Notice of Violation from Insp on 890522-26 & 0620-22. Violation Noted:Hpci (Train a) & LPCI (Train B) Not Installed in Accordance W/Drawings & Exemptions at Elevation of 20 Ft
ML20247L185
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 07/21/1989
From: Conlon C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20247L168 List:
References
50-324-89-11, 50-325-89-11, NUDOCS 8908010172
Download: ML20247L185 (2)


Text

-_ - - _ _ - _ _ _

, g s

L ENCLOSURE 1 NOTICE OF VIOLATION Carolina Power and Light Company Docket Nos. 50-325, 50-324 Brunswick License Nos. DPR-71. DPR-62 During the Nuclear Regulatory Comission (NRC) inspection conducted on

  • May 22-26 and June 20-22, 1539, a violation of NRC requirements was identified.

In accordance with the " General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C (1989), the violation is listed below:

10 CFR 50.48, Appendix R, Section III G, 2.6, requires that separation of cables and equipment and associated nonsafety circuits of redundant trains by a horizontal distance of more than 20 feet with no intervening combustible or fire hazards.

Contrary to the above, on May 23, 1989, the NRC inspectors found that the HPCI (Train A) and LPCI (Train B) were not installed in accordance with drawings and exemptions at elevation of 20 feet in the Southwest corner of Unit I reactor building.

This is a Severity Level IV violation (Supplement II).

Pursuant to the provisions of 10 CFR 2.201, Carolina Power & Light is hereby required to submit a written statement or explanation to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555, with a copy to the Regional Administrator, Region II, and a copy to the NRC Resident Inspector, within 30 days of the date of the letter transmitting this Notice.

This reply should be clearly marked as a " Reply to a Notice of Violation" cnd should include [for each violation]: (1) admission or denial of the violation, (2) the reason for the violation if admitted, (3) the corrective steps which have been taken and the results achieved, (4) the corrective steps which will i be taken to avoid further violations, and (5) the date when full compliance will be achieved. Where good cause is shown, consideration will be given to extending the response time. If an adequate reply is not received within the time specified in this Notice, an order may be issued to show cause why the I

l i

8908010172 890721 PDR ADOCK 03000324 Q PDC

I

i- y  ;

a ]

L- ,- j Carolina Power and Light Company

-Brunswick ~

'd Docket.Nos.J50-325, 50-324 l License Nos. DPR-71. DRR-62 5 I

i

license should not be' modified, suspended, or revoked or.why such other action as may be proper should not be taken.

~

i FOR THE NUCLEAR REGULATORY COMMISSION.

original signed by I

Thomas E. Conlon .

Caudie A. Julian, Chief Engineering Branch Division of Reactor Safety _

Dated at Atlanta, Georgia this21st day of July 1989