March 12, 2021 MEMORANDUM TO: Louise Lund, Director Division of Engineering Office of Nuclear Regulatory Research FROM: Meraj Rahimi, Branch Chief /RA/
Division of Engineering Office of Nuclear Regulatory Research
SUBJECT:
RESULTS OF PERIODIC REVIEW OF REGULATORY GUIDE 1.102, Revision 1, FLOOD PROTECTION FOR NUCLEAR POWER PLANTS The Office of Nuclear Regulatory Research and the Office of Nuclear Reactor Regulation staff have reviewed Revision 1 of Regulatory Guide (RG) 1.102, Flood Protection for Nuclear Power Plants. As discussed in Management Directive 6.6, Regulatory Guides, the NRC staff reviews RGs approximately every 10 years to ensure that the RGs continue to provide useful guidance. The results of the staffs review of RG 1.102, Revision 1, are summarized in the enclosed document.
Based on the results of the periodic review, the staff concludes that revision of RG 1.102 is warranted. Flood protection features and procedures for civil infrastructure have evolved considerably since the current revision of RG 1.102 was issued in 1976. Perception of the risk that external flooding may pose to nuclear power plants has also evolved considerably during this time frame based on operational experience of flooding events at several nuclear power plants. In addition, proposed nuclear power plant designs, as well as potential applications and siting locations are rapidly evolving away from large light-water reactors (e.g. small modular reactors, micro reactors, non-light-water reactors). These issues warrant revising RG 1.102, Revision 1.
Any questions should be directed to the contacts listed in this memorandum.
Enclosure:
Periodic Review of RG 1.102, Revision 1 (ML21068A405)
CONTACTS:
Joseph Kanney Kenneth See Edward ODonnell RES/DRA/FXHAB NRR/DE/EXHB RES/DE/RGGIB 301-415-1920 301-415-1508 301-415-3317
L. Lund 2
SUBJECT:
RESULTS OF PERIODIC REVIEW OF REGULATORY GUIDE 1.102, FLOOD PROTECTION FOR NUCLEAR POWER PLANTS March 12, 2021 DISTRIBUTION:
K. See, NRR/DE J. Kanney, RES/DRA ADAMS ACCESSION NO: Package: ML21068A403 Memo: ML21068A404, Periodic Review of RG: 1.102: ML21068A405 OFFICE NRR/DE/EXHB RES/DRA/FXHAB RES/DE/RGGIB RES/DE/RGGIB NAME B. Hayes* MH. Salley* E. ODonnell* M. Rahimi*
DATE 03/09 /2021 03/09/2021 3/12/2021 3/12/2021