MONTHYEARML20141L6202020-05-22022 May 2020 Request for Withholding Information from Public Disclosure in Holtec International March 19, 2020, Submittal of Thermal Topical Report on the HI-STORM 100 and HI-STORM FW Systems Project stage: Withholding Request Acceptance ML20141L6212020-05-22022 May 2020 Acceptance for Review of Holtec International Thermal Topical Report on the HI-STORM 100 and HI-STORM Systems Project stage: Acceptance Review ML20202A6582020-06-29029 June 2020, 17 July 2020 July 17, 2020 Holtec Topical Report Review Public Meeting Project stage: Request ML20244A0232020-09-0101 September 2020 September 9, 2020 - Regulatory Audit Plan for Holtec International (Holtec) Topical Report for Allowance of Heat Load Patterns in Hi-Storm 100 and Hi-Storm FW Systems (EPID L-2020-TOP-0018) Ltr Project stage: Other ML20282A5252020-11-0202 November 2020, 3 November 2020 Audit Report Regarding the September 9, 2020, Regulatory Audit for Holtec International Topical Report for Allowance of Heat Load Patterns in Hi-Storm 100 and Hi-StormFW Systems Project stage: Request ML20282A5262020-11-0202 November 2020 Transmittal Letter for Audit Report Regarding the September 9, 2020, Regulatory Audit for Holtec International Topical Report for Allowance of Heat Load Patterns in Hi-Storm 100 and Hi-Storm FW Systems Project stage: Other ML20282A5272020-11-0303 November 2020 Audit Report Regarding the September 9, 2020, Regulatory Audit for Holtec International Topical Report for Allowance of Heat Load Patterns in Hi-Storm 100 and Hi-StormFW Systems (EPID: L-2020-TOP-0018)(Non-Proprietary) Project stage: Other ML21034A5962021-02-17017 February 2021 Transmittal of Draft Safety Evaluation for Holtec International Topical Report HI220034, Topical Report for Allowance of Heat Load Patterns in HI-STORM 100 and HI-STORM FW Systems Project stage: Draft Approval PMNS20210234, Closed Meeting with Holtec International (Holtec) and the U.S. Nuclearregulatory Commission (NRC) Regarding Topical Report for Allowance of Heat Load Patterns in Hi-Storm 100 and Hi-Storm FW Systems2021-02-26026 February 2021 Closed Meeting with Holtec International (Holtec) and the U.S. Nuclearregulatory Commission (NRC) Regarding Topical Report for Allowance of Heat Load Patterns in Hi-Storm 100 and Hi-Storm FW Systems Project stage: Request ML21092A1652021-04-0202 April 2021 Attachment 3: Responses to NRC Staffs Open Items Project stage: Request ML21092A1622021-04-0202 April 2021 Submittal of Holtec Proprietary Information Review and Response to Open Items on the Thermal Topical Report on the HI-STORM 100 and HI-STORM FW Systems Project stage: Request ML21082A0852021-04-0909 April 2021 Summary of Closed Meeting with Holtec International and U.S. Nuclear Regulatory Commission Regarding Topical Report for Allowance of Heat Load Patterns in Hi-Storm 100 and Hi-Storm FW Systems Project stage: Meeting ML21125A1862021-09-14014 September 2021 Final Safety Evaluation for Holtec International Topical Report HI-2200343 Revision 2, Topical Report for Allowance of Heat Load Patterns in HI-STORM 100 and Hi STORM FW Systems Project stage: Request ML21125A1912021-09-14014 September 2021 Transmittal Letter U.S. NRC Final Safety Evaluation for Holtec International Topical Report HI-2200343 Revision 2, Topical Report for Allowance of Heat Load Patterns in HI-STORM 100 and Hi STORM FW Systems Project stage: Approval ML21216A1812021-09-14014 September 2021 Non-Proprietary Enclosure 1 U.S. NRC Final Safety Evaluation for Holtec International Topical Report HI-2200343 Revision 2, Topical Report for Allowance of Heat Load Patterns in HI-STORM 100 and Hi STORM FW Systems Project stage: Approval ML21302A1482021-09-29029 September 2021 Attachment 3: Affidavit Pursuant to 10CFR2.390 Project stage: Other ML21302A1452021-09-29029 September 2021 Submittal of Topical Report HI-200343 - a Version Project stage: Other ML21302A1472021-10-29029 October 2021 Attachment 2: HI-2200343-A Topical Report for Allowance of Heat Load Patterns in HI-STORM and HI-STORM FW Systems (Non-Proprietary Version) Project stage: Other ML21336A4582021-12-16016 December 2021 NRC 896 Form for the U.S. Nuclear Regulatory Commission Staff -A Verification of the HI-2200343, Rev 2, Topical Report for Allowance of Heat Load Patterns in HI-STORM 100 and HI-STORM FW (Flood Wind) Systems Project stage: Other ML21336A4502021-12-17017 December 2021 Transmittal Email of NRC 896 Form for U.S. Nuclear Regulatory Commission Staff -A Verification of the HI-2200343, Rev 2, Topical Report for Allowance of Heat Load Patterns in HI-STORM 100 and Hi STORM FW (Flood Wind) Systems Project stage: Other 2021-12-16
[Table View] |
Text
From:
Perkins, Leslie To:
Debu Majumdar Cc:
Bajwa, Chris; Piotter, Jason
Subject:
DRAFT SAFETY EVALUATION FOR HOLTEC INTERNATIONLTOPICAL REPORT HI-2200343, TOPICAL REPORT FOR ALLOWANCE OF HEAT LOAD PATTERNS IN HI-STORM 100 AND HI-STORM FW SYSTEMS Date:
Wednesday, February 17, 2021 1:32:00 PM
Dear Dr. Mitra-Majumdar,
By letter dated March 19, 2020 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML20101N174), Holtec International (Holtec) submitted for U.S. Nuclear Regulatory Commission (NRC) staff review the Topical Report (TR) HI-2200343 Revision 0, Topical Report for Allowance of Heat Load Patterns in HI-STORM 100 and HISTORM FW Systems.
A copy of the draft safety evaluation (SE) with open items has been placed in the box.com folder. Holtec has been given access to the folder. The draft SE is being provided for proprietary information review and for Holtec to provide responses to the NRC staffs open items. If Holtec provides comments on other areas, the NRC staff will exercise its discretion on whether to address those comments.
Pursuant to Section 2.390 of Title 10 of the Code of Federal Regulations (10 CFR), we have determined that the draft SE may contain proprietary information. If you believe that any information in the draft SE is proprietary, please identify such information line-by-line and define the basis pursuant to the criteria of 10 CFR 2.390. Use double brackets and yellow highlight to identify any ((proprietary information)). After 10 working days, the draft SE will be made publicly available, if appropriate.
Your response must be via a letter from an authorized individual. In addition, please provide an electronic redline/strikeout Word version of the SE either via email or the box.com folder. It helps expedite the NRC staff response to comments if Holtec provides in the formal transmittal and in a separate Word file, a table with the following columns; Comment No., PageNo., and Line No., Comment Type (if comments other than proprietary information are provided (i.e.,clarity, accuracy)), Suggested Revision, and a blank column NRC Disposition. However, Holtec may provide its comments in any format it chooses.
The final SE will be issued after making any necessary changes.
Note that at this stage of the process, the NRC staff has completed its review of the submitted information and will only entertain technical discussions regarding the open items identified in the draft SE. The staff conclusions and conditions will not change unless new information is provided that was not available during our review. If Holtec would like to discuss the draft SE in detail, we can do that in a noticed meeting that can be closed if proprietary information will be discussed.
Both this email and the draft SE have been placed in ADAMS and made Official Agency Records. The draft SE is declared as nonpublic because it may contain proprietary information. This email is declared public.
If you have any questions, please feel free to contact me at 301-415-2375 or by email at Leslie.Perkins@nrc.gov.
Sincerely, Leslie Perkins Project Manager, Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation e-mail: Leslie.Perkins@nrc.gov Phone: 301-415-2375