Summarizes 890822 Meeting W/Util in Region IV Ofc to Discuss Results of INPO Evaluation of Facility.List of Attendees Encl
ML20247C308
Person / Time
Site: River Bend Entergy icon.png
Issue date: 09/01/1989
From: Milhoan J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Deddens J
GULF STATES UTILITIES CO.
References
NUDOCS 8909130320
Download: ML20247C308 (4)


Text

___

.. SEP ' 1 -- 1989 t

'In Reply Refer.To:

, Docket: - 5 % 458 Gulf States Ut111 ties ATTN: Mr. Jana s C. Deddens Senior + ice President (RBNG)

P.O. Box 220 St. Francisv111e, Louisiana 70775 Gentlemen:

.This refers to the meeting conducted in the Region IV office on August 22, 1989. This meeting related to activities ~ authorized by NRC License No. NPF-47 for River Bend Station and was attended by those . listed on the attached attendance list.

The topics covered during your presentation are described in the enclosed

. meeting ~ summary.

It is.our opinion that this meeting was beneficial and provided a better understanding of the issues discussed.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations, a copy of this letter will be placed in the NRC's Public Document Room.

Should you have any questions concerning this letter, we will be pleased to discuss them with you.

Sincerely,

. Origina! Signed By:

Thomas P. Gwynn James L. Milhoan, Director Division of Reactor Projects

Enclosure:

Meeting Summary cc:

Gulf States Utilities ATTH: J. E. Booker, Manager-River Bend Oversight P.O. Box 2951 Beaumont, Texas 77704 RIV:DRP/Cf;h*)

GLMadsen;df C:

G P DRPH 9 ble yJLMilhoan h

8/30/89 8 /89 jX/1/89 q F gg 8909130320

'DR 890901 ADOCK 05000458 PDC

i V, ,j l 'b: , i 1

'E

. ~;l . ' h y ,l ; .l l ,% ,

$aj.f R ';;g(M@ , "'

4-f.[<-

s .- u ,. n f " ' -y ME

v 1 . a

-+..- ,

l-;. 4 m.

1:

P $ ' Gulf State's Utilit',es. -

g "'

i

.g

' Gulf- St'ates Utilities ' .

ATTN: Eles England Di&ctor

' Nuclear Licensing - RBNG

~

.P.O. Box'220 .

Sti Francisville, Louisiana '70775

' Louisiana State University.

Government Documents Department

.1.0%isiana. Radiation Control- Program Director M cg,ts & {1E46) * ***

bcc distrib'. bylRIV:

DRP . RRI R.1D. Martin,'RA . SectionChief(DRP/C) 1 .Lisa Shea,.RM/ALF MIS System RPB-DRSS' RSTS Operator

. Project Engineer (DRP/C)_ .

.RIV File.

W. Paulsori, NRR Project Manager (MS: 13-D-18) DRS

'4 L

T

. i ft I

. l.~i . I

a.

.[ p.s,-4 .

b ', { " '

  • L ,

1; yt i; . .

. i

v. ,

MEETING

SUMMARY

v Licensee:' - Gulf. States Utilities -

Facility: River Bend Station License'No.( NPF-47 Docket'No.: S0-458

Subject:

- Results of INP0 Evaluation On August 22, 1989, representatives of Gulf. States Utilities met with' Region IV personnel in Arlington, Texas, to discuss the results of a recent-INP0 evaluation of the River Bend Station. The lictnsee described the findings 11 n each. area, including the strengths and weaknesses that were identified by the team._ -The NRC ' representatives thanked GSU for the information briefing. , The attendance list is attached to this sunnary.

Attachment:

Attendance List'

I l

Q=_: _ = _-- _ - - :_ - - -_

- m,m , , . , . . , . . .

.,j - ,. ,

.tw. < pe ; ;g

,- : Vc . .. * :.4 !' t -

~'

[ J . ;., . _.

.l..

gl I

'  ?

.. .s ATTENDANCE LIST.

t

Attenciance at' the Gulf States Utilities (GSU)/NRC meeting on August 22, 1989, at-L
the NRC Region IV office

1 GSU --

~ J. E. Booker, Manager, River Bend Oversight

.T. F. Plunkett, Plant Manager.

I NRC j.

l

' J. L.- M11hoan, Director, Division of Reactor Projects (DRP)-

A. B.l Beach, Director, Division of Radiation Safety and Safeguards i J. P. Jaudon, Deputy Director, Division of Reactor Safety-F - G. L. Constable, Chief, Reactor. Project Section C DRP.

Ih h

.. . . = _ _ _ _ - _ _ - _ _ _ - _ _ _ - _ _ . _ . _ _ .