Text
NRC FORM 898 (01-2021)
Topical Report Completeness Determination U.S. NUCLEAR REGULATORY COMMISSION NRC FORM 898 (01-2021)
Page 1 of 2 Topical Report Information Report Number:
NEDO-33914, Revision 0
Title:
BWRX-300 Advanced Civil Construction and Design Approach ADAMS Accession Number:
ML21020A137 EPID:
L-2021-TOP-0002 Docket Number:
99900003 Review Information Office/Division/
Branch:
NRR/DEX/ESEB (Lead Branch); NRR/DEX/
EXHB; NRR/DRA/ARCB Project Manager:
James Shea Alina Schiller Reviewers:
Amitava Ghosh, et al Review Type:
Standard
Compressed ADAMS Accession Numbers (Top row is for transmittal of this form)
Package: ML21048A245 E-mail: ML21048A244 This Form: ML21048A243 Withholding Determination: ML N/A Fee Waiver: ML N/A Topical Reports for Review
The NRC staff has performed an acceptance review of the subject topical report. We have found that the material presented is sufficient to begin our review. The dates below are based on current resources, if they change the NRC staff will contact you.
Information for Topical Reports That Are Found Acceptable for Review Issue Dates For Requests for Additional Information: 07/30/2021 Issue Dates For Draft Safety Evaluation: 12/23/2021 Review hours total includes project management and contractor time:
1,100 Topical Reports Not Acceptable for Review Based on its review of the information provided, the NRC staff cannot find sufficient details in the submittal to allow the staff to evaluate the proposed topical report.
[Only for Use with Topical Reports in Standard Review Process] Although the NRC staff has found the current topical report is not sufficiently detailed to begin our review, the sponsor can supplement the submittal with additional information. The additional information should be submitted within 60 days the date of this form.
Basis for Nonacceptance:
Additional Information Needed:
NRC FORM 898 (01-2021)
Topical Report Completeness Determination U.S. NUCLEAR REGULATORY COMMISSION NRC FORM 898 (01-2021)
Page 2 of 2 Approvals Technical Branch Chief Projects Branch Chief Joseph Colaccino Digitally signed by Joseph Colaccino Date: 2021.02.26 12:18:48 -05'00' Michael I. Dudek Digitally signed by Michael I. Dudek Date: 2021.03.01 14:09:54 -05'00'