l l-Mr. Lee Liu.
May 14; 1998~
Chrirmin of th3 Boird and Chief Executive Officer '
IES Utilities Inc.
200 First Street, SE.-
- P.O. Box 351 ~
Cedar Rapids, IA 52406-0351 l
SUBJECT:
- REQUEST FOR ADDITIONAL INFORMATION ON GENERIC LETTER 9744,
" ASSURANCE OF SUFFICIENT NET POSITIVE SUCTION HEAD FOR l
EMERGENCY CORE COOLING AND CONTAINMENT HEAT REMOVAL l.
PUMPS," - DUANE ARNOLD ENERGY CENTER (TAC NO.' M99987)
Dear Mr. Liu:
~
The staff issued Generic Letter 97-04, " Assurance of Sufficient Net Positive Suction Head for Emergency Core Cooling and Containment Heat Removal Pumps," on October 7,1997. The GL requested that licensees provide information necessary to confirm the adequacy of the net
' positive suction head available for emergency core cooling and containment heat removal pumps. By letter dated January 5,1998, you submitted the 90-day response to GL 97-04 for the Duane Amold Energy Center. The staff has reviewed your retoonse and has determined that additional information is necessary. Please provide the information in the attached request within 30 days from the date of this letter.
If you should have any questions regarding this request, please contact me at (301) 415-1373.
.l Sincerely, Original signed by:
Richard J. Laufer, Project Manager Project Directorate lll-3 Division of Reactor Projects lil/IV j
Office of Nuclear Reactor Regulation Docket No. 50-331
Enclosure:
' As stated
~
. cc w/ encl.:' See next page Distribution :
Docket File I
~ PUBLIC KKavanagh PD3-3 Reading RBellamy-EAdensam(EGA1). OGC GGrant, Rlli ACRS
- DOCUMENT NAME: G:\\DUANEARN\\DA99987.RAI.
l
. To receive a copy of this document, indicate in the box: "C" = Copy without enclosures L
~ "E" = Copy with enclosures "N" = No copy-(
l OFFICE PM:PD33 -
0 LA:PD33 6
SR$(NRR l'" SCSBMRiis l
NAME.
RLaufer P EBamhill 8(tr" SCarus4 JKudri'cl(\\d g DATE
$/8198/f/i/6 -
5/6/98 3 /(2,/98 '
9/ LV98W V\\
'0FFICIAL:RECORDCOPYpfll l
)
1
- = a== aap=P pgg AgCETHEB ggpy 9eosaooa6a voosto m
Mr. Leo Liu M y 14, 1998 Chairman of ths Bo::rd end Chi f Exscutivo Officer IES Utilities Inc.
200 First Street, SE.
P.O. Box 351 Cedar Rapids, IA 52406-0351
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION ON GENERIC LETTER 97-04,
" ASSURANCE OF SUFFICIENT NET POSITIVE SUCTION HEAD FOR EMERGENCY CORE COOLING AND CONTAINMENT HEAT REMOVAL PUMPS," - DUANE ARNOLD ENERGY CENTER (TAC NO. M99987)
Dear Mr. Liu:
The staff issued Generic Letter 97-04, " Assurance of Sufficient Net Positive Suction Head for Emergency Core Cooling and Containment Heat Removal Pumps," on October 7,1997. The GL requested that licensees provide information necessary to confirm the adequacy of the net positive suction head available for emergency core cooling and containment heat removal pumps. By letter dated January 5,1998, you submitted the 90-day response to GL 97-04 for the Duane Amold Energy Center. The staff has reviewed your response and has determined that additionalinformation is necessary. Please provide the information in the attached request within 30 days from the date of this letter.
If you should have any questions regarding this request, please contact me at (301) 415-1373.
Sincerely, Original signed by:
Richard J. Laufer, Project Manager Project Directorate ill-3 Division of Reactor Projects Ill/IV Office of Nuclear Reactor Regulation Docket No. 50-331
Enclosure:
As stated cc w/ encl.: See next page Distribution :
Docket File PUBLIC KKavanagh PD3-3 Reading RBellamy EAdensam(EGA1)
OGC GGrant, Rlil ACRS DOCUMENT NAME: G:\\DUANEARN\\DA99987.RAI To receive a copy of this document, indicate in the box: "C" = Copy without enclosures "E" = Copy with enclosures "N" = No copy
(
OFFICE PM:PD33 C
LA:PD33 6
SR$(NRR P, SCSBMRRs NAME RLaufer p/
EBarnhill 8y F3Caius'b JKudri'ck\\d e DATE
$/8198/f/i/4i 5/8/98 S /\\l/98 T /iL/98 % W \\
0FFICIALRECORDCOPYpl[l
~'I p'
en 44 g
gw UNITED STATES j
l g
j NUCLEAR REGULATORY COMMISSION 2
WASHINGTON, D.C. 30866 0001
\\...../
May 14, 1998 l
l Mr. Lee Liu I
Chairman of the Board and Chief Executive Officer IES Utilities Inc.
200 First Street, SE.
P.O. Box 351 Cedar Rapids, IA 52406-0351
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION ON GENERIC LETTER 97-04,
" ASSURANCE OF SUFFICIENT NET POSITIVE SUCTION HEAD FOR EMERGENCY CORE COOLING AND CONTAINMENT HEAT REMOVAL PUMPS," - DUANE ARNOLD ENERGY CENTER (TAC NO. M99987)
Dear Mr. Liu:
The staff issued Generic Letter 97-04, " Assurance of Sufficient Net Positive Suction Head for Emergency Core Cooling and Containment Heat Removal Pumps," on October 7,1997. The i
GL requested that licensees provide information necessary to confirm the adequacy of the net i
positive suction head available for emergency core cooling and containment heat removal pumps. By letter dated January 5,1998, you submitted the 90-day response to GL 97-04 for the Duane Amold Energy Center. The staff has reviewed your response and has determined that additional information is necessary. Please provide the information in the attached request within 30 days from the date of this letter.
If you should have any questions regarding this request, please contact me at (301) 415-1373.
Sincerely, Richard J. Laufer, Project Manager Project Directorate lil-3 Division of Reactor Projects Ill/IV Office of Nuclear Reactor Regulation Docket No. 50-331
Enclosure:
As stated cc w/ encl.: See next page
i Lee Liu Duane Arnold Energy Center IES Utilities Inc.
cc:
l Jack Newman, Esquire Kathleen H. Shea, Esquire Morgan, Lewis, & Bockius i
1800 M Street, NW.
Washington, DC 20036-5869 i
Chairman, Linn County Board of Supervisors Cedar Rapids, IA 52406
\\
IES Utilities Inc.
ATTN: Gary Van Middlesworth Plant Superintendent, Nuclear 3277 DAEC Road Palo,IA 52324 John F. Franz, Jr.
Vice President, Nuclear
)
Duane Arnold Energy Center 3277 DAEC Road Palo,IA 52324 Ken Peveler Manager of Regulatory Performance Duane Arnold Energy Center 3277 DAEC Road Palo,IA 52324 U.S. Nuclear Regulatory Commission Resident Inspector's Office Rural Route #1 Palo,IA 52324 Regional Administrator, Rll!
U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4531 Parween Baig Utilities Division Iowa Department of Commerce Lucas Office Building,5th floor Des Moines,IA 50319
e I
REQUEST FOR ADDITIONAL INFORMATION GENERIC LETTER 97-04 l
l
- 1. Have all the errors found in the NPSH analyses been corrected?
- 2. When will the new containment pressure and temperature analysis be complete?
l
- 3. The staff believes that the Duane Amold licensing basis needs to be clarified with regard to l
credit for containment overpressure, especially since the potential exists that an increased reliance on containment overpressure will be needed to resolve Bulletin 96-03 issues. What i
l are your plans / schedule for clarifying the licensing basis?
I l
l l
l l