Forwards Amend 128 to License NPF-39 & Se.Amend Documents NRC Staff Approval of Implementation of Plant Mod to Support Installation of Replacement Suction Strainers for ECCS at Plant,Unit 1
ML20247M667
Person / Time
Site: Limerick Constellation icon.png
Issue date: 05/14/1998
From: Buckley B
NRC (Affiliation Not Assigned)
To: Geoffrey Edwards
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
Shared Package
ML20247M670 List:
References
TAC-M99856, NUDOCS 9805260329
Download: ML20247M667 (4)


Text

[

3 UNITED STATES

[-MM 4

NUCLEAR REGULATORY COMMISSION j-I usHINSTcN, D.C. *=maal

'+, * * * * * #

May 14, 1998 Mr. Garrett D. Edwards Director-Uonasing, MC 62A-1 i

PECO Energy Company Nuclear Group Headquarters l _

Correspondence Control Desk l

P.O. Box No.195 Wayne, PA 19087-0195

SUBJECT:

UMERICK GENERATING STATION, UNIT 1 - REPLACEMENT SUCTION 8 TRAINERS FOR THE EMERGENCY CORE COGUNG SYSTEM (TAC NO. M99856)

Dear Mr. Edwards:

The Commission has issued the enclosed Amendment No.128 to Facility Operating Uconse No.

NPF-39 for the Limerick Generating Station, Unit 1. This amendment is in response to your application dated October 6,1997, as supplemented February 2,1998.

This amendment documents the NRC staff's approval of the implemcr,tation of a plant modification to support the installation c/ replacement suction strainers for the emergency core cooling systems at the Umerick Generating Station, Unit 1. This amendment also authorizes you, through two license conditions, to incorporate changes to the description of the facilities in the Updated Final Safety Analysis Report (UFSAR), as described in the licensee's application dated October 6,1997, as supplemented by letter dated February 2,1997, and evaluated in the enclosed safety ovaluation. As an administrative action by the Nuclear Regulatory Commission (NRC), which only involves the format of the licenses and does not authorize any activities outside the scope of your application and supplement, the NRC has amended the license to include an Appendix C, which lists additionallicense cor:ditions. Approval of this amendment through license conditions has been discussed with your staff on May 13,1998, in a conference call and your staff has agroad, by submittal dated May 13,1998, to the structure of the license for issuing these license conditions. The information in support of this modification was technically comprehensive and addressed the relevant issues. The evaluation of the proposed replacement suchon strainers for Umerick Geriorating Station Unit 2 is being deferred pending your response -

to our request for additional information with regard to Unit 2.

A copy of our safety evaluation is also enclosed. Notice of issuance will be included in the Commission's biweekly Egdatal Etnister notice.

l I

i f

I hfff

$f s

9905260329 990514 PDR ADOCK 05000352 P.

PDR

h G. Edwards l This completes our effort on this issue for Limerick Generating Station, Unit 1 and we are, j

therefore, closing out TAC No. M99856.

Sincerely,

/s/

B.artholomew C. Buckley, Senior Project Manager Project Directorate 1-2 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation Docket No. 50-352

Enclosures:

1. Amendment No 128 to License No. NPF-39
2. Safety Evaluation
3. Notice ofissuance cc w/encis: Sea next page DISTRIBUTQtt Docket File MO'Brien WBeckner TCollins PUBLIC BBuckley KKavanagh CBerlinger PD!-2 Reading OGC ACRS JZwolinski GHill(2)

THarris (E-Mail SE)

RCapra CAnderson, RGN-1 RElliott

  • Previously Concurred OFFICE PDid/ PPA PDl4/h OGk/

SRXB*

SCSB*

PDI-2/D db'kd TCollins CBerlinger. /[/fN4w/

RCapYa NAME BBuc mw DATE I/'f/98 D/h/98 e

.b/ 98 5 /t4 /98 04/27/98 04/27/98 OFFICIAL RECORD COPY

'd DOCUMENT NAME: A: LIM 99856.AMD -

1 1

G. Edwards 1 1

l This completes our eNort on this issue for Limerick Generating Station, Unit 1 and we are, therefore, closing out TAC No. M99856.

Sincerely, d[4.

Wd

,M@4 Bartholomew C. Buckley, Senior Prd oct Manager Project Directorate 1-2 Division of Reactor Projects - 1/11 ONice of Nuclear Reactor Regulation Docket No. 50-352

Enclosures:

1. Amendment No.128to License No. NPF-39
2. Safety Evaluation
3. Notice of issuance cc w/encis: See next page 4

s

Mr. Garrett D. Edwards Umorick Generating Station, Units 1 & 2

/

PECO Energy Company cc:

1 J. W. Durham, Sr., Esquire Chief-Division of Nuclear Safety j

Sr. V.P. & General Counsel PA Dept. of Environmental Resources l

PECO Energy Company P.O. Box 8469 2301 Market Street Harrisburg, PA 1710M469 Philadelphia, PA 19101 Manager-Umorick Uconsing,62A-1 Director-S!te Engineering PECO Energy Company Umerick Generating Station 965 Chesterbrook Boulevard P.O. Box A l

Wayne, PA 19087-5691 Senatoga, PA 19464 Mr. James D. von Suskil, Vice President i

Umerick Generating Station Manager-Experience Assessment Post Office Box A Umerick Generating Station Sanatoga, PA 19464 P.O. Box A l

Sanatoca, PA 19464 Plant Manager Umorick Generating Station Ubrary l

P.O. Box A U.S. Nuclear Regulatory Commission Sanatoga, PA 19464 Region 1 475 Allendale Road Regional Administrator, Region i King of Prussia, PA 19406 U.S. Nuclear Regulatory Commission 475 Allendale Road Senior Manager-Operations 1

King of Prussia, PA 19406 Umerick Generatir:g Station P.O. Box A Senior Resident inspedor Sanatoga, PA 19464 U.S. Nuclear Regulatory Commission Umerick Generating Station Dr. Judith Johnsrud P.O. Box Sg6 National Energy Committee 4

Pottstown, PA 19464 Sierra Club 433 Orlando Avenue Director-Site Support Services State College, PA 16803 Umorick Generating Station P.O. Box A Sanatoga, PA 19464 Chairman Board of Supervisors of Umorick Township i

646 West Ridge Pike Unfield, PA 19468