Pre-Submittal Meeting with the NRC Exelon Decommissioning Licensing Action Submittal Plan for Byron and Dresden Stations Early Shutdowns September 22, 2020
Exelon announced closure Byron Station on or before September 30, 2021 Dresden Station on or before November 30, 2021 Cessation letters submitted September 2, 2020 Key Milestones Milestones NRC Decommissioning Submittals - Byron & Dresden 1
Permanent Shutdown Permanent Defuel End of Zirc-Fire Period*
Byron Units 1 and 2 On or before September 30, 2021 September-October 2021 January 2023 Dresden Units 2 and 3 On or before November 30, 2021 November-December 2021 September 2022 Zirc-Fire period will be determined by analysis, estimated for submittal purposes to be 10-months for Dresden (BWR) and 16-months for Byron (PWR)
Overall goal is to provide for a safe and efficient transition from an operating site to a permanently shutdown site Licensing submittals based on:
Review of regulations and guidance documents Review of Industry guidance documents (NEI Guidance)
Benchmarking and lessons learned o Industry peers o Exelon decommissioning transition experience at Oyster Creek and Three Mile Island o RAI review Licensing submittals will align with licensing actions previously submitted and approved by NRC o Improved by incorporation of RAI lessons learned Consistent with proposed NRC Decommissioning Rule Updates of submittal schedule will be discussed during periodic Byron and Dresden NRR Project Managers calls Submittal Background NRC Decommissioning Submittals - Byron & Dresden 2
Permanent Shutdown Licensing Actions NRC Decommissioning Submittals - Byron & Dresden 3
Licensing Document Submittal Requested Approval Byron Dresden Certified Fuel Handler Program Combined Oct 2020 Aug 2021 ( 10 months*)
Security Exemption Combined Oct 2020 Aug 2021 ( 10 months*)
Administrative License Amendment Request By Site Early-Oct 2020 Aug 2021 ( 10 months*)
Oct 2021 ( 12 months)
Post-Defueled Technical Specifications By Site Late-Oct 2020 Aug 2021 ( 9 months*)
Oct 2021 ( 12 months)
Post-Shutdown Emergency Plan By Site Nov 2020 Sep 2021 ( 10 months*)
Oct 2021 ( 11 months*)
Records Exemption Combined Oct 2020 Oct 2021 ( 12 months)
Post-Shutdown Decommissioning Activities Report By Site Apr 2021 N/A N/A Decommissioning Cost Estimate By Site Apr 2021 N/A N/A Spent Fuel Management Plan By Site Apr 2021 N/A N/A Exemption to Use Decommissioning Trust Fund for Spent Fuel Management By Site Apr 2021 Under Consideration Oct 2021 ( 6 months*)
Zirc-Fire Window Licensing Actions NRC Decommissioning Submittals - Byron & Dresden 4
Site Licensing Document Submittal Requested Approval Dresden EP Exemption Mar 2021 May 2022 ( 14 months)
Dresden PDEP Mar 2021 May 2022 ( 14 months)
Byron EP Exemption Apr 2021 Oct 2022 ( 18 months)
Byron PDEP Exemption Apr 2021 Oct 2022 ( 18 months)
Dresden Offsite Insurance Exemption Jul 2021 Jul 2022 ( 12 months)
Dresden On-Site Insurance Exemption Jul 2021 Jul 2022 ( 12 months)
Byron Offsite Insurance Exemption Nov 2021 Nov 2022 ( 12 months)
Byron On-Site Insurance Exemption Nov 2021 Nov 2022 ( 12 months)
Defueled Quality Assurance Program (DQAP)
Incorporate Byron and Dresden to existing NRC approved DQAP through 50.54(q)
Security Plans Changes As allowed through 50.54(p)
Alternate Means Changes NRC Decommissioning Submittals - Byron & Dresden 5
Dresden Unit 1 will be included, as appropriate, in decommissioning licensing actions for Units 2 and 3 Exelon evaluating currently docketed and planned non-decommissioning related licensing submittals for Byron and Dresden Communicate results to appropriate NRR Project Manager Engagement with NRC Region III regarding scheduled inspections Other Considerations NRC Decommissioning Submittals - Byron & Dresden 6
Site Permanent Shutdowns Byron Station on or before September 30, 2021 Dresden Station on or before November 30, 2021 Licensing Submittals Align with licensing actions previously submitted and approved by NRC Consistent with proposed NRC Decommissioning Rule Requesting timely NRC review of licensing submittals Alternate Means Changes Incorporate Byron and Dresden under 50.54(q) into Exelons previously NRC approved DQAP Security Plans Changes as allowed through 50.54(p)
Summary NRC Decommissioning Submittals - Byron & Dresden 7
Pre-Submittal Meeting with the NRC Exelon Decommissioning Licensing Action Submittal Plan for Byron and Dresden Stations Early Shutdowns QUESTIONS?