ML20247K143

From kanterella
Jump to navigation Jump to search
Ack Receipt of Util Submitting Schedule for Implementation of Closed Circuit Television Sys Upgrade,Per Insp Rept 50-458/89-09
ML20247K143
Person / Time
Site: River Bend Entergy icon.png
Issue date: 03/28/1989
From: Callan L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Deddens J
GULF STATES UTILITIES CO.
References
NUDOCS 8904050178
Download: ML20247K143 (2)


See also: IR 05000458/1989009

Text

]

'

i-

-.,

'

q'

r

,

,-

.

In Reply-Refer To:

WR 2 81989 -

!

Docket: 50-458/89-09

3

' Gulf States Utilities .

ATTN: Mr. James C. Deddens

Senior Vice President (RBNG)

P.O. Box 220'

St. Francisville, Louisiana 70775

Gentlemen:

-

.

j

Thank you-for your letter of February 28, 1989, which transmitted the

]

1

' schedule for, implementation of your. closed circuit' television system upgrade.

]

L

We have reviewed your schedule for implementation and find it timely and

-

responsive to the concerns raised in our Notice of Violation.

Sincerely,

. Original Signed B'y,

E B. Beacli

L. J. Callan, Director

J

Division of Reactor Projects

cc:

Gulf States Utilities-

ATTN:

J. E. Booker, Manager-

River. Bend Oversight

P.O. Box.2951

Beaumont, Texas 77704

Gulf States Utilities

ATTN:

Les England, Director

Nuclear Licensing - RBNG

P.O. Box 220

,.

St. Francisville, Louisiana 70775

Louisiana State University,

Government Documents Department

Louisiana Radiation Control Program Director

l

RIV

S:RPB

C:S

RPB

C:RPB

C:RPS/CfMhy

g3

AB

st:cd

RJE

tt

BMurray

LConstable

an

b

3/J9/89

'b / 2489

) / /89

3 />y/89

3j7989

~ 90405017e 890328

8

PDR

ADOCK 0500

8

Q

gg

QC-f

_

- _ -

- --_

r

,_

- - _ _

.

o

-r

.

,

-

.

Gulf States Utilities

-2-

bec to DMB (IE04)

bec w/non-safeguards portion of licensee's letter:

R. D. Martin, RA DRP

Resident Inspector

Section Chief, DRP/C

Lisa Shea, RM/ALF

MIS System

DRS

RSTS Operator

RPB-DRSS

i

RIV File

1

Inspector

Section Chief

B. Murray

R. L. Bangart

,

R. E. Hall

'

Project Engineer, DRP/C

W. Paulson, NRR Project Manager

>

_ - _ - _ - - _ _ - - _ .

-

SAFEGUARDS INFORMATION

.

-

.

.

.

,s

GULF STATES

UTILITIES COMPANY

ama em srarm

o . a n. <

v<m_

..s_ww.2om

g g GN c.. y3) tj

ami a

a, ec u

m am

i

gs. - -

-

February 28, 1989

i

{

%,7g

-

,

RBG-

30184

File Nos. G9.5, G15.4.1

L.-

'

.

~

,

Director, Office of Nuclear Reactor Regulations

'

O.S. Nuclear Regulatory Commission

!

Attn: Document Control Desk

Washington, DC 20555

Gentlemen:

RIVER BEND STATION - UNIT 1

REFER TO: REGION IV

l

DOCKET NO. 50-458/ REPORT 88-09

i

This supplemental response to the Notice of Violation contained in NRC

Inspection Report No. 50-458/88-09 is being submitted to provide a

current status on corrective action taken on item 8809-01, " Assessment

Aids".

Initial response to the Violation was provided in a

letter

i

from Mr.

J.

C.

Deddens dated July

6,

1988 (RBG-28210) with a

supplemental report provided on November 30,

1988 (RBG-29473).

The

inspection was performed by Mr. A. B. Earnest on April 11-15, 1988 of

l

activities authorized by NRC Operating License NPF-47 for River Bend

Station - Unit 1.

,

In accordance with 10CFR73.21, information contained in the attachment

has been determined to contain safeguards information and should be

handled accordingly.

Should you have any questions, please contact Mr., Rick J. King at

(504)381-4146.

Sincere y,

-

'g/(/!v

l

4 ohm

g

J. C. Deddens

Senior Vice-president

l

River Bend Nuclear Group

Attachments (Safeguards)

,

.. . - . . . . . . . . _ .

.

cc: Mr. LRobert D. Martin, Regional Administrator

U.S. Nuclear Regulatory Commission

.

611 Ryan Plaza Drive, Suite 1000;

Arlington.TX76011l

'

..

,

NRC Resident Inspector (w/o attachment)

THIS PAGE NOT SUBJECT TO PROTECTIVE REQUIREMENTS WHEN SEPARATED

FROM MATERIAL CONTAINING SAFEGUARDS INFORMATION.

- _ _ _ _ - _ _ _