Letter Sequence Request |
---|
EPID:L-2020-LLL-0024, Letter Authorization for Shipment of Atrium Fuel Equipped with Eatf Rods (Approved, Closed) |
|
MONTHYEARML20283A3572020-10-0909 October 2020 Letter Authorization for Shipment of Atrium Fuel Equipped with Eatf Rods Project stage: Request ML20309A4232020-10-0909 October 2020, 4 November 2020 Authorization for Shipment of Framatome Boiling Water Reactor Atrium 10XM Fresh Fuel Assemblies Equipped with Inert Test Rods Project stage: Request ML20309A4242020-11-0404 November 2020 Submittal of Authorization for Shipment of Framatome Boiling Water Reactor Atrium 10XM Fresh Fuel Assemblies Equipped with Inert Test Rods Project stage: Request ML20315A2702020-11-10010 November 2020 Enclosusafety Evaluation Report - Authorization for Limited Shipments Project stage: Approval ML20315A2682020-11-10010 November 2020 Revised Authorization for the Shipment of Framatome Eatf BWR Atrium Assemblies Project stage: Request ML20315A2692020-11-10010 November 2020 Cover Letter: Revised Authorization for Shipment of Framatome BWR Atrium 10XM Fresh Fuel Assemblies Equipped with Inert Test Rods Project stage: Other 2020-11-10
[Table View] |
|
---|
Category:Letter
MONTHYEARML24156A1052024-06-0606 June 2024 Transmittal Letter - Certificate of Compliance No. 9372, Rev. 5, for the Model No. TN-B1 Package ML24082A1872024-03-22022 March 2024 Framatome TN-B1 Shipping Container, Request for Additional Information Response ML23348A1782023-12-14014 December 2023 Framatome Inc. Request for Five Year Renewal of Certificate of Compliance No. 9372 for the Model No. TN-B1 Packaging ML23282A0052023-10-0909 October 2023 Framatome, Inc., Submittal of 71-9372, TN-81 License Drawing Correction ML23282A0082023-10-0909 October 2023 Framatome, Inc. - 10 CFR 71.95 - 60 Day Report - TN-B1 Certificate Not Followed ML23031A2142023-01-31031 January 2023 Framatome, Inc., TN-B1 Shipping Container, Amendment Request for Increased Enrichment Values ML22305A5412022-10-31031 October 2022 Framatome, Inc. - 10 CFR 71.95 - 60 Day Report - TN-B1 Certificate Not Followed ML22175A1232022-06-24024 June 2022 Framatome, Inc., Intent to Request License Amendment ML22034A9672022-02-11011 February 2022 Letter Authorization TN-B1-2022 ML22028A1852022-01-28028 January 2022 Framatome, Inc., Submittal of Model No. TN-B1 Transport Package, License Amendment Request ML21302A1382021-11-29029 November 2021 Framatome, Inc., Intent to Request an Amendment ML21319A3892021-11-15015 November 2021 Framatome Intends to Request a Letter Authorization Utilizing Docket No. 71 -9372, Framatome TN-B1 Shipping Container ML20315A2692020-11-10010 November 2020 Cover Letter: Revised Authorization for Shipment of Framatome BWR Atrium 10XM Fresh Fuel Assemblies Equipped with Inert Test Rods ML20315A2702020-11-10010 November 2020 Enclosusafety Evaluation Report - Authorization for Limited Shipments ML20309A4242020-11-0404 November 2020 Submittal of Authorization for Shipment of Framatome Boiling Water Reactor Atrium 10XM Fresh Fuel Assemblies Equipped with Inert Test Rods ML20309A4252020-10-0909 October 2020 Authorization for Shipment of Framatome Boiling Water Reactor Atrium 10XM Fresh Fuel Assemblies Equipped with Inert Test Rods ML20283A3592020-10-0909 October 2020 Encl 1: Safety Evaluation Report - Authorization for Limited Shiments ML20283A3582020-10-0909 October 2020 Letter Authorization for Shipment of Atrium 10XM Assemblies Equipped with Eatf Test Rods ML20167A1872020-06-15015 June 2020 Letter Authorization Application Utilizing Certificate USA 9372/B(U)F-96 for Model No. TN-B1 Transport Package ML20115E5912020-04-24024 April 2020 Framatome, Inc., Intends to Request a Letter Authorization Utilizing Docket No. 71-9372, TN-B1 Shipping Container ML19070A0202019-03-0606 March 2019 Letter to T. Tate Certificate of Compliance No. 9372, Revision No. 2, for the Model No. TN-B1 Package ML18283B3172018-10-0909 October 2018 Letter to T.J. Tate Certificate of Compliance No. 9372, Revision No. 2, for the Model No. TN-B1 Package ML18173A0332018-06-21021 June 2018 Letter to T. Tate Certificate of Compliance No. 9372, Revision No. 1, for the Model No. TN-B1 Package 2024-06-06
[Table view] |
Text
framatome November 4 , 2020 T JT:20 :024 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Director, Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards 11555 Rockville Pike One White Flint North Rockville, MD 20852
Subject:
Docket No. 71 -9372; Authorization for Shipment of Framatome Boiling Water Reactor ATRIUM 10XM Fresh Fuel Assemblies Equipped with Inert Test Rods
References:
(1) U.S. Nuclear Regulatory Commission , Authorization Letter for the Model No. TN-81 Package, Docket No. 71-9372 , Dated October 9, 2020 Framatome Inc. (Framatome) is requesting a change to the allowable number of transports allowed in the TN-81 Letter Authorization, Docket No. 71 -9372 [Ref. 1],
provided by the NRC in October of this year.
After receipt of the authorization, Framatome identified a risk that the reactor site, due to a currently unforeseen reason , may not be able to receive the fuel assemblies with the inert test rods . In this case, this strands the fresh fuel assemblies with no ability for them to be returned to Framatome. As such, the following change is requested within the authorization :
Existing Condition (1) Authorization is for a maximum of 1 shipment of all 8 test rods (4 fuel assemblies) in one transport.
Requested Change (1) Authorization is for a maximum of 3 shipments of up to 8 test rods (4 fuel assemblies) in one transport.
Framatorne lr\C.
2101 HO* n Rapids Road Rich!and, WA 9935~
Tel: (509) 375-0 100 www.fmmatome.com
US NRC T JT:20:024 November 4, 2020 Page 2 This change will allow one or multiple non-conforming fuel assemblies with inert test rods to be returned to Framatome, the noncompliance corrected, and the fuel assemblies to again be delivered to the reactor.
No other changes are requested and Framatome is not increasing the total number of fresh fuel assemblies with inert test rods being fabricated. This request is only to address the off chance that the reactor facility cannot accept these fuel assemblies upon delivery.
To support the shipping window beginning in mid-February, Framatome requests this change by mid-January, 2021.
Please feel free to contact me at (509) 375-8550 or Bryan Flanagan of my staff at (509) 375-8537 if you have any questions or need additional information.
Very Truly Yours,
~'-~~
Timothy J. Tate, Manager Environmental, Health, Safety and Licensing Attachments:
- 1. Recommended changes to NRC Letter Authorization, Docket No. 71-9372, Dated October 9, 2020 Pierre Saverot US Nuclear Regulatory Commission (w attachments)