t I
GPU Nuclear Corporation NUC MF One Upper Pond Road Parsippany, New Jersey 07054 201-316-7000 TELEX 136-482 Writer's Direct Dial Numbet August 30, 1989 5000-89-1813 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555 Gentlemen Subjects Oyster Creek Nuclear Generating Station Docket No. 50-219 Mark 1 Containment Long Term Program Torus Attached Piping Refc ence: 1)
MPR-999, Revision 3, December 1988
" Addendum to MPR-734, Plant Unique Analysis Report, Torus Attached Piping" 2)
GPU Nuclear letter (No. 5000-88-1647) to the NRC dated October 14, 1988 The enclosed report (Reference 1) documents reanalyses of torus attached piping systems at Oyster Creek. This report supercedes Revision 1 which was forwarded by Reference 2.
MPR 999, Revision 1, documented the calculated stress results for two specific piping locations (location H in Figure 2.1-1; location A in Figure 2.2-2) where Code allowables were slightly exceeded for certain Mark I loading combinations. These calculated overstresses were judged co be acceptable based on known conservatism in the analysis methodology.
GPU Nuclear (GPUN) concluded there would be no actual overstresses.
The acceptability of the calculated overstresses was questioned by the NRC during Inspection 88-15.
GPUN submitted a letter dated June 1, 1988 and provided further infor nation during a meeting at the NRC Region I of fices on July 26, 1988. At the meeting, GPUN presented preliminary results of more accurate analyses indicating Code allowables are met.
MPR 999, Revision 3, enclosed, provides the results of the reanalyses. The results confirm the adequacy of our judgement concerning the overstresses calculated originally and documented in MPR 999, Revision 1.
l l
89090so2eo e90eso Ago;
{DR ADOCK 03000219 is FDC I \\
GPU Nuclear Corporation is a subsidiary of General Public Utilities Corporation j
T2rua AttachXd Piping L
'Page 2 MPR 999, Revision 3, is submitted for information as committed to by GPUN at the July 26, 1988 meeting and in our response (dated September 19, 1988) to the notice of violation associated with Inspection 88-15.
Very tr ly yours, i
/
[h#)$/d
. K. 'Oroneberger Acting Director Technical Functions DKC/PC/lml Enclosure cc: Administrator Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 NRC Resident Inspector Oyster Creek Nuclear Generating Station Forked River, NJ 08731 Kr. Alex Dromerick U.S. Nuclear Regulatory Commission Mail Station P1-137 Washington, DC 20555