MONTHYEARML23354A2902024-01-0505 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0028 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) RS-23-103, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML22060A2622022-03-0808 March 2022 FRN - Notice of Issuance of COVID-19 Exemptions Issued in February 2022 ML22042A0762022-02-15015 February 2022 Exemption from Specific Requirements of 10 CFR Part 26 (EPID L-2022-LLE-0008 (COVID-19)) ML22041A4512022-02-10010 February 2022 Incoming Request-La Salle-Constellation Energy, COVID-19 Related Request for Exemption from Part 26 Work Hours Requirements ML21060B5492021-03-16016 March 2021 Federal Register Notice, Exemption from Part 26 Requirements for Pre-Access Drug and Alcohol Testing (EPID-L-2021-LLE-0011) ML21053A0012021-02-22022 February 2021 Approval of Exemption from Certain Requirements of 10 CFR Part 26, Fitness for Duty Programs (EPID L-2021-LLE-0011 (COVID-19)) RS-21-026, Request for Exemption from Pre-Access Drug and Alcohol Testing Requirements in 10 CFR 26.652021-02-20020 February 2021 Request for Exemption from Pre-Access Drug and Alcohol Testing Requirements in 10 CFR 26.65 ML21025A2942021-02-0202 February 2021 Exemption from Select Requirements of 10 CFR Part 26 (EPID L-2021-LLE-0004 (COVID-19)) RS-21-011, Subsequent Request for Exemption from Part 26 Work Hours Requirements2021-01-22022 January 2021 Subsequent Request for Exemption from Part 26 Work Hours Requirements ML20346A0142020-12-18018 December 2020 Temporary Exemption from Biennial Emergency Preparedness Exercise Frequency Requirements of 10 CFR Part 50, Appendix E, Section IV.F.2.b (EPID-L-2020-LLE-0223 (COVID-19)) ML20324A1042020-12-0909 December 2020 Exemption from Annual Force-on-Force Exercise Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel, Subsection VI.C.3(l)(1) (EPID L-2020-LLE-0191 (COVID-19)) ML20330A3262020-12-0101 December 2020 Exemption from Select Requirements of 10 CFR Part 26 (EPID L-2020-LLE-0217 (COVID-19)) ML20329A3012020-11-24024 November 2020 Incoming Request-La Salle-Exelon Generation Co., LLC RS-20-144, Request for Exemption from the Biennial Emergency Preparedness Exercise Requirements in 10 CFR 50, Appendix E, IV.F.2.b2020-11-23023 November 2020 Request for Exemption from the Biennial Emergency Preparedness Exercise Requirements in 10 CFR 50, Appendix E, IV.F.2.b NMP1L3362, Request for an Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding 2020 Annual Force-on-Force (FOF) Exercises Due to COVID- 19 Public Health Emergency2020-11-13013 November 2020 Request for an Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding 2020 Annual Force-on-Force (FOF) Exercises Due to COVID- 19 Public Health Emergency ML20243A0002020-09-23023 September 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for August 2020 ML20203M2332020-08-0303 August 2020 Temporary Exemption Request from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel, Section VI (EPID L-2020-LLE-0116) (COVID-19) ML0614302462006-06-27027 June 2006 TMI and Zion - Exemption from the Requirements of 10 CFR 50.54(a)(3) Re Submittal of Changes to Quality Assurance Topical Report ML0233805992002-11-25025 November 2002 Exemption Request from the Requirements of 10 CFR 50.36(c)(1) 2024-01-05
[Table view] Category:Letter
MONTHYEARIR 05000373/20230042024-01-24024 January 2024 County Station - Integrated Inspection Report 05000373/2023004 and 05000374/2023004 ML24024A1332024-01-24024 January 2024 Confirmation of Initial License Examination IR 05000373/20230122024-01-18018 January 2024 County Station - Biennial Problem Identification and Resolution Inspection Report 05000373/2023012 and 05000374/2023012 ML23354A2902024-01-0505 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0028 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23360A6082023-12-27027 December 2023 County Station Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000373/2024010 and 05000374/2024010 ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums RS-23-120, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information IR 05000373/20230032023-11-0909 November 2023 County Station Integrated Inspection Report 05000373/2023003, 05000374/2023003, and 07200070/2023001 ML23286A2602023-11-0808 November 2023 Issuance of Amendment Nos. 260 and 245 to Renewed Facility Operating Licenses Relocation of Pressure and Temperature Limit Curves to the Pressure Temperature Report IR 05000373/20234012023-11-0707 November 2023 County Station Security Baseline Inspection Report 05000373/2023401 and 05000374/2023401 RS-23-103, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans IR 05000374/20230102023-10-11011 October 2023 NRC Inspection Report 05000374/2023010 IR 05000373/20233012023-09-15015 September 2023 Errata to NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor ML23212A9012023-08-0303 August 2023 Regulatory Audit Report to Support the Review of the Amendments to Relocation of the Pressure Temperature Limit Curves to the Pressure and Temperature Limits Report IR 05000373/20230022023-08-0101 August 2023 County Station - Integrated Inspection Report 05000373/2023002 and 05000374/2023002 ML23208A3182023-07-27027 July 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI RS-23-084, Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis2023-07-24024 July 2023 Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis ML23192A5272023-07-12012 July 2023 NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 ML23186A2062023-07-0606 July 2023 Information Request for a NRC Post-Approval Site Inspection for License Renewal 05000374/2023010 ML23181A1502023-06-30030 June 2023 Combined Response to Request for Additional Information and Supplemental Information in Support of LAR to Relocate Pressure and Temperature Limit Curves to the Pressure and Temperature Limits Report ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III IR 05000373/20230112023-06-26026 June 2023 County Station - Quadrennial Fire Protection Team Inspection Report 05000373/2023011 and 05000374/2023011 RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23167A0352023-06-16016 June 2023 Registration of Use of Cask to Store Spent Fuel ML23171A9562023-06-12012 June 2023 Post Exam Ltr RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling IR 05000373/20230012023-05-10010 May 2023 County Station - Integrated Inspection Report 05000373/2023001 and 05000374/2023001 ML23123A2202023-05-0303 May 2023 Relief Request I4R-14 for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 ML23121A1612023-05-0101 May 2023 Information Meeting (Open House) with a Question-and-Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of LaSalle County Station, Units 1 and 2 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23107A1822023-04-18018 April 2023 Operator Licensing Examination Approval Lasalle County Station, May 2023 RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23073A2182023-03-22022 March 2023 Issuance of Amendment No. 258 to Renewed Facility Operating Licenses Exigent Amendment to Revise Design Basis Related to Seismic Requirements RS-23-048, Exigent Amendment Request to Revise Design Basis Related to Seismic Requirements2023-03-0707 March 2023 Exigent Amendment Request to Revise Design Basis Related to Seismic Requirements ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000373/20220062023-03-0101 March 2023 Annual Assessment Letter for LaSalle County Station, Units 1 and 2 (Report 05000373/2022006 and 05000374/2022006) RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-037, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station2023-02-22022 February 2023 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station ML23024A1372023-02-0303 February 2023 Request for Withholding Information from Public Disclosure for LaSalle County Station, Unit Nos. 1 and 2 ML23031A1972023-01-31031 January 2023 Notification of NRC Fire Protection Team Inspection Request for Information, Inspection Report Nos. 05000373/2023011 and 05000374/2023011 IR 05000373/20220042023-01-31031 January 2023 County Station - Integrated Inspection Report 05000373/2022004 and 05000374/2022004 RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 2024-01-05
[Table view] |
Text
COVID-19 Related Request for Exemption from Part 26 Work Hours Requirements Submitted: Nov 24, 2020
- 1. Submitter Name/Title:
Putri D. Kusumawati Murray, Senior Manager - Licensing
- 2. Email Address Please enter the email address for which you would like to receive communications regarding this request.
Putri.Kusumawatimurray@exeloncorp.com
- 3. Organization Exelon Generation Co., LLC
- 4. Plant Name La Salle
- 5. Plant Unit(s): 1,2
- 6. Need By Date 2020-12-07
- 7. Docket Number(s)
Example: 05000313 05000373 05000374
- 8. License Number(s)
Example: DPR-51 NPF-11 NPF-18
- 9. NRC Licensing Project Manager B. PURNELL
- 10. Statement that the licensee above can no longer meet the work hour controls of 10 CFR 26.205(d) for certain personnel or groups of personnel specified in 10 CFR 26.4(a) because of site specific issues as a result of the COVID-19 public health emergency (PHE).
As a result of the Coronavirus Disease 2019 (COVID-19) public health emergency (PHE), Exelon Generation Company, LLC (EGC) is requesting NRC approval to utilize the alternative work hour controls delineated in the NRCs March 28, 2020 letter (ML20087P237) and November 10, 2020 letter (ML20261H515) for LaSalle County Station (LaSalle) for the covered workers noted below.
The alternative controls will support maintaining staffing requirements as a result of recent increase in personnel absence due to COVID-19 positive test results or contact tracing quarantines that cannot be accommodated by the current work hour control requirements of 10 CFR 26.205(d)(1) through (d)(7) to support plant operational safety and security. The increase in COVID-19 cases in the state of Illinois and communities surrounding LaSalle could impact station's ability to meet the work hour controls of 10 CFR 26.205(d) in maintaining minimum staffing and ensuring adequate qualified individuals of personnel specified in 10 CFR 26.4(a)(1) through (a)(5) are available to complete necessary operations, tests, inspections, and maintenance in a manner that supports nuclear safety and security. Therefore, EGC has determined that implementing the alternative work hour controls would allow LaSalle to proactively take steps to ensure added flexibility is available to facilitate further worker and community protection and ensure safe operation during the period of the exemption.
Exemption from the 10 CFR 26.205(d)(1) through (d)(7) requirements is intended to prevent and limit the spread of COVID-19 and to mitigate its effect should LaSalle staffing be significantly impacted. LaSalle intends to use the alternative controls, where necessary, to efficiently perform operation, inspection, maintenance and testing activities that cannot be performed in accordance with the Centers for Disease Control and Prevention (CDC) recommendations related to social distancing, mask usage, worker screening, and limiting close proximity work. This practice will reduce the number of people involved in specific activities to limit the potential spread of COVID-19 and supports LaSalle's continuing efforts to maintain CDC recommendations. In addition, the alternative controls will be used to mitigate the staffing impacts should personnel absences challenge required staffing levels.
As the U.S. Departments of Homeland Security and Energy have stated in their guidance, the electric grid and nuclear plant operation make up the nations critical infrastructure similar to the medical, food, communications, and other critical industries.
LaSalle's operation must be conducted such that the plant is available when needed, including during the critical peak winter loads.
In accordance with the NRC Letter from H. Nieh to NEI, "U.S. Nuclear Regulatory Commission Planned Actions Related to the Requirements for Work Hour Controls During the Coronavirus Disease 2019 Public Health Emergency," dated March 28, 2020 (ML20087P237) and NRC Letter from H. Nieh to NEI, "U.S. Nuclear Regulatory Commission Updated Planned Actions Related to Certain Requirements for Operating and Decommissioning Reactor Licensees During the Coronavirus Disease 2019 Public Health Emergency," dated November 10, 2020 (ML20261H515), the following work groups would begin phasing in on December 7, 2020 the site-specific alternative controls, as necessary, to minimize transition issues:
10 CFR 26.4(a)(1) Operators 10 CFR 26.4(a)(2) Health Physics and Chemistry 10 CFR 26.4(a)(3) Fire Brigade 10 CFR 26.4(a)(4) Maintenance 10 CFR 26.4(a)(5) Security
- 11. List of personnel or groups of personnel specified in 10 CFR 26.4(a) for which the licensee will maintain current work hour controls under 10 CFR 26.205(d)(1)-(d)(7).
N/A
- 12. List and description of alternative controls for the management of fatigue to address site specific issues as a result of the COVID-19 PHE.
LaSalle's site-specific COVID-19 PHE fatigue-management controls are consistent with the constraints outlined in the referenced NRC letters and its attachment and enclosure.
LaSalle will continue to follow the fatigue management controls, behavioral observation requirements, and self-declaration allowances currently delineated within the EGC work hour control program and procedures (LS-AA-119, SY-AA-102, SY-AA-103-500).
The requirements of 10 CFR 26.33, Behavioral observation; 10 CFR 26.209, Self-declarations; and 10 CFR 26.211, Fatigue assessments remain in effect during the period of the exemption. These requirements provide reasonable assurance that should
personnel become impaired due to fatigue, requirements and processes are in place to identify the impairment through observation by plant staff or by worker self-declaration, and to assess and address instances of impairment through fatigue assessments.
- 13. Date when the licensee will begin implementing its site-specific COVID-19 PHE fatigue-management controls for personnel specified in 10 CFR 26.4(a) 2020-12-07
- 14. The time when the licensee will begin implementing its alternative controls for the management of fatigue for personnel (or group of personnel) specified in 10 CFR 26.4(a).
00:00
- 15. Statement that the licensees site specific alternative controls for the management of fatigue are consistent with the minimum alternative controls listed below.
LaSalle's site-specific COVID-19 PHE fatigue-management controls are consistent with the constraints outlined in the referenced NRC letters, dated March 28, 2020 and November 10, 2020.
- 16. Does Licensee continue to meet the requirements of 10 CFR 26.33, Behavioral observation; 10 CFR 26.209, Self declarations; and 26.211, Fatigue assessments.
Yes
- 17. The alternative controls include the following, as a minimum:
- 1. Individuals will not work more than 16 work-hours in any 24-hour period and not more than 86 work-hours in any 7-day period, excluding shift turnover;
- 2. A minimum 10-hour break is provided between successive work periods;
- 3. 12-hour shifts are limited to not more than 14 consecutive days;
- 4. A minimum of 6-days off are provided in any 30-day period; and
- 5. Changes in actions to meet requirements for behavioral observation for both acute and cumulative fatigue and self declaration during the period of the exemption as appropriate due to potential for increased worker fatigue.
Yes
- 18. Additional Information:
Use the area below to provide any additional information related to your exemption request.
Upon NRC approval, LaSalle would implement the alternative controls described in the referenced NRC letters for the management of fatigue on December 7, 2020 for an initial period of 60 days. Near the end of the 60-day period, if COVID-19 pandemic conditions persist at the site affecting staffing requirements and the efforts to maintain CDC, state and local recommendations related to social distancing, worker screening, and limiting close-proximity work, as well as of particular concern is the COVID-19 challenge in the immediate community of LaSalle, an additional email supplement request may be submitted to extend the 60-day exemption period implementation.