St. Lucie Plant, Units 1 and 2 Subsequent License Renewal Application (SLRA)

Safety Pre-Application Meeting April 21, 2021 Hector Rodriguez-Luccioni Safety Project Manager License Renewal Projects Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation

Meeting Agenda

Inputs into NRC Licensing Decision

  • Safety Review:

o Process Overview o Tentative Review Schedule for St. Lucie

  • NRC Contact Information
  • Conclusion / Questions 2

Subsequent License Renewal Review Process +

Inputs into NRC Licensing Decision Environmental Review (10 CFR 51)

Subsequent License NRC Renewal Renewal Application Hearings* Decision (SLRA) Accepted 10 CFR 2 (10 CFR 54.29)

Safety ACRS Review Recommendation (10 CFR 54) (10 CFR 54.25) 3

Safety Review:

Process Overview Acceptance Review In-Office Technical Review On-Site Audit Breakout Audit Audit Issue Safety Evaluation Report (SER) 4

St. Lucie: Tentative Safety Review Schedule Note: The review schedule below is tentative and subject to change.

The schedule is only finalized once the application has been accepted forreview and docketing.

Activity Estimated Date Application Submission Date August 03, 2021 Acceptance Date (Project Start Date) September 17, 2021 In-Office Technical Review Audit September/October 2021 On-Site Audit October 2021 Breakout Audit November/December 2021 Safety Evaluation Report October 2022 Advisory Committee on Reactor Safeguards December 2022 (ACRS) Full Committee Meeting Licensing Decision March 2023 5

NRC Contact Information Safety Project Managers

Safety Branch Chief

Environmental Project Manger

Environmental Branch Chief

Questions?