ML21090A173

From kanterella
Jump to navigation Jump to search
Slides: Cimarron Environmental Response Trust - Facility Decommissioning Plan, Rev. 2
ML21090A173
Person / Time
Site: 07000925
Issue date: 03/24/2021
From:
Cimarron Environmental Response Trust
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
Shared Package
ML21091A190 List:
References
Download: ML21090A173 (28)


Text

CIMARRON ENVIRONMENTAL RESPONSE TRUST Facility Decommissioning Plan - Rev 2 DP SECTION 8-PLANNED DECOMMISSIONING ACTIVITIES DP SECTION 12 - ENVIRONMENTAL MONITORING & CONTROL DP SECTION 9 - SCHEDULE DP SECTION 16 - FINANCIAL ASSURANCE Note: Information provided herein consists of partial or incomplete images and information taken from multiple other data sources. It is provided for summary purposes only and should not be relied upon as technically complete or comprehensive.

March 24, 2021

DP Section 8 - Planned Decommissioning Activities 8.1-Overview 8.6 - In-Process Monitoring 8.2 - Groundwater Extraction 8.7 - Waste Management 8.3 - Water Treatment 8.8 - Post-Remediation Monitoring 8.4 - Treated Water Injection 8.9 - Demobilization 8.5 - Treated Water Discharge 8.10- Ongoing Remediation

8.1 - Groundwater Remediation Overview 3

Phase I

  • Only recover groundwater from areas in which U > DCGL.
  • Maintain separate injection for BAt and WA treated water.
  • Phase I ends when all wells yield uranium < DCGL.

Phase II - dependent on remaining funding

  • Options - Stop operating, continue with existing systems, or add infrastructure and expand operations.
  • Operations cease and post-remediation monitoring begins when funding dictates.

From DP Figure 8-2(a)

BA1-C U < DCGL Alluvium j WAA U > DCGL Alluvium BA1-B U > DCGL Alluvium 1206-NORTH Sediment GETR-VWJ-02 I BA1-A U > dcgl ISSB & TZ WU-BA3 Sandstone A Groundwater Extraction

\\

From DP Figure 8-1(a)

WATF ft

5 8.2.4 - 1206-NORTH Remediation WA EXTRACTION REDUCTION-S'TO 2" GETR-WU-02 (BEGIN TRENCH)

GE-WAA-03

-HOPE REDUCTION X4-T0 2" HOPE REDUCTION 6* TO 4*

GE-WAA-06 ->

2 HD PE g £-WAA-11 TREATMENT DISCHARGE JTO OUTFALL 001)'

/' s GETR-WU-02 /

^(END TRENCH) /

EX.OVERHEAC POWER UNES

'(APPROX.)

  • vX. '

GVM- -

UP1-02 1

GW-UP1-03

)

(BEGIN)

GVM-UP2-01A *

(BEGIN TRENCH) 120^bRAJNAGE

'AREAS-SEE SHEETC011 FOR REMEDIATION PLAN PHASE I INCLUDES GROUNDWATER CONVEYANCE PIPING AND FIBER OPTIC LINE

.GWI-UP2-04B (END TRENCH GW1-UP2-01 GWI-UP2-04A SEE NOTE 7 GWI-UP1-04 (BEGIN)

I/VI-UP1-04A GW-UP2-GVM-UP2-01 /

(END TRENCH) -J GVU-UP2-01D

^ FUTURE'Sv^RHEAD ELECTRIC (BY

^UTILITY, SEE NOTES 2&3)

' /GW-UP2-04' ^

//(BEGIN TRENCH)'

UPDATED' TOPOGRAPHIC SURVEY LIMITS (SEE NOTE 2)

I till r MIX EXCAVATED 1206' DRAINAGE SEDIMENT-MATERIAL WITH EXCESS I TRENCH MATERIAL AND1 SPREAD WITHIN AREA INDICATED.

- INSTALL TRACER WIRE IN TRENCH WHERE NO

/INSTRUMENTATION OR

, POWER CABLE IS PRESENT DO NOT DISTURB EX.

UNKNOWN PIPE SEE SHEET M102 FOft 1

'*-.TYPICAL INJECTION WELL

. DETAILS (ASSEMBLY

) APPLIES TO ALL

' Injectio n wells

)-----------

Ij /

) )!

(BEGIN TRENCH)

EXISTING CONTAINMENT

.CELL----- s.

FORMER PHASE I INCLUDES 3* WATER FIBER OPTIC AND SUPPLY PIPE POTABLE WATER

\\

/

PIPING,

/

10* OG&E EASEMENT HUM POND 2 (END TRENCH)\\

EXISTING POND EXTRACTION^

/ >P WA TREATMENT

"'ll'"

/

FACILITY (SEE

< J SHEETS C006 &

ROAD IMPROVEMENTS,

/C007)

.SEE SHEET C108 FORPETAILS A. ^

INSTALL TRUNK LINE

^ ^

CLEANOUT, TYP. (SEE SHEET C108 FOR DETAILS)

From DP Appendix I-2 Drawing C-004 7T HDPE 1A,getr

-vaj -oT\\.

V (BEGIN TRENCH)

INSTALL 20 LF X201 W 050=12" RIPRAP CENTERED OVER TRENCH

8.3 - Water Treatment WATF Building Layout 6

8.3 - Water Treatment WATF Office Area 7

8.3 - Water Treatment Uranium Removal 8

From Appendix J-4 Drawing G-121

12 8.6 - In-Process Monitoring Process Sampled Material pH U-235 &

U-238 Nitrate Fluoride Tc-99 Ion Exchange Skid for Western Area Groundwater WA Train Influent (pre-acid addition)

X X

X X

X WA Train Influent (post-acid addition)

X WA Train Lead Vessel Effluent First Cycle X

X Second Cycle X

X Third Cycle X

X WA Train Lag Vessel Effluent First Cycle X

X Second Cycle X

X Third Cycle X

X W

Ef A Train Polish Vessel fluent First Cycle X

X X

X From DP

' Table 8-4 Second Cycle X

X X

X Third Cvcle X

X X

X B/

B/

\\ Train Influent (pre-acid addition)

\\ Train Influent (post-acid addition)

X X X

X X

X Ion Exchange Skid for BA1 Groundwater B>\\ Train Lead Vessel Effluent First Cycle X

X Second Cycle X

X Third Cycle X

X By^ Train Lag Vessel Effluent First Cycle X

X Second Cycle X

X Third Cycle X

X By\\ Train Polish Vessel Effluent First Cycle X

X X

X Second Cycle X

X X

X Third Cycle X

X X

X Effluent wATF Effluent in Tank 102*

X X

X X

X

8.6 - In-Process Monitoring 13 Process Sampled Material Flow PH Ion Exchange Skids WA Influent (pre-acidification)

X WA Influent (post-acidification)

X X

From DP Table 8-3 BA1 Influent (pre-acidification)

. X BA1 Influent (post-acidification)

X X

Discharge Outfall 001 X

Location Sample ID Flow pH U-235 &

U-238 Nitrate Fluoride Combined Discharge Outfall 001 X

X X

X X

BA1 Injection GWI-BA1-01A X

GWI-BA1-02A X

From DP Table £i-5 GWI-BA1-03A X

Composite X

X X

X WA Injection GWI-WU-01A X

X X

X X

Resin Mixture from BA1 Ion Exchange Skid From DP Table 8-6 Resin Mixture from WA Ion Exchange Skid 2nd Batch of Spent Resin 1st Batch of Spent Resin 2nd Batch of Spent Resin BA1-02-01 BA1-l)2-02 BA1-02-XX WA1-01-01 WA1-01-02 i

WA1-01-XX WA1-02-01 WA1-02-02 I

WA1-02-XX

^ote. Once homogeneity of uranium in processed resin has been established, one sample per resin vessel will suffice for waste characterization.

Note:

Filtered sediment is delivered with filter backwash to the effluent tank for discharge.

Ion Exchange Skids lE>l E>

From Appendix J-2 Drawing G-100

1. Sampled - Awaiting Data
2. Accepted - Needs Manifesting

[3. Ready to be Shipped

4. Needs to be Re-Processed

. ISI,c D

^ir


f pf (10-) \\V

---(24') tn

From DP Figure 8-11 10 Locations l lpFrom DP Figure 8-10

! *lf~ 9 Locations 02 wiz

8.9 - Demobilization &

8.10 - Ongoing Remediation 16 Demobilization

  • Release Surveys
  • Equipment May or May Not be Removed
  • Removal is not Included in Cost Estimates Ongoing Remediation
  • Dependent Upon Remaining Funding
  • Determination Made by EPM & Beneficiaries

DP Section 12 - Environmental Monitoring & Control Environmental Monitoring

  • In-process groundwater monitoring replaces RPP Section 15 Effluent Monitoring
  • Potential for air effluents addressed by air sampling during resin processing
  • Discharge monitoring per OPDES Permit
  • Injection monitoring per Underground Injection Control Program Stormwater Control
  • During Construction
  • During Operations

DP Section 12 - Environmental Monitoring & Contrif Stormwater Control

19 DP Section 9 - Schedule &

DP Section 16 - Financial Assurance Presented by Phase

  • Pre-Construction
  • Construction
  • Remediation
  • Post-Remediation

Pre-Construction Schedule (Summarized from DP Figure 9-1) 20 Activity 2021 2022 2023 Q1 J F M Q2 A M J Q3 J A S Q4 0 N D Q1 J F M Q2 A M J Q3 J A S Q4 0 N D Q1 J F M Q2 A M J Submit Decommissioning Plan Review Decommissioning Plan Issue RAIs Respond to RAIs Prepare EA, SER Review Draft License Issue Amended License Finalize Drawings & Specifications Prepare and Issue Requests for Bids Receive & Evaluate Bids Pepare Construction Funding Request Agencies RevieWApprove Funding Obtain Best & Final Bids Execute Contracts

21 Pre-Construction Costs (Summarized from DP Table 16-1)

Description 2021 2022 Q1-Q2 2023 Administration Total

$216,000

$216,000

$108,000 License Compliance EPM

$160,000

$160,000

$80,000 Enercon

$327,924

$377,113

$188,556 Burns & McDonnell

$100,000

$80,000

$40,000 Annual Environmental

$14,800

$14,800

$14,800 Total

$602,724

$631,913

$323,356 Federal Agency Fees Total

$800,000

$800,000

$400,000 Decommissioning EPM

$120,000

$120,000

$60,000 Burns & McDonnell

$1,030,000

$630,000

$230,000 Enercon

$205,391

$236,200

$118,100 Veolia

$668,462

$542,640

$243,000 Total

$2,023,853

$1,528,840

$651,100 State Agency Fees Total

$36,000

$36,000

$18,000 Total. Preconstruction Phase Costs $3,678,577

$3,212,753

$1,500,456

Construction Schedule (Summarized from Figure 9-2)

Activity 2023 2024 Q2 Q3 Q4 Q1 Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Mobilize, Clear & Grub, Install BMPs Install Extraction Wells & Trenches Install Injection Wells & Trenches Excavate & Backfill 1206 Drainage Install Utilities, Discharge, & Outfall Grading for WATF, BA1 Facilities Construct WATF Building Install Treatment & Waste Processing Systems Construct BA1 Facilities Install Electric, Water, and Communications Startup and Commisison Note: Start and Finish Times are Approximate and Are Intended to Show Sequencing of Tasks

Construction Costs (Summarized from DP Table 16-2)

Description Q3-Q4 2023 Q12024 f

Administration Total

$108,000

$54,000 License Compliance EPM

$100,000

$50,000 Enercon

$326,812

$163,406 Burns & McDonnell

$40,000

$20,000 Total

$466,812

$233,406 Federal Agency Fees Total

$150,000

$75,000 Decommissioning EPM Support

$70,000

$35,000 Enercon Support

$118,100

$59,050 Veolia Support (includes startup)

$415,000

$142,000 Burns & McDonnell Support (includes startup)

$70,000

$283,590 Total Contractor Support Cost

$673,100

$519,640 Site Civil (includes BA1 and WATF civil)

$1,849,500

$3,590,205 Site Electrical and Controls

$366,520

$711,480 Burial Area #1 Facility

$240,058

$123,666 Western Area Treatment Facility

$4,650,028

$1,343,192 Direct Capital Costs

$7,106,106

$5,768,543 Indirect Capital Costs (Direct Costs X 36%)

$2,559,137

$2,076,990 Total Decommissioning Cost

$10,338,343

$8,365,173 State Agency Fees Total

$16,000

$8,000 Total Construction Phase Costs

$11,079,155

$8,735,579

Remediation Costs (Summarized) 25 Description Q2-Q4 2024 2025 2026-2034 2035 Q1-Q3 2036 Average Total Administration EPM Support

$135,000

$180,000

$180,000

$1,620,000

$180,000

$135,000 Other Costs

$27,000

$36,000

$36,000

$324,000

$36,000

$27,000 Total

$162,000

$216,000

$216,000

$1,944,000

$216,000

$162,000 License Com iliance EPM Support

$150,000

$170,000

$160,000

$1,440,000

$160,000

$120,000 Enercon Support

$477,298

$636,397

$636,397

$5,727,570

$636,397

$477,298 Bums & McDonnell Support

$60,000

$80,000

$80,000

$720,000

$80,000

$60,000 Total

$687,298

$886,397

$876,397

$7,887,570

$876,397

$657,298 NRC Fees

$300,000

$280,000

$240,000

$2,160,000

$240,000

$180,000 Decommiss oning EPM Support

$105,000

$125,000

$120,000

$1,080,000

$120,000

$90,000 Remediation Operations

$733,676

$964,121

$964,010

$8,676,094

$962,794

$722,908 Resin & Resin Disposal

$223,246

$223,246

$180,179

$1,621,610

$199,751

$99,094 Total

$1,061,922

$1,312,367

$1,264,189

$11,377,704

$1,282,545

$912,002 State Agency Fees

$27,000

$36,000

$36,000

$324}000

$36,000

$27,000 Total Remediation Phase Costs $2,238,220

$2,730,764

$2,632,586 $23,693,274

$2,650,942

$1,938,299

Post-Remediation Schedule (Summarized from DP Figure 9-4) 26 Activity 2036 2037 2038 2039 2040 Q4 O N D Q1 J F Ml Q2 A Ml J Q3 J A S Q4 0 N D Q1 J F M Q2 A M J Q3 J A S Q4 O N D Q1 Q2 Q3 jfm lamj ljas Q4 0 N D Q1 J F M Q2 A M J Q3 J A S BA1 Post-Remediation Groundwater Monitoring WA Post-Remediation Groundwater Monitoring Prepare & Submit Final Status Survey Plan Agency Review Final Status Survey Plan Rnalize Final Status Survey Plan Release & Demobilize Equipment Perform Final Status Survey Prepare and Submit Final Status Survey Report Revise Dose Model and Apply for Termination NRC Reviews Application for Termination License T ermination

27 Post-Remediation & Life-Cycle Costs (Summarized from DP Table 16-3)

Description Q4 2036 2037 2038 Q1-Q3 2039 Q4 2039 Q1-Q3 2040 Life of Project Subtotal/Total Administration EPM Fee

$45,000

$180,000

$180,000

$135,000

$45,000

$135,000

$4,266,000 Outside Services - BMcD, legal support

$5,000

$20,000

$20,000

$15,000

$5,000

$15,000 Other Direct Costs

$4,000

$16,000

$16,000

$12,000

$4,000

$12,000 Total

$54,000

$216,000

$216,000

$162,000

$54,000

$162,000 License Compliance EPM

$50,000

$200,000

$200,000

$150,000

$25,000

$75,000

$15,414,866 Enercon

$81,981

$327,924

$327,924

$245,943

$81,981

$245,943 Burns & McDonnell

$10,000

$40,000

$40,000

$20,000

$10,000

$30,000 Total

$141,981

$567,924

$567,924

$415,943

$116,981

$350,943 NRC Fees

$50,0001

$200,000

$200,000 \\

$150,0001

$60,000 \\

$180,0001l

$6,225,000 Decommissioning EPM Support

$35,000

$140,000

$140,000

$105,000

$25,000

$75,000

$39,941,980 Maintenance Allowance

$20,000

$80,000

$80,000

$60,000

$20,000

$60,000 Post-Remediation Groundwater Monitoring

$5,275

$21,100

$21,100

$15,825 Final Status Survey Plan

$21,995

$7,332 Final Status Survey

$14,600

$43,801 Final Status Survey Report

$28,801

$9,600 License Termination

$58,701 Total

$60,275

$263,095

$263,032

$253,427

$54,600

$193,701 State Agency Fees

$8,000

$32,000

$32,000

$24,000

$10,000

$30,0001l

$700,000 Total Post-Remediation Phase Costs

$314,256

$1,279,019

$1,278,956

$1,005,370

$295,581

$916,644

$66,547,846

66SNOIlS3nO 83