Letter Sequence Other |
|---|
|
Administration
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
|
MONTHYEARML20322A3202020-10-31031 October 2020 Materials Reliability Program: Functionality Analysis for Babcock & Wilcox Representative PWR Internals (MRP-229, Revision 4) NON-PROPRIETARY Project stage: Request ML20322A3212020-11-17017 November 2020 Transmittal Letter for Topical Report MRP-229, Revision 4 Project stage: Request ML21006A0102021-01-0606 January 2021 Transmittal Email for Withholding Determination of MRP-229, Rev 4 Project stage: Other ML21006A0112021-01-0606 January 2021 NRC 897 Withholding Determination for MRP-229 Rev 4 Project stage: Other ML21006A0202021-02-11011 February 2021 Summary of Meeting Between the U.S. Nuclear Regulatory Commission Staff and the Electric Power Research Institute to Discuss MRP-230, Revision 3 Project stage: Meeting ML21049A0692021-02-18018 February 2021 NRC Staff Withholding Determination for Feb 23, 2021 Meeting on MRP-229, Rev 4 Project stage: Meeting ML21019A0062021-02-18018 February 2021 NRC Form 897 for Withholding Determination for MRP-228, Rev 4 Project stage: Other ML21019A0072021-02-18018 February 2021 Transmittal Email for Withholding Determination for MRP-228, Rev 4 Project stage: Other ML21049A0682021-02-18018 February 2021 NRC Form 897, Withholding Determination EPRI Presentations for Feb 23 2021 Meeting on MRP 229 Rev 4 Project stage: Meeting ML21007A0092021-03-0101 March 2021 Summary of Meeting Between the U.S. Nuclear Regulatory Commission Staff and the Electric Power Research Institute to Discuss MRP-229, Revision 4 (L-2020-PPM-0002) Project stage: Meeting PMNS20210898, Meeting Between the NRC Staff and Electric Power Research Institute2021-07-0808 July 2021 Meeting Between the NRC Staff and Electric Power Research Institute Project stage: Request ML21224A0062021-08-12012 August 2021 NRC 897, Withholding Determination for EPRI Aug 12 2021 Meeting Slides Project stage: Meeting ML21224A0072021-08-12012 August 2021 Transmittal Email for EPRI Aug 12 2021 Meeting Slides Withholding Determination Project stage: Meeting ML21189A0142021-09-10010 September 2021 Summary of August 12, 2021 MRP232 Rev 2 EPRI Meeting with U. S. Nuclear Regulatory Commission Project stage: Meeting ML21285A0232021-10-12012 October 2021 Meeting Attendees for October 12, 2021, Information Exchange on Materials Reliability Program: Aging Management Strategies for B&W Pressurized Water Reactor Internals (MRP-231, Rev. 4) Project stage: Meeting ML21285A1782021-11-0101 November 2021 NRC Form 897, Withholding Determination for MRP-231, Rev. 4 October 12, 2021, Meeting Slides Project stage: Meeting ML21285A1772021-11-0101 November 2021 Transmittal Email for NRC Form 897, Withholding Determination for MRP-231, Rev. 4 October 12, 2021, Meeting Slides Project stage: Meeting ML21285A0222021-11-0303 November 2021 Summary of October 12, 2021, Meeting Between the U.S. Nuclear Regulatory Commission Staff and the Electric Power Research Institute to Discuss MRP-231 Revision 4 Project stage: Meeting 2021-11-03
[Table View] |
Text
NRC FORM 897 (12-2020)
Topical Report Withholding Determination U.S. NUCLEAR REGULATORY COMMISSION NRC FORM 897 (12-2020)
Page 1 of 1 Topical Report Information Report Number:
MRP-229, Rev 4
Title:
Materials Reliability Program: Functionality Analysis for Babcock & Wilcox Representative PWR Internals ADAMS Accession Number:
ML20322A319 EPID:
L-2020-PPM-0002 Docket Number:
99902021 Review Information Office/Division/
Branch:
NRR/DNRL/NVIB Project Manager:
J. Holonich Reviewers:
Staff Withholding Determination
The NRC staff has reviewed your application and the material in accordance with the requirements of 10 CFR 2.390.
Based on the statements in the affidavit, the NRC staff has determined that the submitted information contains proprietary, commercial information and should be withheld from public disclosure.
Therefore, the submitted information marked as proprietary will be withheld from public disclosure under 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
The NRC staff has reviewed your application and the material in accordance with the requirements of 10 CFR 2.390.
Based on our review, we have concluded that the proprietary request does not comply with the requirements of 10 CFR 2.390. Therefore, the NRC staff is denying the request to withhold the information under 10 CFR 2.390.
ADAMS Accession Numbers (Top row is for transmittal of this form)
Package: ML21006A009 E-mail: ML21006A010 This Form: ML21006A011 Incoming Letter: ML20322A321 Nonproprietary Version: ML20322A320 Basis for Denial:
Approvals Technical Branch Projects Manager Ganesh S. Cheruvenki Digitally signed by Ganesh S. Cheruvenki Date: 2021.01.06 09:30:24 -05'00' Joseph J. Holonich Digitally signed by Joseph J. Holonich Date: 2021.01.18 10:38:30 -05'00'