MONTHYEARML24019A2012024-01-19019 January 2024 Fourth 10-Year Interval, Second Period Owners Activity Report Number 1R24 ML24019A1362024-01-18018 January 2024 Inservice Inspection Request for Information ML24012A2452024-01-12012 January 2024 Response to Request for Additional Information to Proposed Method to Manage Environmentally Assisted Fatigue for the Pressurizer Surge Line ML24010A1532024-01-10010 January 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection ML23341A0062023-12-21021 December 2023 Project Manager Assignment IR 05000528/20230112023-12-18018 December 2023 License Renewal Inspection Report 05000528/2023011 ML23335A0782023-11-30030 November 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23325A1602023-11-17017 November 2023 Supplemental Submittal - Relief Request 70 Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle IR 05000528/20234032023-11-13013 November 2023 NRC Security Inspection Report 05000528 2023403, 05000529 2023403, 05000530 2023403 (Full Report) ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23299A3052023-10-26026 October 2023 Response to Request for Additional Information Relief Request 70 Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle IR 05000528/20230032023-10-17017 October 2023 Integrated Inspection Report 05000528 2023003 and 05000529 2023003 and 05000530 2023003 ML23270B9232023-09-28028 September 2023 Notification of Age-Related Degradation Inspection (05000528/2024012, 05000529/2024012, and 05000530/2024012) and Request for Information ML23251A2332023-09-13013 September 2023 Notification of Post Approval Site Inspection for License Renewal and Request for Information Inspection (05000528/2023011) ML23241B0182023-09-13013 September 2023 Use of Honeywell Mururoa V4F1 and MTH2 Supplied Air Suits within Respiratory Protection Program IR 05000528/20243012023-09-0606 September 2023 Notification of NRC Initial Operator Licensing Examination 05000528/2024301; 05000529/2024301; 05000530/2024301 IR 05000528/20230102023-08-22022 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000528/2023010, 05000529/2023010 and 05000530/2023010 IR 05000528/20230052023-08-21021 August 2023 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2023005 and 05000529/2023005 and 05000530/2023005) ML23222A2762023-08-10010 August 2023 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Transportable Storage Canister Identification Numbers AMZDFX175 and AMZDFX176 and Vertical Concrete Cask Identification Numbers AMZDNE175, and AMZDNE176 ML23199A2942023-08-0909 August 2023 Issuance of Amendment Nos. 221, 221, and 221, to Revise Technical Specifications to Adopt TSTF-107, Separate Control Rods That Are Untrippable Versus Inoperable IR 05000528/20230022023-08-0808 August 2023 Integrated Inspection Report 05000528/2023002 and 05000529/2023002 and 05000530/2023002 ML23207A2482023-07-26026 July 2023 License Renewal Pressurizer Surge Line Inspection ML23188A1872023-07-0707 July 2023 Fourth 10-Year Interval, Second Period Owners Activity Report Number 2R24 ML23166B0832023-07-0505 July 2023 Independence Spent Fuel Storage Installation - Issuance of Exemption ML23181A1602023-06-30030 June 2023 2 to Updated Final Safety Analysis Report, and Revision 3 to Operations Quality Assurance Program Description ML23180A2222023-06-29029 June 2023 Application to Revise Technical Specifications (TS) 3.5.1, Safety Injection Tanks (Sits) - Operating, TS 3.5.2, Safety Injection Tanks (Sits) - Shutdown, and TS 3.6.5, Containment Air Temperature ML23181A0772023-06-29029 June 2023 Program Review - Simulator Testing Methodology ML23157A1292023-06-0101 June 2023 Annual Report of Guarantee of Payment of Deferred Premium ML23144A3722023-05-24024 May 2023 Response to Regulatory Issue Summary (RIS) 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23143A3912023-05-23023 May 2023 Independent Spent Fuel Storage Installation - Request for Exemption from NAC-MAGNASTOR Certificate of Compliance 72-1031 - Cask Lid Batch 3 Design Requirements ML23145A2772023-05-17017 May 2023 10-PV-2023-05 Post-Exam Comments ML23132A3392023-05-12012 May 2023 Application to Revise Technical Specifications 3.3.11 to Adopt TSTF-266-A, Revision 3, Eliminate the Remote Shutdown System Table of Instrumentation and Controls IR 05000528/20230012023-05-0808 May 2023 and Independent Spent Fuel Storage Installation - Integrated Inspection Report 05000528/2023001 and 05000529/2023001 and 05000530/2023001 and 07200044/2023001 ML23128A0692023-05-0808 May 2023 Notification of Biennial Problem Dentification and Resolution Inspection and Request for Information ML23122A1822023-04-29029 April 2023 Transmittal of Technical Specification Bases Revision 76 ML23122A1912023-04-29029 April 2023 Unit 1 Core Operating Limits Report Revision 32, Unit 2 Core Operating Limits Report Revision 25, Unit 3 Core Operating Limits Report Revision 31 ML23116A2772023-04-26026 April 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report 2022 ML23115A4012023-04-26026 April 2023 Review of the 2022 Steam Generator Tube Inspections During Refueling Outage 23 ML23115A4982023-04-25025 April 2023 2022 Annual Environmental Operating Report IR 05000528/20230122023-04-19019 April 2023 Notification of Commercial Grade Dedication Inspection (05000528/2023012, 05000529/2023012, and 05000530/2023012) and RFI ML23108A0342023-04-18018 April 2023 NRC Initial Operator Licensing Examination Approval 05000528/2023301; 05000529/2023301; 05000530/2023301 ML23103A4642023-04-13013 April 2023 Annual Radiological Environmental Operating Report 2022 ML23103A4312023-04-13013 April 2023 Emergency Core Cooling System Performance Evaluation Models, 10 CFR 50.46(a)(3)(ii) Annual Report for 2022 IR 05000528/20224012023-04-13013 April 2023 Cyber Security Inspection Report 05000528/2022401 and 05000529/2022401 and 05000530/2022401 ML23102A3292023-04-12012 April 2023 Application for Authorized Use of Mururoa Single-Use, Supplied Air Suits, Models V4F1 and MTH2 ML23102A3242023-04-12012 April 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-107-A, Separate Control Rods That Are Untrippable Versus Inoperable ML23089A4002023-03-30030 March 2023 Consolidated Decommissioning Funding Status Report - 2022 ML23088A4012023-03-30030 March 2023 Project Manager Assignment IR 05000528/20234022023-03-29029 March 2023 and 3 - NRC Security Inspection Report 05000528-2023402, 05000529-2023402, and 05000530-2023402, (Cover Letter Only) ML23080A3002023-03-21021 March 2023 Present Levels of Financial Protection 2024-01-19
[Table view] |
Text
Public Serv,ce Company of New Mexico 414 Silver Ave SW Albuquerque, NM 87102-3289 PNM com
- p. JI ~
December 9, 2020 Via FedEx U.S. Nuclear Regulatory Commission Attn: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, 11D 20852-2738 Sale and Leaseback Transaction by Public Service Company of New Mexico NRC Docket No. STN 50-528 Renewed Facility Operating License No. NPF-41 Palo Verde Nuclear Generating Station, Unit 1 Ladies and Gentlemen:
The purpose of this letter is to provide prior written notification to the Nuclear Regulatory Commission (the "Commission") of the proposed transfer of an equity interest in a sale and leaseback transaction that was the subject of a license amendment in the above docket The proposed transfer of the equity interest would be from Access Energy Investors II LLC, a Delaware limited liability company (the "Transferor"), to Citicorp Buffalo Basin Inc., a Delaware corporation (the "Transferee"). The Transferee has represented that its 100% indirect owner, Citigroup, Inc. ("Citigroup"), a Delaware corporation, will have on the date the proposed transfer is consummated a net worth or capital and surplus of at least $25,000,000. The Transferee is not affiliated with Public Service Company of New Mexico ("PNM"). Upon the transfer, the Transferee will own an equity interest, through an existing owner trust, of a portion of the interest in the Palo Verde Nuclear Generating Station ("PVNGS") Unit 1, which was the subject of a sale and leaseback transaction in 1985 that was approved by the Commission.
Background. In 1985, PNM proposed to enter into the sale and leaseback transaction relating to PVNGS Unit 1. By letter dated December 26, 1985, the Commission issued Amendment No. 3 to Facility Operating License NPF-41 (Palo Verde Unit 1), approving the Unit 1 sale and leaseback transactions, subject to 10 C.F.R. § 50.81 and the conditions set forth in such Amendment. Currently, the Transferor holds (through the existing owner trust structure) a 1.36 percent undivided ownership interest in Unit 1. The Transferee is the previous owner of the Subject Interest (as defined below), having transferred the same to the Transferor on November 12, 2015 pursuant to a transaction notified to the Commission by letter dated October 13, 2015.
December 9, 2020 Page2 Subject of this Notice. The Transferor's 1.36 percent undivided ownership interest in Unit 1 is the subject of this notice (the "Subject Interest"). With respect to another (unrelated) equity interest transfer in 2007, Mike Markley of the Commission Staff advised PNM by letter dated October 18, 2007 (TAC NOS. l'v1D6791) that prior written notice to the Commission is required for the transfer of an equity interest in a PVNGS sale and leaseback transaction from one party to another, even if the terms of the sale and leaseback remain unchanged.
Notably, this is a prior written notice requirement and not a Commission approval requirement. This point was clarified in an e-mail from Randy Hall in connection with the 2010 transfer from Cypress PV Partnership to the Transferee. Mr. Hall, in an e-mail dated November 18, 2010, explained that the operating license condition to provide prior written notice to the Commission is satisfied by the delivery to the Commission of the notice letter.
The Transferor has notified PNM that the Transferor proposes to transfer the Subject Interest to the Transferee and, in connection therewith, the Transferee will execute an assignment and assumption agreement for the Subject Interest, pursuant to which the Transferee will assume the rights and obligations of the Transferor under the existing applicable PVNGS sale and leaseback transaction documents and will otherwise comply with the transaction documents.
The Transferor has further notified PNM that the parties plan to close the proposed transfer on or about December 23, 2020, and it has therefore requested that PNM provide this advance written notice to the Commission with respect to the transfer. The proposed transfer will be made in a manner that is specifically permitted under the sale and leaseback transaction as it was originally approved by the Commission. The current "owner trustee" for the sale and leaseback transaction, U.S. Bank National Association, will remain unchanged, and the terms of the lease will remain unchanged.
The Transferee has notified PNM that it is a wholly owned subsidiary of Citigroup
("Citigroup"). Additional information regarding Citigroup's business and financial statements can be found at www.Citigroup.com.
Request. Consistent with the explanation provided by Mr. Hall in 2010 noted above, we are not seeking any kind of review, approval or other action from the Commission. The license requirement with which we are complying simply requires prior notice in writing to the Commission.
Accordingly, confirmation of delivery of this notice by the overnight carrier to the Commission will be used by the parties as confirmation of compliance with the prior written notice requirement. We are sending an informational copy of this notice by e-mail to Siva Lingam, who we understand is the current Project Manager.
December 9, 2020 Page 3 If you have any questions, please do not hesitate to contact the undersigned at 505-241-4941. Again, as noted above, the Transferor and the Transferee plan to close the transaction on or about December 23, 2020.
Sincerely,
~
~
Leonard Sanchez Associate General Counsel PNM Resources, Inc.
cc by e-mail: Siva Lingam, Project Manager for PVNGS, (SivaLingam@nrc.gov)