Report2022-01-0606 January 2022 Report of 10 CFR 50.59 Changes, Tests, and Experiments and 10 CFR 52 Appendix D Departure Report ND-21-1003, Request for Exemption: Applicability of 10 CFR 26.3. Scope, Until Initial Fuel Load - Supplement2021-11-12012 November 2021 Request for Exemption: Applicability of 10 CFR 26.3. Scope, Until Initial Fuel Load - Supplement ND-21-0991, Exemption Request: Applicability of 10 CFR 26.3, Scope, Until Initial Fuel Load2021-11-0505 November 2021 Exemption Request: Applicability of 10 CFR 26.3, Scope, Until Initial Fuel Load ML21280A3042021-10-0707 October 2021 Q 2020 Performance Summary ML21280A3052021-10-0707 October 2021 Q/2020 Performance Summary ML21277A0762021-10-0404 October 2021 Vog 4 Dashboard 10-4-2021 ND-21-0848, Enclosure - Unit 4 Operator Candidates Requesting Credit for Unit 3 Written Examination and Operating Test (Revised)2021-10-0101 October 2021 Enclosure - Unit 4 Operator Candidates Requesting Credit for Unit 3 Written Examination and Operating Test (Revised) IR 05000424/20210052021-08-25025 August 2021 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 and 2 (Report 05000424/2021005 and 05000425/2021005) ND-21-0603, Electrical Construction and Measuring & Test Equipment Control2021-06-25025 June 2021 Electrical Construction and Measuring & Test Equipment Control ML21179A0972021-06-15015 June 2021 to Tier 1 ML21132A0482021-05-12012 May 2021 Construction Reactor Oversight Process Resources Report May 2021 ML21118A1162021-04-28028 April 2021 Emergency Response Data System (ERDS) Data Point Library for Vogtle Unit 3 ND-21-0342, Emergency Response Data System (ERDS) Data Point Library for Vogtie Unit 42021-04-28028 April 2021 Emergency Response Data System (ERDS) Data Point Library for Vogtie Unit 4 ML21090A2092021-03-31031 March 2021 Construction Reactor Oversight Process Resources Report March 2021 ML21040A1672021-02-0909 February 2021 (Vegp), Units 3 and 4, Revision to Westinghouse Non-Proprietary Technical Description of the Flaw Tolerance Evaluation Conducted on the Subject Weldolet Branch Connections ML20358A1822020-12-31031 December 2020 LTR-SDA-20-096-NP, Revision 1, Flaw Tolerance Evaluation to Assess Lack of Inspection Coverage of AP1000 14 X 4 Stainless Steel Weldolets to Pipe Welds ML20343A0672020-12-0202 December 2020 Dashboard Report 12-2-2020 ML20314A0492020-11-0909 November 2020 Construction Reactor Oversight Process Resources November 2020 ND-20-1220, Report of Changes Incorporated Into Revision 6 to the Security Plan, Training and Qualification Plan, and Safeguards Contingencv Plan2020-10-21021 October 2020 Report of Changes Incorporated Into Revision 6 to the Security Plan, Training and Qualification Plan, and Safeguards Contingencv Plan ML20287A1862020-10-13013 October 2020 Construction Reactor Oversight Process Resources October 2020 ML20274A2582020-09-10010 September 2020 Wp on Uswc for AP1000_Revised, Reactor Oversight Process Whitepaper - Modification of the Description of Unplanned Scrams with Complications Performance Indicator to Reflect AP1000 Design ML20191A3832020-08-14014 August 2020 Transition to Reactor Oversight Process for Vogtle Electric Generating Plant, Units 3 and 4 ND-20-0907, Revision to Proposed Alternative Requirements for Preservice Inspection Acceptance of Volumetric Examinations, in Accordance with 10 CFR 50.551(z)(1),(VEGP 3&4-PSI/ISI-ALT-14R1)2020-07-28028 July 2020 Revision to Proposed Alternative Requirements for Preservice Inspection Acceptance of Volumetric Examinations, in Accordance with 10 CFR 50.551(z)(1),(VEGP 3&4-PSI/ISI-ALT-14R1) ND-20-0561, Submittal of Turbine Maintenance and Inspection Program in Accordance with Updated Final Safety Analysis Report2020-07-10010 July 2020 Submittal of Turbine Maintenance and Inspection Program in Accordance with Updated Final Safety Analysis Report ML20189A4292020-07-0707 July 2020 Construction Reactor Oversight Process Resources July 2020 ML20136A4562020-04-30030 April 2020 Updated Flex Plan Nuclear Regulatory Commission Order EA-12-049 Strategies for Beyond Design Basis External Events NL-19-0832, EPRI Technical Report 3002014590, Technical Bases for Inspection Requirements for PWR Steam Generator Feedwater and Main Steam Nozzle-to-Shell Welds and Nozzle Inside Radius Sections.2019-12-31031 December 2019 EPRI Technical Report 3002014590, Technical Bases for Inspection Requirements for PWR Steam Generator Feedwater and Main Steam Nozzle-to-Shell Welds and Nozzle Inside Radius Sections. ML19284B3722019-11-15015 November 2019 Attachment - VEGP U3 Amendment 166 (LAR-19-008) 2024-10-23
[Table view] Category:Miscellaneous
MONTHYEARNL-23-0926, Correction of Technical Specification Typographical Error2024-01-12012 January 2024 Correction of Technical Specification Typographical Error ML22348A0932023-07-28028 July 2023 Finding That the Acceptance Criteria in the Combined License Are Met ML23184A0472023-07-0303 July 2023 Dashboard Report 7-3-2023 ND-22-0831, Comments on AP1000 Standard Technical Specifications (STS) – Draft NUREG-2194, Revision 12022-10-31031 October 2022 Comments on AP1000 Standard Technical Specifications (STS) – Draft NUREG-2194, Revision 1 ML22215A0962022-08-0303 August 2022 Construction Reactor Oversight Process Resources Report August 3, 2022 ML22214A0072022-08-0101 August 2022 Archives ML22131A0502022-05-11011 May 2022 Construction Reactor Oversight Process Resources Report May 11, 2022 ND-21-1003, Request for Exemption: Applicability of 10 CFR 26.3. Scope, Until Initial Fuel Load - Supplement2021-11-12012 November 2021 Request for Exemption: Applicability of 10 CFR 26.3. Scope, Until Initial Fuel Load - Supplement ND-21-0991, Exemption Request: Applicability of 10 CFR 26.3, Scope, Until Initial Fuel Load2021-11-0505 November 2021 Exemption Request: Applicability of 10 CFR 26.3, Scope, Until Initial Fuel Load ML21280A3042021-10-0707 October 2021 Q 2020 Performance Summary ML21280A3052021-10-0707 October 2021 Q/2020 Performance Summary IR 05000424/20210052021-08-25025 August 2021 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 and 2 (Report 05000424/2021005 and 05000425/2021005) ND-21-0603, Electrical Construction and Measuring & Test Equipment Control2021-06-25025 June 2021 Electrical Construction and Measuring & Test Equipment Control ML20343A0672020-12-0202 December 2020 Dashboard Report 12-2-2020 ML20314A0492020-11-0909 November 2020 Construction Reactor Oversight Process Resources November 2020 ML20287A1862020-10-13013 October 2020 Construction Reactor Oversight Process Resources October 2020 ML20191A3832020-08-14014 August 2020 Transition to Reactor Oversight Process for Vogtle Electric Generating Plant, Units 3 and 4 ND-20-0907, Revision to Proposed Alternative Requirements for Preservice Inspection Acceptance of Volumetric Examinations, in Accordance with 10 CFR 50.551(z)(1),(VEGP 3&4-PSI/ISI-ALT-14R1)2020-07-28028 July 2020 Revision to Proposed Alternative Requirements for Preservice Inspection Acceptance of Volumetric Examinations, in Accordance with 10 CFR 50.551(z)(1),(VEGP 3&4-PSI/ISI-ALT-14R1) ML19284B3722019-11-15015 November 2019 Attachment - VEGP U3 Amendment 166 (LAR-19-008) ND-18-1500, CFR 50.46 Thirty Day Report2018-12-18018 December 2018 CFR 50.46 Thirty Day Report ML18152B7852018-10-12012 October 2018 Summary of Nuclear Regulatory Commission Vendor Inspections Affecting Inspections, Tests, Analyses, and Acceptance Criteria ND-18-1047, Enclosure 2 - Redacted COL Operational Programs and Other License Conditions Implementation Schedule2018-08-0808 August 2018 Enclosure 2 - Redacted COL Operational Programs and Other License Conditions Implementation Schedule NL-18-0670, Third 10-Year Interval Inservice Inspection Program ISI Program Update: Notification of Impractical ASME Code Requirements2018-05-24024 May 2018 Third 10-Year Interval Inservice Inspection Program ISI Program Update: Notification of Impractical ASME Code Requirements NL-17-1889, NEI 12-06, Appendix H, Revision 4, H.4.5 Path 5: GMRS Greater than 2 X SSE, Mitigating Strategies Assessment (MSA) Report for the New Seismic Hazard Information2017-12-0505 December 2017 NEI 12-06, Appendix H, Revision 4, H.4.5 Path 5: GMRS Greater than 2 X SSE, Mitigating Strategies Assessment (MSA) Report for the New Seismic Hazard Information NL-17-0777, Flooding Focused Evaluation Summary Report2017-06-30030 June 2017 Flooding Focused Evaluation Summary Report NL-17-0218, Fukushima Near-Term Task Force Recommendation 2.1: Seismic Probabilistic Risk Assessment2017-03-27027 March 2017 Fukushima Near-Term Task Force Recommendation 2.1: Seismic Probabilistic Risk Assessment NL-15-2276, Submittal of 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20142015-12-23023 December 2015 Submittal of 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2014 ML15106A3102015-04-17017 April 2015 April 22, 2015, Meeting with Southern Nuclear Company, Draft Minimum Shift Staffing Analysis ND-14-2009, 4 - 10 CFR 26.719(c) Report: False Negative Results for a Blind Performance Test Sample2014-12-17017 December 2014 4 - 10 CFR 26.719(c) Report: False Negative Results for a Blind Performance Test Sample NL-14-1899, Vogle, Units 1 and 2 - 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20132014-12-0808 December 2014 Vogle, Units 1 and 2 - 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2013 ML14279A3522014-11-0606 November 2014 Staff Assessment of Response to 10 CFR 50.54(f) Information Request - Flood-Causing Mechanism Reevaluation ML14169A5992014-06-30030 June 2014 Staff Assessment of the Flooding Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-ichi Nuclear Power Plant Accident ML14049A3542014-02-24024 February 2014 Staff Assessment of the Seismic Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima DAI-ICHI Nuclear Power Plant Accident ML13162A5342013-06-10010 June 2013 Initial Exam 2013-301 Final SRO Written Exam NL-13-0173, Southern Nuclear Operating Company'S Overall Integrated Plan in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order EA-12-051)2013-02-27027 February 2013 Southern Nuclear Operating Company'S Overall Integrated Plan in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) NL-12-0324, Special Report 2011-001-02, Inoperable Radiation Monitor 1RE-00062012-02-16016 February 2012 Special Report 2011-001-02, Inoperable Radiation Monitor 1RE-0006 NL-11-0626, Special Report 2011-001-00, Inoperable Radiation Monitor 1RE-0062011-03-29029 March 2011 Special Report 2011-001-00, Inoperable Radiation Monitor 1RE-006 NL-10-1536, Special Report 2010-001-00, Inoperable Radiation Monitor 1RE-0062010-08-18018 August 2010 Special Report 2010-001-00, Inoperable Radiation Monitor 1RE-006 ML1015903342010-06-0808 June 2010 Audit of Steam Generator H Amendment Reference Documents ML1019304172010-05-0606 May 2010 Tritium Database Report ML1012704392010-05-0505 May 2010 Y020100187 - List of Historical Leaks and Spills at U.S. Commercial Nuclear Power Plants NL-09-1449, Submittal of Emergency Response Data System (Eros) Data Point Library Modification2009-09-24024 September 2009 Submittal of Emergency Response Data System (Eros) Data Point Library Modification NL-09-1375, Enclosure 2 and 3 to NL-09-1375 - Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specification (TS) Sections 5.5.9 and TS 5.6.102009-08-25025 August 2009 Enclosure 2 and 3 to NL-09-1375 - Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specification (TS) Sections 5.5.9 and TS 5.6.10 NL-08-1405, Report of Unsatisfactory Performance Testing2008-09-12012 September 2008 Report of Unsatisfactory Performance Testing NL-08-0343, Response to NRC Request for Additional Information Relating to LTR-CDME-08-11 NP-Attachment2008-03-18018 March 2008 Response to NRC Request for Additional Information Relating to LTR-CDME-08-11 NP-Attachment NL-07-1777, Supplemental Response to NRC Generic Letter 2004-022008-02-28028 February 2008 Supplemental Response to NRC Generic Letter 2004-02 NL-08-0275, Response to 01/28/2008 Request for Additional Information2008-02-27027 February 2008 Response to 01/28/2008 Request for Additional Information ML0732407392007-11-0505 November 2007 Stratigraphy and Depositional Environments of Sediments from Five Cores from Screven and Burke Counties, Georgia ML0732403812007-11-0505 November 2007 10 CFR 50.75(g) Leak/Spill Decommissioning Record, Figure 1, for 1980s and 1990s, NMP-EN-002, Version 1.0 ML0732405722007-11-0505 November 2007 Vegp Groundwater Calculation Package Addendum. 2024-01-12
[Table view] |
Text
Michael J. Yox 7825 River Road A Southern Nuclear Rs9u,ato.,Affa,rsD,rector Regulatory Al Vogtle 3 & 4 wav<<
myoxtfflsouthernco.com June 25, 2021 Docket Nos.: 52-025 ND-21-0603 52-026 10 CFR 50.55(e)
U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Units 3 and 4 Submittal of 10 CFR 50.55(e) Report Regarding Electrical Construction and Measuring & Test Equipment Control Ladies and Gentlemen:
This submittal is made with regard to the Vogtle Electric Generating Plant, Units 3 and 4 (VEGP 3&4), license numbers NPF-91 and NPF-92, pursuant to 10 CFR 50.55(e).
Southern Nuclear Operating Company(SNC) hereby submits a report in accordance with 10 CFR 50.55(e) pertaining to electrical construction and measuring & test equipment control.
This letter contains no regulatory commitments.
If there are any questions regarding this letter, please contact Steve Leighty at(706) 848-6790.
U.S. Nuclear Regulatory Commission ND-21-0603 Page 2 of 4 Respectfully submitted, Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4 Southern Nuclear Operating Company MJY/CAC/sfr
Enclosure:
10 CFR 50.55(e) Report Regarding Electrical Construction and Measuring & Test Equipment Control
U.S. Nuclear Regulatory Commission ND-21-0603 Page 3 of 4 cc:
Southern Nuclear Operating Company / Georgia Power Company Mr. S. E. Kuczynski (w/o enclosures)
Mr. P. P. Sena III (w/o enclosures)
Mr. M. D. Meier (w/o enclosures)
Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. D. L. McKlnney (w/o enclosures)
Mr. T. W. Yelverton (w/o enclosures)
Mr. B. H. Whitley Mr. W. Levis Ms. C. A. Gayheart Ms. M. Ronnlund Mr. J. M. Delano Mr. M. J. Vox Mr. C. T. Defnall Mr. J. Tupik Ms. A. C. Chamberlain Mr. S. Leighty Ms. K. Roberts Mr. J. Haswell Mr. D. T. BIythe Mr. K. Warren Mr. A. S. Parton Mr. A. Nix Nuclear Regulatory Commission Ms. A. Veil(w/o enclosures)
Mr. M. King (w/o enclosures)
Mr. G. Bowman (w/o enclosures)
Ms. M. Bailey (w/o enclosures)
Mr. G.J. Khouri Mr. G. Armstrong Mr. C. Patel Mr. C. Santos Mr. B. Kemker Mr. J. Eargle Mr. C. J. Even Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. O. Lopez-Santiago Mr. M. Webb Mr. B. Gleaves
U.S. Nuclear Regulatory Commission ND-21-0603 Page 4 of 4 Nuclear Regulatory Commission Mr. T. Fredette Ms. K. McCurry Mr. B. Davis Mr. J. Parent Mr. B. Griman Mr. P. McKenna State of Georoia Mr. R. Dunn Qqlethorpe Power Corporation Mr. M. W. Price Mr. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georoia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinohouse Electric Company. LLC Mr. L. Oriani (w/o enclosures)
Mr. T. Rubenstein (w/o enclosures)
Mr. M. Corletti Mr. D. Hawkins Mr. J. Coward Other Mr. S. W. Kline, Bechtel Power Corporation Ms. L. A. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.
Mr. S. Roetger, Georgia Public Service Commission Mr. R.L. Trokey, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham
Southern Nuclear Operating Company ND-21-0603 Enclosure 1 10 CFR 50.55(e) Report Regarding Electrical Construction and Measuring & Test Equipment Control (This Enclosure consists of 2 pages, not including this cover page)
U.S. Nuclear Regulatory Commission ND-21-0603 Page 1 of 2 (i) Name and address of the individual or individuals informing the Commission.
Michael J. Vox, 7825 River Road, Waynesboro, GA 30830 (ii) Identification of the facility, the activity, or the basic component supplied for the facility or the activity within the United States which contains a defect or fails to comply.
The activities include construction processes including, installation of some electrical and mechanical commodities, and control of measuring & test equipment at the Vogtle 3&4 construction project.
(iii) Identification of the firm constructing or manufacturing the facility or supplying the basic component which fails to comply or contains a defect.
The Vogtle 3&4 construction project primary construction firm is Bechtel Power Corporation (Bechtel).
(iv) Nature of the defect or failure to comply and the safety hazard which is created or could be created by the defect or failure to comply.
This report is being provided based on construction nonconformances including, installation of some electrical and mechanical commodities, and control of measuring & test equipment (M&TE)for Vogtle Units 3&4. The nonconformances affect cable separation and other raceway structural elements. The extent of condition for the M&TE issue is under evaluation and may impact additional safety-related work.
The identified construction nonconformances are a small fraction of the overall structures and components. There is no specifically identified substantial safety hazard (SSH)for these nonconformances. The nonconformances identified affect some safety-related components and based on this it was conservatively judged that the issues could be related to an SSH. These issues were discovered while the facility is under construction. The identified conditions will be corrected prior to completion of the facility.
(v) The date on which the information of a defect or failure to comply was obtained.
The evaluation was completed on June 24, 2021.
(vi) In the case of a basic component which contains a defect or fails to comply, the number and location of all the basic components in use at the facility subject to the regulations in this part.
As stated in the response to (iv) above, there are no specifically identified basic components that have been identified to contain a defect for Vogtle Units 3&4. The nonconformances identified affect some safety-related components and based on this it was conservatively judged that these conditions involve a failure to comply that could be related to an SSH.
U.S. Nuclear Regulatory Commission ND-21-0603 Page 2 of 2 (vii) In the case of a completed reactor manufactured under part 52 of this chapter, the entities to which the reactor was supplied.
Not applicable.
(viii) The corrective action which has been, is being, or will be taken; the name of the individual or organization responsible for the action; and the length of time that has been or will be taken to complete the action.
Comprehensive extent-of-condition reviews and correction of identified conditions are being conducted. The actions to identify and resolve the nonconforming conditions are in process and will be completed in accordance with the site corrective action program. Bechtel, and other subcontractors as needed, will implement actions to correct the identified conditions and ensure that processes are in place to avoid future occurrences. Southern Nuclear Operating Company(SNC)is the organization responsible for ensuring Bechtel and the other subcontractors complete the required actions to correct the nonconforming conditions and ensuring that processes are in place to avoid future occurrences.
(ix) Any advice related to the defect or failure to comply about the facility, activity, or basic component that has been, is being, or will be given to other entities.
None.