ML20246N778

From kanterella
Jump to navigation Jump to search
Forwards Emergency Preparedness Program Appraisal Insp Repts 50-445/89-43 & 50-446/89-43 on 890605-09.Apps a & B Contain Inclusive Listing of All Outstanding Onsite Emergency Prepardness Items
ML20246N778
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 08/30/1989
From: Warnick R
Office of Nuclear Reactor Regulation
To: William Cahill
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
Shared Package
ML20246N784 List:
References
NUDOCS 8909080262
Download: ML20246N778 (7)


See also: IR 05000445/1989043

Text

__ - .

. _ .

. _ .

_

_-

fR'i+

4' - A

AUG 351989

'

In Reply Refer:To:

' Dockets: '50-445/89-43

50-446/09-43

,

TV Electric

- ATTN:

W. J. Cahill, Jr., Executive

..

-Vice President

Skyway Tower

400 North Olive, L.B. 81

Dallas,-Texas 75201

~ Gentlemen:

SUBJECT: EMERGENCY-PREPAREDNESS APPRAISAL

During the period of June 5-9, 1989, NRC conducted an appraisal of the -

emergency preparedness program at the Comanche. Peak Steam Electric Station.

.The appraisal was performed by a team of inspectors and contractors with

Mr. Nemen M.' Tere as Team Leader. The objective of the appraisal was to

evaluate the' overall" adequacy and effectiveness of the licensee's onsite

emergency.. preparedness program and to identify areas of weakness that need to

be strengthened. Areas examined in this appraisal are described in the

. enclosed report. .Within these areas, the appraisal. team reviewed selected

procedures and representative records, inspected emergency facilities and

equipment, and interviewed personnel.

The findings of this emergency preparedness appraisal indicate that certain

corrective actions are required in your emergency preparedness program. These

are discussed in Appendix A, "Significant Appraisal Findings." Appendix B,

" Emergency Preparedness Improvement Items," contains'other findings which are

of lesser significance then those of Appendfx A, but which may require

corrective measures.

Appendices A and B of this letter contain an inclusive listing of all

. outstanding onsite emergency preparedness items at your facility at the time of

the appraisal. The findings of the prior emergency preparedness appraisal,

conducted during the period September 26 through October 7, 1983, are

considered closed since the present appraisal replaced those findings.

We recognize that in addition to applicable regulatory requirements, other

criteria were used to make a determination of adequacy, such as nuclear

industry standards and professional judgement, for which no explicit regulatory

requirement may currently exist. Notwithstanding this, you are requested to

submit a written statement within 30 days af ter receipt of this letter,

describing your planned actions for correcting each of the items contained in

-Appendix A and the results of your consideration of each of the items in

EIV SEPS

C:SEPS

C:RPB

D:DRSS

NRR ppg

  • NMTerc
  • DAPowers
  • BMurray

BBeacidj'

RWarh'ick

/ /89

/ /89

/ /89

3 /p/87

P/Rf/89

  • previously concurred.

(

/

I

)

8909080262 890830

PDR

ADOCK 05000445

d/

O

PDC

Y

'

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

57

. .

- . .

s - 0 v.,;

~, k !

, ' S::

'

-

V

..

L

LTU' Electric.

-2-

l

Should you.have any questions concerning this' inspection, we will.be pleased to

discuss them with you.

Sincerely,

Orlglnal Signed By,

u

R. F. Warnick, _ Assistant Director

for Inspection Programs 1

Comanche Peak Project. Division-

Office of Nuclear Reactor Regulation

Enclosures:

.

.

1.

Appendix A - Significant

Appraisal Findings

2.

Appendix'B -1 Emergency

Preparedness ~ Improvement Items

3. ' Appendix C - NRC Inspection Report-

50-445/89-43

50-446/89-43'

cc w/ enclosures:

TV Electric

ATTN:

Roger D. Walker, Manager,

Nuclear Licensing

h

S kyway. Tower

1400 North Olive Street, L.B. 81

Dallas, TX 75201

Juanita Ellis

President - CASE

- 1426 South Polk Street

Dallas, TX~ 75224

GDS Associates, Inc.

Suite 720

.

-1850 Ptrkway Place

Marietta, GA 30067-8237

Susan M. Theisen

Assistant Attorney General

,

Environmental Protection Division

.P.O. Box 12548, Capitol Station

Austin, TX 78711-1548

Fulbright & Jaworski

. ATTN: Joseph' F. Fulbright

1301 McKinney Street

Houston, TX 77010

_ - _ _ _ _ _ _ _ _ _ -

_ _ _ _ _ _ _

.

,

_ ,_

..

, -:$./. ': /

-

w.

,.f

s '.:

<

, . - i

.TU Electric

-3-

- p:

Senior Citizens Alliance of:Tarrant -

1'

. County,;Inc.

.

ATTN: : George A. Parker, Chairman

!

Public Utility Committee.

6048 Wonder Drive

< Fort Worth, TX- 76133

-Heron, Burchette, Ruckert, & Rothwell

ATTN: William A. Burchette, Ern.

Counsel for Tex-La' Electric

.1025 Thomas' Jefferson St. , N.W.

Washington, DC 20007-

E; F. Ottney

'P.O. Bc,x 1777

Glen Rose, TX 76043

Newman & Holtzinger,-P.C.

ATTN: Jack R. Newman, Esq.

.1615 L.--' Street, N.W.

Washington, D.C.

20036

' Chief, Technological Hazards Branch

-

FEMA Region 6-

Federal Center

800; North Loop 288

'Denton, Texas' 76201-3698

bec dist, by-RIV:

CPPD:0SP Reading _(MS:

7-H-17)

  • RIV Files.

.

Local PDR

ADSP Read'ng (MS: 7-D-24)

  • Site Reading File
  • MIS-System, RIV-

NRC-PDR --

'*RSTS Operator

_

  • DRP
  • L.,Shea, ARM /LFMB

J. Dyer, NRR

P. McKee,.OSP'

J. Lyons, OSP

J. Wilson, ADSP, NRR

M. Malloy, DSP

J._ Moore, OGC-WF_

J. Gilliland

M. Fields, OSP

E. Jordan

.

. B.' Grimes, NRR-WF

B. Hayes

  • R.. Martin
  • RPB-DRSS

D. Crutchfield, OSP-

  • R. Warnick, CP

'*J) Wiebe, CP

  • H. Livermore, CP

CPPD-LA, OSP

C. Grimes, OSP

  • w/766

L

L

. . .

_--

__

-'

t ..

.

s

,

9:.

.

APPENDIX A

SIGNIFICANT APPRAISAL FINDINGS

L

Improvements in the following areas are required to achieve an adequate-

'

program:

'-

Review the description of your emergency organization and revise it as

necessary to provide a clear depiction of all emergency functions required

during initial, intermediate, and final phases of augmentation and

l

recovery; update the Site and Corporate Emergency Plans to describe the

updated organization; revise and issue implementing' procedures which have

I

been human engineered so that all emergency response tasks can be carried

out using the command and information pathways of the organization. The

. updated description of the emergency or3..:dva+1on should include a

-

sufficient level of detail:

clearly specify the command hierarchy, its

structure, reporting chains and interrelationships at any phase of

augmentation, and include supervisory as well as non-supervisory elements.

(See Section 2.0 of the Appraisal Report.)

'

Remove dose assessment responsibilities from the shift technical

advisor (STA) in order to comply with the intent of NUREG-0737,

Appendix C.

(Section2.0)

Complete training for emergency response personnel including any training

associated with'the completion of. emergency systems and related

procedures.

(Section 3.0)

' -

Review and revise. training requirements to include pt ctical, hands-on

training, and drill participation.

(Section 3.0)

Develop specific qualification requirements for each position in the

emergency response organization.

(Section 3.0)

Complete the 'nsta11ation and testing of instrumentation, systems, and

'

controls in t .e control room that are required to assess plant and

environmental conditions.

(Section 4.1.1.1)

Complete the installation of Technical Support Center (TSC) equipment.

(Section 4.1.1.2)

Complete the setup of the multichannel analyzer and NaI detector

for counting environmental samples.

(Section 4.1.1.5)

Assemble medical kits containing key medical supplies for emergency

~'

response personnel who would respond as part of the first-aid team.

(Section 4.1.2.2)

Provide decontamination supplies in decontamination facilities.

(Section 4.1.2.3)

.

.

_-_________.-________.____m___

_ . . _ _________

%-

-

['

6"

..

?

^

..

l.y

2

7

Revise Procedure EPP-207 to provide _ specific instructions as to the riews

media and offsite agencies to be contacted initially for the dissemination

.of information to the.public.

(Section4.1.4)

~

  • ~

Complete the news media seminar providing the news media with the utility

points of contact and locations where accident information can be

obtained. .'(Section 4.1.4)

'

Complete the training of the CPSES staff on their duties in the. News

Center and dissemination of information to the.public.

(Section 4.1.4)

l

Complete the installation, testing, and turnover of.the Digital Radiation

  • -

-Monitoring System (ORMS), and cf.afirm that instrument maintenance and

calibration. checks are performed in accordance with applicable

. requirements. -(Section 4.2.1.2)

Complete the installation, testing, and turnover of non-radiation

monitoHng systems.

Initiate appropriate preventive maintenance checks on

- the systems and conduct appropriate training on operation, analysis, and

distribution of data obtained from the systems.

(Section 4.2.1.3)

Complete the construction and installation of +.he primary meteorological

tower and related equipment.

(Section 4.2.1.1)

Complete the review.and revision of the Emergency Action

Level (EAL)/ Emergency C1s sification procedure.

(Section 5.1)

Revise procedures to assign a staff member other than the STA to perform

dose assessment functions until the control room is relieved of the

function by the TSC. (Section 5.1):

Revise Procedure EPP.-304 to add guidance for daveloping offsite

-PARS based on operational assessment of plant conditions.

Incorporate, in Procedure EPP-304, a oecisionmaking aid such as the

" logic tree" shown in IE Information Notice 83-28, Figure 1, " Flow

Chart for General Emergency Offsite Protective Decisions." Delete,

from Procedure EPP-304, those considerations (such as weather,

special facilities, and population distributions) that are not

germane to effectively developing and recommending a protective

action. Revise Procedure EPP-304 to eliminate the need to discuss

PARS with the state or counties until after the PARS are made to

offsite agencies.

(Section 5.3)

Demonstrate that the evacuation of the owner-controlled area (OCA),

including all buildings, can be accomplished in c thorough and timely

manner. (Section 5.4.3.2)

Demonstrate the capability of performing personnel accountability of

all personnel within the protected area within 30 minutes.

(Section 5.4.3.3)

Modify training materials to incorporate PARS based on core and

containment conditions and retrain all personnel having responsibilities

.to formulate PARS.

(Section 7.1.5)

______-____________- _ _ _ __ -

-

..

-

'

.

.

,

,

.

APPENDIX B

IMPROVEMENT ITEMS

The following matters are considered improvement items:

Position the required, dedicated emergency equipment in the Operations

Support Center (OSC) or provide assurance that all required equipment will

be properly located in the event of an emergency.

(See Section 4.1.1.3 of

the Appraisal Report.)

Install an ingestion pathway map to assist in monitoring the efforts of

o r site authorities responsible for defining the extent of long term,

/ / site radiological conditions.

(Section 4.1.1.4)

Maintain first-aid supplies in an orderly fashion.

(Section 4.1.2.2)

Review and revise Section 10.2 of the Emergency Plan to reflect the

correct location of the onsite first-aid supplies and that Hood General

Hospital Ambulance Service is the primary ambulance service, and complete

the turnover of the ambulance service from the contractor.

(Section 4.1.2.2)

Review and revise Section 6.9 of the Emergency Plan to list the electrical

and control building as the location of the decontamination facility in

the plant rather than the turbine building.

(Section 4.1.2.3)

Include the correct storage locations of emergency kits in procedures.

(Section 4.2.1.1)

Mark spare batteries with shelf life expiratior, dates to permit persons

performing inventories to readily deterrine if supplies are adequate.

(Section 4.2.1.1)

Provide potassium iodine (KI) tolerance testing for emergency responders.

(Section 4.2.1.1)

Assure that proper physical units are available at local instrument

channel racks for emergency radiation monitors read-outs.

(Section 4.2.1.2)

[

Install protective dust caps / thread protectors on spare self contained

breathing apparatus (SCBA) bottles.

(Section 4.2.2.1)

Initiate periodic testing as appropriate for all emergency communication

systems; review and revise procedures to require periodic testing of all

emergency communication systems and increase the FM radio capability at

the TSC to permit monitoring of emergency channels. (Section 4.2.3)

Correct administrative errors and discrepancies ir, emergency procedures.

(Section 5.1)

1

___--__

, . . .

',

'4

.I,.'

,

9

'o.

(

..

.

.

.

,,

~2-

'

Review the alarm response procedures (ALPS) and include appropriate

references to Procedure EPP-201.

(Section 5.2)

Correct inconsistencies in referencing the EP in abnormal conditions

procedure. (Section 5.2)

'

Enhance the emergency dose assessment program with a segmented plume

- atmospheric dispersion model that will take wind shifts into account.

(Section 5.4.2.1)

Complete the documentation of the Xu/Q values using the dose assessment model

and document these values into procedures'.

(Section 5.4.2.1)

Delete the reference to the calculation of total population dose from

Procedure EPP-206.

(Section 5.4.2.1)

Ensure that units on ihe DRMS monitors used for dose assessment

calculations are consistent with those in the RM-11 system, and the dose

assessment.model.

(Section 5.4.2.1)

Revise Section 7.3.2 of'the Emergency Plan to indicate the actual

communication link between emergency facilities and the offsite monitoring

. teams. (Sc: tion 5'.4.2.2)

Develop a procedure for the routine maintenance and operability check on

the NaI detector system, and develop a procedure to describe counting -

procedures for environmental samples and the activation of the counting

laboratory. (Section 5.4.2.2)

Provide icgible maps showing environmental thermoluminescent

dosimeter (TLD) locations in Procedure EPP-309, including specific

descriptions on how to reach these locations.

(Section 5.4.2.5)

Consider issuing dosimetry to personnel as they ed er the Emergency

,

Operations Facility (EOF).

(Section 5.4.3.1)

'

Review and revise Procedure EPP-313 to specify the use of emergency

medical technicians (EMTs) as first-aid team members.

(Section 5.4.3.5)

Update the Letters of Agreement with the offsite support agencies.

(Section 6.0)

1

Prepare a matrix that would indicate what offsite agencies are to be

trained, the subject to be trained on, and the status of completion.

,

(Section 6.0)

Review the materials for EAL training and revise, as necessary, to ensure

that control room decisionmaking personnel fully understand the

application of the " fire" EAL. (Section 7.1.2)

~

Revise Procedure EPP-303 to include instructions for using a default

release rate based on the most likely containment failure mode.

(Section7.1.4)

- _ -___ _ ____ _ _ _ -

___

__-

-

_

_

_

. _ _ _

'

f.

..

,

z...

.

j

.

APPENDIX C

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

NRC Appraisal Report:

50-445/89-43

Construction Permits: CPPR-126

'

50-446/89-43

CPPR-127

Dockets: 50-445

50-446

Applicant: .TU Electric

400 North Olive, L.B. 81

Dallas, Texas 75201

'

Facility Name: Comanche Peak Steam Electric Station (CPSES)

Appraisal At: Comanche Peak Site, Glen Rose, Texas

Appraisal Conducted: June 5-9, 1989

Lead

Appraiser:

~

A

.

8- /.f-PT

-

-

Nemen M. Terc, NRC Team Leader

Date

Personnel:

R. 'J. Everett, Chief, Nuclear Materials

Licensing Staff, NRC, Region IV

R. T. Hogan, Emergency Preparedness Analyst,

NRC, NRR

A. B. Earnest, Security Specialist, SEPS

NRC, Region IV

D. H. Schultz, Engineer, Comex Corporation

G. A. Stoetzel, Senior Research Scientist

Pacific Northwest Laboratories

M. N. Stein, Engineer, Sonolex Corporation

Approved:

M

b/

@

Dr. D. A. Powers, Chief, Security and

Date

Emergency Preparedness Section

Ay raisal Conducted June 5-9, 1989 (Report 50-445/89-43; 50-446/89-43)

Areas-Appraised and Approval Summary

.

Special, announced emergency preparedness program appraisal to determine the

adequacy of the applicant's program.

8909080265 890830

PDR

ADOCK 05000443

Q

PDC

_ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ . _ _ _ _ _ _ _

-

_ _ -

. _ _

>

'

.

,

.

-

-2-

The appraisal of the onsite emergency preparedness program at Texas Utilities

Electric Company's (TUCO) Comanche Peak Electrir Steam Station included seven

general areas:

administration of the emergency preparedness program, emergency

organization, emergency training, emergency facilities and equipment,

procedures which implement the Emergency Plan, coordination with offsite

agencies, and walk-throughs of emergency duties.

A review of the applicant's emergency organization showed that although the

applicant had identified several organizational response elements, improvements

were needed to further clarify duties and responsibilities, and to provide an

organizational structure consistent with each emergency response task.

A review of the emergency preparedness training program showed that the program

had been established, but qualification requirements for each task or position

were not clearly specified and practical training was not required. A large

portion of the training had been performed for the emergency responders, but

the status of completion of some systems will require further training for

personnel operating such systems.

In addition, some organizational elements

had not received training consistent with their duties during emergencies.

Those portions of emergency response facilities (ERFs) that had been completed

were basically satisfactory; however, some facilities were still in various

stages of completion, and equipment and supplies were not completely in place.

Personnel accountability and evacuation of the protected areas (pas) and the

owner-controlled areas (OCAs) have not been demonstrated. The applicant has a

unique situation in these areas due to the large number of workers in the pas

and OCAs.

Specific deficiencies were found in some procedures, mainly in the procedure

used for making protective action recommendations (PARS), including the absence

of operational assessment of plant conditions, and the inclusion of extraneous

considerations which may have an impact on the efficient release of PARS.

.The appraisal team concluded that the applicant has made a strong commitment to

the emergency preparedness program. However, the findings identified in

Appendix A to this report need to be corrected in order for the applicant to

have an adequate emergency preparedness program.

-

)

i

,

l

i

I

. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _

.-

... ,

.

.

.

1

-

i

'

CONTENTS

PAGE

1.0 ADMINISTRATION ................................................ 4

2.0 EMERGENCY ORGANIZATION ........................................ 4

3.0 T RA I N I N G . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

i

'

4.0 EMERGENCY FACILITIES AND EQUIPMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

.

4.1 Emergency Facilities ..................................... 7

L

4.1.1 As s e s sme nt Fa ci l i ti e s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

4.1.1.1

Control Room ............................. 7

4.1.1.2 Technical Support Center ................. 8

4.1.1.3

Operations Support Center ................ 8

4.1.1.4

Emergency Operations Facility ............ 9

4.1.1.5 Offsite Laboratories ..................... 9

1

4.1.2

Protecti ve Faci li ti e s . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

4.1.2.1

Assembly / Reassembly Areas ............... 10

4.1.2.2 . Medical Treatment Facilities ............ 10

4.1.2.3

Decontamination Facilities .............. 11

4.1.3 Expanded Support Facilities ...................... 12

4.1.4 News Center, Public Information, and News Media .. 12

4.2 Emergency Equipment ..................................... 13

4.2.1 Assessment Equipment ............................. 13

4.2.1.1

Emergency Kits and Emergency Survey

Instruments ............................

13

4.2.1.2

Emergency Monitoring Systems ............ 14

4.2.1.3

Nonradiation Process Monitors .,......... 15

4.2.1.4

Meteorological Instrumentation .......... 15

,

_ _ - _ . _ _ - _ - _ - - _ - _ _ - _ -

_

_ _ _ - _

_ _ _ .

k f.,

g, :

p

-

,,.

-2-

.

.

s.

.

p

'4.2.2

Protective Equipment ............................. 15'

4.2.2.1

Respiratory Protection .................. 15

l

.4.2.2.2

Protective Clothing ..................... 16

.

4.2.3 Communications .................................... 16

'

_

4.2.4 Damage Control / Corrective Action ................. 17

4.2.5_ Reserve Emergency Supplies and Equipment ......... 18

4.2.6 Transportation .................................... 18

5.0 EMERGENCY ~ IMPLEMENTING PROCEDURES ............................ 18

'5.1

General Content and Format .............................. 18

5.2 . Emergency, . Alarm, and Abnormal Occurrence Procedures .. . . 20

5.3 Implementing Instructions ............................... 21

5.4 Implementing Procedures ................................. 22

5.4.1 Notifications .................................... 22

5.4.2 Assessment Actions ............................... 23

5.4.2.1

Dose Assessment ......................... 23

5.4.2.2

Offsite Radiological Surveys ............ 24

5.4.2.3

Onsite (Out-of-Plant) Radiological

Surveys .................................. 25

5.4.2.4

In-Plant Radiological Surveys ........... 25

5.4.2.5

Radiological.and Environmental Monitoring.

Program ................................. 26

5.4.3 Protective Actions ............................... 26

5.4.3.1

Radiation Protection During Emergencies . 26

5.4.3.2

Evacuation of Owner-Controlled Areas .... 27

5.4.3.3

Personnel Accountability ................ 27

5.4.3.4

Personnel Monitoring and Decontamination ~.28

5.4.3.5 Onsite Fi rst-Aid / Rescue . . . . . . . . . . . . . . . . . 28

_ _ _ _ _ _ _ _ _ - - _ _ _ .

_ _ - - _ _ - -

_ - _ .

[ , .. s

..t,

. . ,

J.

.

,

..e

i

. 1

,

-3-

5.4.4 Security During Emergencies ....................... 29

5.4.5 Repair / Corrective Action ......................... 29

5.4.6 R e c o v e ry . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . 2 9

5.5 Suppl ementa ry Procedure s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30

5.5.1

Inventory, Operational Check, and Calibration of

Eme rg e n cy Eq u i pme n t . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30

5.5.2 Drills and Exercises ............................. 30

5.5.3 Review, Revision, and Distribution ............... 30

5.5.4 Audits of Emergency Preparedness ................. 31

6.0 - COORDINATION WITH OFFSITE GROUPS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31

7.0 DRILLS, EXERCISES, AND WALK-THROUGHS ......................... 32

7.1 Wa l k-Th ro u g h Ob s e rva t i o n s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32

7.1.1

Eme rg e n cy De tecti o n . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 3

7.1.2 Emergency Cl a ssi ficati on . . . . . . . . . . . . . . . . . . . . . . . . . 33

7.1.3 Notification ..................................... 33

7.1.4 Do se Cal cul ati on s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34

7.1.5 Protective Action Decisionmaking ................. 34

7.1.6 Offsite, Onsite, and In-ilant Radiological

Monitoring ....................................... 35

8.0 EX I T M E ET I NG . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 5

9.0 PERSONS CONTACTED ............................................ 36

.

._______.-___._.___.__m___--

- _ _ _ _ . _ _ _ . _ _ _ . _ _

_

__

.

. , . .

x

.

'

-4-

.

.

.

,,

DETAILS

1.0 ADMINISTRATION OF EMERGENCY PREPAREDNESS

The administration of the applicant's emergency preparedness program was

reviewed with respect to the requirements of 10 CFR 50, Appendix E,

paragraph IV.A; and the criteria contained in NUREG-0654, Sections II.A

and P.

The appraisal team reviewed responsibilities assigned for the

administration of emergency planning, including authorities given to the

emergency planning manager.(EPM); coordination with onsite and offsite

organizations, and members of the public.

In addition, the appraisal team

reviewed the selection and qualifications of the emergency planning staff;

held discussions with members of the staff; reviewed position descriptions

and individual qualifications; and reviewed in place training programs for

. ensuring that the' staff remains abreast of current developments in the

emergency preparedness area.

Based on the above findings, this portion of the applicant's program

appears to be adequate.

'2.0

EMERGENCY ORGANIZATION

.The appraisal team reviewed the applicant's emergency response

organization against the requirements of 10 CFR 50.47 and 10 CFR 50,

Appendix E, paragraph IV.A.

In addition, the appraisal team reviewed

CPSES Emergency Plan, Revision 10, dated July 27, 1988 (hereafter referred

to as the Emergency Plan or EP) and Emergency Plan Procedures (EPPs), and

held discussions with applicant personnel to evaluate the emergency

organization.

The EP considers three basic augmentation phases (i.e., staffing levels):

. initial, intermediate, and final augmentation. The initial phase consists

of the minimum staff operating the plant (i.e., in particular, during back

shifts). The intermediate phase comprises the fully staffed onsite

emergency organization, formed within about 60 minutes. The final

augmentation phase includes the first two staffing levels, plus additional

corporate staff and other support groups. A fourth recovery phase would

be entered after the reactor has stabilized and any significant releases

of radioactivity to the environment and any further potential for releases

has ceased. At that point, the applicant will implement an organization

designed to recover from the accident. The recovery phase will be further

discussed in Section 5.4.6.

The applicant's emergency organization is identified in Section 1 of the

EP. This included a description of the various phases of augmentation,

including organizational charts and lists of duties and respon'sibilities

for some of the organizational elements.

____ _ _ ___ _ _ _

_

_ _ - _ _ _

,

.

.,

.,

,

c

.

.

.

.

-5-

..

,

The appraisal team noted the following:

"

The EP failed to describe the functional breakdown of the initial

phase of the emergency organization consisting of the minimal staff

operating the plant. Emergency titles and specific duties of the

various organizational elements, including non-supervisory positions,

were lacking.

The applicant's organizational description did not include a block

diagram showing the chain of command and information flow for the

initial emergency phase.

The assignment of dose assessment responsibilities to the shift

technical advisor (STA) does not agree with NUREG-0737, Appendix C.

The STA is a critical element of the operations staff responsible for

technical support to operations during emergency conditions.

Dose

assessment responsibilities could prevent the STA from performing

primary operations duties assigned to the STA.

Although the EP described the general duties of some supervisory

elements (i.e., emergency coordinators [ECs]), specific details on

the organizational structure of the intermediate augmentation phase,

including a detailed functional breakdown for supervisory and

non-supervisory elements, were not provided.

The EP did not clearly present, by a separate organizational chart,

the organizational structure of the intermediate phase; including

lines of command, information flow, and interrelationships among

organizational elements.

The emergency organization chart (Figure 1.4) in the EP represents

the final augmentation phase due to the inclusion of corporate

support and emergency operations facility (EOF) activation. Again,

the description of the organization was obscured by the attempt to

represent three distinct phases of augmentation occurring at

different times, by one block diagram.

Procedures requiring the formal transfer of EC responsibilities from

the control room (CR) to the technical support center (TSC) or to the

EOF failed to indicate as a necessary condition that the ERF needs to

be fully activated for the EC to be able to adequately perform

duties.

The numbar of persons reporting directly to the EC appears to be

excessive. A study of the information flow patterns from and to the

EC would be needed to ensure that an excessive number of simultaneous

information inputs would not saturate the EC and result in deficient

coordination and control.

,

Based on the above findings, the following items are identified as

significant appraisal findings-

!

l

_

_ _ _ _ _ - _ . _

.

f

.

.

7

.

.

-6-

'

Review the description of your emergency organization and revise it

as necessary to provide a clear depiction of all emergency functions

required during initial, intermediate, and final phases of

augmentation and recovery; update the' site and corporate EPs to

describe the updated organization; and revise and issue implementing

procedures which have been human engineered so that all emergency

response tasks can be carried out using the command and information

pathways of the organization. The updated description of the

emergency organization should include a sufficient level of detail:

clearly specify the command hierarchy, its structure, and reporting

chains and interrelationships at any phase of augmentation, and

include supervisory as well as non-supervisory elements.

(445/8943-01; 446/8943-01)

o

Remove dose assessment responsibilities from the STA in order to

comply with NUREG-0737, Appendix C.

(445/8943-02; 446/8943-02)

3.0 TRAINING

The appraisal team reviewed the applicant's training program with respect

to the requirements of 10 CFR 50, Appendix E, paragraph IV.F and the

criteria contained in NUREG-0654, Planning Standard 0, and the training

and retraining requirements for individuals assigned emergency duties and-

responsibilities as outlined in Section 13 of the EP and described in

Procedure TRA-105, " Emergency Preparedness Training."

The appraisal team noted that the training program described the initial

training and annual retraining for specific categories of emergency

personnel, including personnel onsite and corporate support personnel, but

.

no qualification requirements were specified for each emergency position.

Personnel were assigned to the emergency organization based on their

supervisor's judgement and their regular duties.

The appraisal team noted that hands-on training or drills were.not used to

qualify emergency response personnel; however, instructors were aware of

the need to conduct practical hands-on training and drills, and as a

consequence, made attempts to perform this type of training immediately

after the classroom training for that module, even though the procedures

and lesson plans did not require it. The appraisal team found no written

requirement that an individual participate in a full-scale drill.

The appraisal team noted that the training program was being implemented

in accordance with the training manual; however, all training had not been

completed.

For example, 31 percent of the public information training,

and 58 percent of the cardiopulmonary resuscitation training were still

l

pending.

In addition, the appraisal team noted that completion of

emergency systems and related procedures will require additional training.

The appraisal team noted that the training records documented ~the status

of emergency personnel participation in hands-on training or drills

associated with specific classroom training modules.

Records of

participation in the full-scale drills were being added to the computer

_ - . _ _ _

_ _ -

.!

-

,,

-p

,

--

-7-

-

-

,.

.

training record system so that personnel without full-scale drill

experience could be identified.

Based on the above findings, the following items are identified as

significant appraisal findings:

Complete. training for emergency response personnel including any

'

training associated with the completion of emergency systems and

related procedures.

(445/8943-03; 446/8943-03)

Review and revise training requirements to include practical,

hands-on training, and drill participation.

(445/8943-04;

446/8943-04)

'

Develop specific qualification requirements for each position in the

emergency response organization.

(445/8943-05; 446/8943-05)

4.0 EMERGENCY FACILITIES AND EQUIPMENT

4.1 Emergency Facilities

4.1.1

Assessment Facilities

4.1.1.1

Control Room

The appraisal team reviewed the CR pursuant to the requirements of

10 CFR 50.47(b)(8); 10 CFR 50, Appendix E, paragraph IV.E; and the

criteria of NUREG-0654, Secticn II.H.

The appraisal team toured the CR to determine if updated copies of

the EP and the EP implementing procedures were in place; that the

emergency equipment specified in the EP was available and operable;

'and if the general status of completion of the CR would support

emergency preparedness operations.

In addition, the appraisal team

reviewed Procedure EPP-112, Revision 6. " Duties of Control Room

Personnel During Emergencies."

The appraisal team noted that several systems that would be used in

emergency operations, such as the Digital Radiation Monitoring

System (DRMS) (RM-11) and support systems such as CR heating,

ventilation, and air conditioning system (HVAC), were in various

stages of completion. Specifically, 80 of 96 channels of

instrumentation in the RM-11 had been installed and tested, and were

being controlled under the preventive maintenance program.

(The

remaining 16 channels were expected to be completed in late

August 1989. Duct-work modifications and other work being performed

in the CR HVAC system were expected to be completed and turned over to

the applicant in September 1989.)

,

Based on the above findings, the following item is identified

as a significant appraisal finding:

_ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _

__ -

_ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ -

...

- - . .

,

,

T&

..

-8-

Complete the installation and testing of instrumentation,

systems, and controls in the CR that are required to assess

plant and environmental conditions. (445/8943-06; 446/8943-06)

4.1.1.2

Technical Support Center (TSC)

The appraisal team reviewed the TSC pursuant to the requirements of

10 CFR 50.47(b)(8); 10 CFR 50, Appendix E, paragraph (IV)(E); and the

. criteria of NUREG-0654,Section II.H. .The appraisal team also

reviewed the EP and Procedure EPP-204, Revision 7, " Activation and

Operation of the TSC;" and supporting procedures for activities and

responsibilities of the TSC staff.

The appraisal team noted that the incomplete csndition of the CR

ventilation system affected the TSC in that the TSC ventilation

system is a part of the CR system.

The level of ongoing construction effort in the CR and TSC made

,

matters of general. housekeeping a concern, particularly in the

L

corridor and adjacent areas.

Dust and construction debris were noted

on various terminals, ERF computer, printers, and on shelves and

technical. manuals' in the TSC library.

Based on the above findings, the following item is identified as

a significant appraisal finding:

1E

Complete the installation of TSC equipment.

(445/8943-07;

'446/8943-07)

.

4.1.1.3

Operations Support Center (OSC)

1

L

The appraisal team reviewed the OSC and alternate OSC pursuant to the

l

requirements of 10 CFR 50.47(b)(8); 10 CFR 50, Appendix E,

l

paragraph IV.E; and the criteria in NUREG-0654,Section II.H.

The

appraisal' team also reviewed the EP and Procedure EPP-205,

" Activation and Operation of the Operations Support Center (OSC)."

The appraisal team noted that a telecopier was listed as required

equipment in the OSC to facilitate communications between ERFs.

However, the team learned that the machine was in routine use in the

maintenance building. The OSC emergency equipment list was not

annotated to reflect the actual location of the machine, and no

person was assigned the responsibility to transport the machine to

the OSC in the event of an accident.

Based on the above findings, the following matter is considered

an improvement item:

~

Position the required, dedicated emergency equipment in the OSC

or provide assurance that all required equipment will be

L

_

_ _ _

_

_ __

.

.,

_

. . .

.

,

.*

.

-

.g.

properly located in the event of an emergency.

(445/8943-08;

446/8943-08)

4.1.1.4

Emergency Operations Facility

The appraisal team reviewed the EOF with respect to the requirements

of 10 CFR 50.47(b)(8); 10 CFR 50, Appendix E, paragraph IV,E; and the

criteria in NUREG-0654,Section II.H.

The appraisal team reviewed

the EP and Procedure EPP-206, " Activation and Operation of the

Emergency Operations Facility (EOF)."

The appraisal team toured the EOF to assure that all equipment and

facilities specified by the EP were installed and operable. The

appraisal team noted that the facility was complete with all

communication systems installed and operable.

The EOF was found to be adequately equipped with supplies and

equipment to perform its intended function. The team did note,

however, that although an emergency planning zone map (10-mile EPZ)

was installed, a 50-mile ingestion pathway map was not available in

the EOF command center to assist in the assessment of offsite

radiological conditions.

Based on the abe n findings, the following item is identified

as a significant appraisal finding:

Install an ingestion pathway map to assist in monitoring the

'

efforts of offsite authorities responsible for defining the

extent of long term, offsite radiological conditions.

(445/8943-09; 446/8943-09)

4.1.1.5

Offsite Laboratory Facilities

The appraisal team reviewed offsite laboratories with respect to the

requirements in 10 CFR 50.47(b)(8); 10 CFR 50, Appendix E,

paragraph IV.E; and criteria in NUREG-0654, Sections II.H and I.

In

addition, the appraisal team reviewed Sections 6.7 and 6.8 of the EP;

toured the applicant's laboratory located in the nuclear operations

support facility (NOSF); and interviewed several staff chemists. The

appraisal team noted that the applicant had not completed the setup

of the multichannel analyzer and the sodium iodide (NaI) detector

that would be used for spectral analysis of environmental samples.

No considerations had been given to detector-source geometries when

counting soil, vegetation, and water samples.

Based on the above findings, the following matter is identified as a

significant appraisal finding:

Complete the setup of the multichannel analyzer and'NaI detector

for counting environmerital samples.

(445/8943-10; 446/8943-10)

,

-_-

_-

. _ - _

___ --

__

_ _ - - _ _

_ _ _

-__

- - _ _ - _ - - _ _ _ _ _

v ..

9-

,-

2:

.

4

~.

.

'

-10-

.

.

..

l

4.1.2 :

Protective Facilities

'

4.1.2.1

Assembly / Reassembly Areas

The appraisaliteam reviewed assembly / reassembly areas with respect to

.the requirements of 10 CFR 50.47(b)(0), 10 CFR 50, Appendix E,-

paragraph IV.E; and the criteria in NUREG-0654,Section II.J.

In

addition, the appraisal team reviewed the applicant's EP,

Section.8.0, Implementing Procedure EPP-314, and held-discussicrs

with members of the applicant's security management staff.

Tne appraisal team noted that the applicant had identified adequate

assembly areas inside~and outside of the pas, and these areas were

clearly marked and boundaries delineated.

In addition, the appraisal

team noted that site personnel had received training on evacuation

routes.and assembly areas. Evacuation' routes were' clearly marked.

The appraisal team noted that designated assembly areas outside the

PA were large and appeared to have the capability to hold all

evacuated personnel.

Bashdontheabovefindings,thisportionoftheapplicant'sprogram

appears to be adequate.

4.1:.2.2

Medical Treatment Facilities

The appraisal teta reviewed medical treatment facilities with respect

to.the requirements of 10 CFR 50.47(b)(12); 10 CFR 50, Appendix E,

paragraph IV.E; and criteria in NUREG-0654,Section II.L.

In

addition, the appraisal team reviewed Sections 10.2 and 10.3 of.the

EP and Procedure EPP-313 entitled, " Medical Re:ponse." The appraisal

team toured the first-aid facilities and conducted interviews with

representatives of the applicant's radiation protection, fire and

-

medical, and industrial safety staffs.

The appraisal team noted that medical kits were not fully assembled.

First-aid supplies were found in the Electrical and Control Building

instead of in the Turbine Building as described in the EP.

In

addition, the appraisal team noted that supplies were not stored in

an orderly fashion.

The appraisal team noted that Section 10.3 of the EP stated that an

ambulance was available ensite for transporting injured personnel to

the appropriate medical facility. However, this ambulance was found

to be under the control of the construction contractor who has plans

to turn over the ambulance to the applicant before plant licensed

'operatiens commence. The appraisal team noted that Hood General

Hospital Ambulance Services was the primary ambulance service until

the onsite ambulance is available.

.

. _ _ -

__

_

_ _ . .. .

_

_

_ _ - _ _ __ __ -

..,;

.

' t'

,

.

33

^

,

.

Based on the above findings, the following item is identified as

a significant appraisal finding:

  • -

Assemble medical kits containing key medical supplies for

emergency response personnel who would respond as part of the

first-aid team.

(445/8943-11; 446/8943-11)

In addition to the above finding, the following matters are

considered improvement items:

Maintain first-aid supplies in an orderly fashion.

(445/8943-12; 446/8943-12)

f

Review and revise Section 10.2 of the EP to reflect the correct

location of the onsite first-aid supply area and that Hood

General Hospital Ambulance Service is the interim ambulance

service and complete the turnover of the ambulance service.

(445/8943-13; 446/8943-13)

4.1.2.3

Decontamination Facilities

The appraisal team reviewed decontamination facilities with respect

^

to the requirements of 10 CFR 50.47 (b)(8); 10 CFR 50, Appendix E,

paragraph IV.E; and criteria in NUREG-0654, Sections II.J and K.

In

addition, the appraisal team reviewed Sections 6.9 and 9.3 of the

applicant's EP and examined the decontamination facilities located in

the Electrical and Control Building and the NOSF, and held

discussions with radiation protection personnel cognizant of the

decontamination' facility.

The appraisal team noted that the decontamination facility was

located in the Electrical and Control Building and not in the Turbine

Building as stated in the EP.

In addition, the appraisal team found

that' decontamination supplies were not in place, and that the

applicant had no requirements for performing an inventory of

decontamination supplies.

Based on the above findings, the following item is identified as

a significant appraisal finding:

Provide decontamination supplies in decontamination facilities.

(445/8943-14; 446/8943-14)

In addition to the above findings, this portion of the applicant's

program appears to be adequate, but the following matter is

considered an improvement item:

Review and revise Sem: tion 6.9 of the EP to list the _ electrical

and control building as the location of the decontamination

facility in the plant rather than the turbine building.

(445/8943-15; 446/8943-15)

1

l

_ - - - - . - _ . _ _ _ - _ . _ _ . _ _ - _ _ . _ _ _ - _ - _ . - _ _ . _ _

_ _ _

c-

-

.

.

.

.

-12-

-

-

..

.

4.1.3.

Expanded Support Facilities

The appraisal team reviewed expanded support facilities pursuant to

the requirements of 10 CFR 50.47(b)(8); 10 CFR 50, Appendix E,

paragraph IV.E; and criteria in NUREG-0654,Section II.H.

The appraisal team noted that the applicant's expanded support

facilities consisted of the NOSF and the logistical support center.

These facilities normally performed functions that would be

expected to be performed in the event of an emergency. Corporate,

,

contractor, and other personnel would be adequately supported with

communications and evaluation equipment, such as computers and

reference materials.

The NOSF housed a complete document library

just outside the EOF command center.

Based on the above findings, this portion of the applicant's program

appears to be adequate.

4.1.4.

News Center, Public Information, and News Media

The appraisal team reviewed the applicant's News Center and the

programs to disseminate information to the news media and to the

public against the requirements of 10 CFR 50.47(b)(7), Appendix E,

paragraph IV.E; and criteria in NUREG-0054,Section II.G.

The appraisal team reviewed Section 6.4 of the EP; reviewed

Procedures EPP-207, " Actuation of the News Center and Personal

Duties," and CEPP-108, " Release of Emergency Related Information;"

interviewed the information coordinator; and inspected the News

Center.

The appraisal team noted that Procedure EPP-207 did not establish the

principal points of contact for the local news media and the offsite

support agencies for the initial dissemination of information to the

public. The applicant stated that the procedure in question was to

be re-written, based on the recommendations of an INPO audit, and the

revised procedure would include specific instructions as to the

agencies and media groups to be contacted.

At the time of the appraisal, a news media seminar had not been

conducted.

The applicant stated that a seminar would be conducted on

July 13, 1989, with invitations extended to the local media and the

major news services. At this meeting, the applicant would establish

the utility points of contact and the physical location where the

media can obtain information during an emergency.

The appraisal team

also noted that media training for the CPSES staff was about

20 percent complete at the time of the appraisal.

~

Based on the above findings, the following items are identified as

significant appraisal findings:

. _ - _ _ _ - _ _ - _ _ _ -

-

-_

,.

.

i

.

.

~

-13-

.

.

Revise Procedure EPP-207 to provide specific instructions as to

the news media and offsite agencies to be contacted initially

for the dissemination of information to the public.

(445/8943-16; 446/8943-16)

Complete the news media seminar providing the news media with

the utility points of contact and locations where accident

information can be obtained.

(445/8943-17; 446/8943-17)

Complete the training of the CPSES staff on their duties in the

News Center and dissemination of information to the public.

(445/8943-18; 446/8943-18)

4.2 Emergency Equipment

4.2.1

Assessment Eouipment

4.2.1.1

Emergency Kits and Emergency Survey Instruments

The appraisal team reviewed emergency survey kits pursuant to the

requirements of 10 CFR 50.47(b)(9); 10 CFR 50, Appendix E,

paragraph IV.C; and the criteria of NUREG-0654, Sections II.H and I.

The appraisal team examined equipment and supplies designated for use

during facility emergencies.

Emergency equipment was found stored in

labeled lockers, cabinets, or foot lockers located in or adjacent to

the associated ERF. The storage facilities were found as specified

in the EP except that Procedure EPP-901, " Maintenance and Inventory

of Emergency Equipment and Supplies," Attachment 1 (Mo.ithly Inventory

Summary), reflected locations of supplies that were no longer

applicable or correctly listed as to location.

Specifically,

Attachment 1 listed an OSC cabinet on the 825-foot 6-inch level which

was no longer used and the EOF kit was listed as a cabinet which has

been deleted.

EOF supplies were properly stored in the EOF emergency

storage room.

The appraisal team performed inventories of the emergency kits, and

noted that the CR kit lacked one flashlight.

Spare batteries in all

kits were not uniformly marked as to " shelf life," and others had no

marking. The battery powered, self-reading pocket dosimeter charger

located in the CR kit did not reflect a date for installation of the

battery.

The appraisal team noted that emergency kits contained ample supplies

of potassium iodide (KI) for emergency workers, and manufacturer's

instructions were available regarding cosage and cautions associated

with usage. The appraisal team determined by interviews with

emergency workers that no iodide tolerance testing had be.en performed

for site personnel.

__ - _ _ - __ - __

-

_ __

_

,

. . .

.

,

-

-

i

-14-

Based on the above findings, the following matters are considered

i

'

improvement items:

Include the correct storage locations of emergency kits in

procedures.

(445/8943-19; 446/8943-19)

Mark spare batteries with shelf life expiration dates to permit

persons performing inventories to readily determine if supplies

are adequate. (445/8943-20; 446/8943-20)

Provide KI tolerance testing for emergency responders.

(445/8943-21; 446/8943-21)

4.2.1.2

Emergency Monitoring Systems

The appraisal team reviewed the emergency monitoring systems pursuant

to the requirements of 10 CFR 50.47(b)(9); 10 CFR 50, Appendir. E,

paragraph IV.E; and criteria in NUREG-0654,Section II.H.

The appraisal team noted that the DRMS was installed but undergoing

repair and testing. Specifically, 16 of 96 channels directly related

to emergency response were in various stages of completion. The

planned completion date for turnover of a fully tested, operational

system was August 1989. All preventive maintenance requirements have

been identified and procedures prepared. Not all calibrations had

been completed at the time of the appraisal.

The appraisal team confirmed that the displays for the DRMS panels

for the various instrument channels had physical units, but the local

panel instrument racks did not include physical units on the

instrument channels (e.g., panel CPX-ECPRCV-10. "N Vent Stack PIG").

In event of failure of the DRMS display, operators would have to

obtain local it;strument channel readings, therefore, physical units

should be readily apparent on the instrument display.

Based on the above findings, the following item is identified as

a significant appraisal finding:

Complete the installation, testing, and turnover of the DRMS

system, and confirm that instrument maintenance and calibration

checks are performed in accordance with applicable requirements.

(445/8943-22; 446/8943-22)

In addition to the above findings, the following matter is

considered an improvement item:

Assure that proper physical units are available at local

instrument channel racks for ARM and PRM read-outs.

~

(445/8943-23; 446/8943-23)

_

_ _ _ _

___ _

7-

_

.

V

.

.

li

'D

'

l

N'

.

<

-15-

,

..

.

'

'4.2.1.3

Non-Radiation' Monitors

=The apprairal team reviewed the non-radiation process monitors

intended to measure vital parameters of a non-radiological nature

'(e.g., plant pressures, temperatures, flows,. seismic events, etc.)

which would be relied upon for accident detection, classification,

assessment, and mitigation; pursuant to the requirements of

10 CFR 50.47(b)(9); 10 CFR 50, Appendix E, paragraph IV.E; and the

criteria' in NUREG-0654,Section II.H.

The appraisal team noted that installation of all non-radiation

monitors was complete, but operational testing of the seismic

monitoring system had not been complete.

~ Based'on the above. findings, the following item is identified as

a significant appraisal finding:

Complete the installation, testing, and turnover of

non-radiation process monitoring systems.

Initiate appropriate

preventive maintenance checks on the systems and conduct

appropriate training on operation, analysis, and distribution of

data obtained from the system.

(445/8943-24;~446/8943-24)

4.2.1.4

Meteorological Instrumentation.

The appraisal team reviewed meteorological instrumentation pursuant

to 10 CFR 50.47(b)(9);'10 CFR 50, Appendix E, paragraph IV.B;

Regulatory Guides 1.23, 1.97, and 1.101; and the criteria in

NUREG-0737. 'In addition, the appraisal team reviewed Section 6.13.5-

of the applicant's EP and Procedure STA-714, " Meteorological

Moritoring Program," and held discussions with the applicant's

representative responsible for the meteorological system.

The appraisal team noted that the primary meteorological tower was

destroyed in a recent storm and was scheduled to be operational in

late July 1989. The new tower is to be constructed in the same

location as the old tower.

Based on the above findings, the following item is identified as

a significant appraisal finding:

Complete the construction and installation of the primary

meteorological-tower and related equipment.

(445/8943-25;

446/8943-25)

<-

4.2.2

protective Equipment

-

4.2.2.1

Respiratory Protection

,

The appraisal team reviewed respiratory protection equipment pursuant

to the requirements of 10 CFR 50.47(b)(11); 10 CFR 50, Appendix E,

_ _ _ _ _ _ _ _ -

_ _ _ - _ _ _ _ _ _ _ _ _

4

4

,

,

.,

.

'

'

-16-

paragraph IV.E; and criteria in NUREG-0654,Section II.H.

The

appraisal team inspected the SCBAs available in the CR, TSC, and EOF

and noteo' that SCBAs were not available in the OSC, but were located

in the adjacent corridor leading to the radiologically controlled

areas.

Each facility was provided with a large number of full-face

respirators with particulate and iodine cartridges. The applicant

had a large number of spare SCBA bottles, and had multiple

capabilities for filling SCBA bottles. The appraisal team examined a

spare bottle at a storage location on the open turbine deck and noted

that no dust cap / thread protector devices were installed. Without

protection, the threads could be damaged, and residue could collect

in the air nozzles.

Based on the above findings, the following matter is considered

an improvement item:

Install protective dust caps / thread protectors on spare SCBA

bottles.

(445/8943-26; 446/8943-26)

4.2.2.2

Protective Clothing

The appraisal team reviewed protective clothing supplies pursuant to

the requirements of 10 CFR 50.47(b)(8); 10 CFR 50, Appendix E,

paragraph IV.E; and criteria in NUREG-0654,Section II.H and J.

The appraisal team observed the stores of protective clothing and

determined that the protective clothing would be accessible, under

,

emergency conditions, to persons assigned to the facilities, and that

'

protective clothing supplies were adequate and ready for use.

Based on the above findings, this portion of the applicant's program

appears to be adequate.

4.2.3

Communications

The 6ppraisal team reviewed the emergency communication systems

pursuant to the requirements of 10 CFR 50.47(b)(6); 10 CFR 50,

Appendix E, paragraph IV.E; and criteria given in NUREG-0654,

Section II.H and J.

The appraisal team reviewed the applicant's communication systems and

the instructions for use as. described in Procedure EPP-202,

" Emergency Communications." All communication systems were in place

and operable.

Monthly communication tests'specified by

Procedure EPP-901, " Maintenance and Inventory of Emergency Equipment

and Supplies," had not been initiated.

Paragraph 2.0 of the

procedure stated that the procedure would not be implemented until

1

90 days before receipt of an operating license.

The applicant

j

completed a check during the period of the appraisal. No problems

j

were identified.

!

!

l

l

-

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ____

m 1.:

g

..

4

.

.

-17-

+

..

- r

~The appraisal team noted that paragraph 4.3.5 of Procedure EPP-901,

"Special Telephone Circuits," did not include the Point-to-Point

telephones located. in .the CR, TSC, OSC, Alternate OSC, EOF, and OSC;

therefore, these. circuits would not be scheduled for testing. The

Point-to-Point telephones were listed as emergency telephones in

>

EPP-202, " Emergency Communications."

'

The appraisal team noted that the applicant's Gaitronics system used

for plant announcing, paging, and alarms was installed and operable

-except for the Unit 2 Gaitronics. The appraisal team determined that

no periodic testing of the plant alarms was being conducted. The

applicant stated that preventive maintenance had been established for

the system, but testing had not been performed.

The appraisal team noted that the applicant had increased the number

of.available channels on FM portable radios to a number that

permitted.first-aid, operations, and offsite survey teams to operate

on independent channels. However, the addition of channele was

accompanied by the disadvantage that the TSC, responsible 'or dose

assessment until relieved by EOF, was unable to monitor the results

of field surveys by off-site monito:ing teams.

Results had to be

passed through the OSC 'since only the OSC and the EOF have the proper

frequency for' communicating with offsite teams.

Based on the above findings, the following matter is considered

an improvement item:

"-

Initiate periodic testirg as appropriate for all emergency

communication systems; review and revise procedures to rere se

periodic' testing of all emergency communication' systems; or.

increase the FM radio capability at the TSC to permit monitoring

of emergency channels.

(445/8943-27; 446/8943-27)'

4.2.4

Damage Control / Corrective Action

The~ appraisal team reviewed procedures, maintenance equipment, and

supplies pursuant to the requirements of 10 CFR 50.47(b)(8);

20 CFR 50, Appendix E, paragraph IV.E; and criteria in NUREG-0654,

Section II.H.

The appraisal team determined that Procedure EPP-116, " Emergency

Repair and Damage Control," was the governing procedure for

initiating and implementing emergency repair functions.

Issues such

as team composition, planning, equipping, routing, and authorization

,,

were adequately covered by the procedure.

Identification of special

equipment was addressed in the planning phase, with ready

availability of tools in the tool crib of the Maintenance Building.

Based on the above findings, this portion of the applican't's program

appears to be adequate.

1.

,

i

C

_ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _

__

_

_ _ _ _

.

j.

, ,. ;

,

-18 '

-

.

..

p

4.2.5

Reserve Emergency Supplies and Equipment

The appraisal team reviewed reserve emergency supplies and equipment

pursuant to the requirements of 10 CFR 50.47(b)(B); 10 CFR 50,

Appendix E, paragraph IV.E; and criteria in SUREG-0654,Section II.H.

~The appraisal team interviewed site personnel and determined that

adequate stocks and supplies of emergency equipment were maintained-

at the warehouse and in-plant locations to support a prolonged

emergency response.

Based on the above findings, this portion of the applicant's program

appears to be adequate.

4.2.6

Transportation

The appraisal team reviewed the transportation equipment available

for emergency response pursuant to the requirements of

10 CFR 50.47(b)(8); 10 CFR 50, Appendix E, paragraph IV.E; and

,

'

criteria in NUREG-0654,Section II.H.

The appraisal team determined that Procedure EPP-10R, " Control of

Designated Emergency Use Vehicles used for Routine Operations," was

the controlling procedure for three designated emergency vehicles.

The. appraisal team exa.nined the .four wheel drive vehicles and their

emergency kits and equipment, including two-way transceivers, and

concluded that.the vehicles were readily available for their intended

i

use and could readily accomplish their function.

Based on the L ve findings, this portion of the applicant's program

appears to be adequate.

5.0 EMERGENCY IMPLEMENTING PROCEDURES

5.1 General Content and Format

The appraisal team reviewed the general content and format of EPPs

pursuant to the requirements of 10 CFR 50.47(b)(5) and (6); 10 CFR 50,

Appendix E, paragraph IV.D; and criteria in NUREG-0654,Section II.E

F.

H, and J.

The appraisal team noted that all EPPs conformed to a standard format that

-specified purpose, applicability, definitions, references, procedural

steps, and attachments anci checklists.

The appraisal team identified the following discrepancies in the

procedures:

a.

Procedure EPP-112. " Duties of CR Personnel During Emergen'cies,"

paragraph 4.2.2, " Shift Technical Advisnr," assigned the STA

secondary duties of performing dose assessment calculations. This

o

e

1

+

.:

,

.

1

.

-19-

l

-

..

assignment of the'STA to dose calculations was not consistent with

the guidance of NUREG-0737, Appendix C.

An alternate staff member

should be trained to perform dose assessment' functions to permit the

STA uninterrupted ability to monitor plant critical safety functions,

evaluate and analyze plant transient response, and perform accident

mitigation and other matters related to operational safety.

(See

Section 2 of this report.)

b.

Procedure EPP-204, " Activation and Operation of the Technical Support

Center (TSC)," addressed the subject of core damage assessment with a

note that required laboratory analysis of plant vent iodine and

particulate samples to be reported to the CR within I hour of.

sampling, and post-accident sampling system (PASS) results to be

completed within 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> of the time the decision was made to obtain

the sample. The appraisal team determined that it was appropriate to

establish goals for_ performing analysis. However, writing the

procedure in a fashion that requited an activity to be performed that

may be impossible to achieve was not deemed appropriate.

!

Procedure EPP-206, " Activation and Operation of the Emergency Operations

Facility (EOF)," contained the following discrepancies:

a.

Action statements for the emergency staff, related to relocating the

EOF, were either inaccurate or incomplete.

For example, Table 4.3.6

directed the offsite radiological assessment coordinator to repor

to

the TSC onsite radiological assessment coordinator (ONRAC) to assist

with dose assessment responsibilities. DJe to limited TSC physical

size and probable radiological conditions, it was noted as highly

unlikely that any additional persons could be transported to or

accommodated in the TSC under accident conditions that required

relocation of the EOF.

b.

The apprai. cal team noted that after the activation of EOF, the

radiological assessment manager (RAM) and the EOF manager (EOFM) will

perform dose assessment and decisionmaking pertaining to PARS

in accordance with the guidance of NUREG-0737, Supplement 1, Table 1.

However, in the event the EOF became uninhabitable, the EOFM would go

to tha alternate EOF and the RAM to the TSC. This is contrary to the

guidanceofNUREG-0737,jupplement1.

In addition, the applicant did not provide instructions for

performing the functions of the EOFM and the RAM while they are in

transit from the EOF to the alternate EOF and to the TSC.

c.

Some persons were not directed to report to any location upon

relocation of the EOF, e.g., the EOF communications coordinator

(Table 4.3.13).

Procedure EPP-901, " Maintenance and Inventory of Emergency Eqtiipment and

Supplies," included Attachment 2, " Verification of Operability of

L

l

L

t

--

_

__ -

--

- _ _ _

._

._

. .;

,y

..

L s_

-

4

+

-

.go.

Designated Emergency Equipment." This attachment was intended as an

equipment guide list; however, the equipment was not specified.

Several informal. documents were used to implement required functions in

i

the 'cC,.such as a communications workbook, operational instructions for

the "-

radio, and an engineering workbook contained appendices and tables

cont O 'ng capacities, curves, and other plant information. The color

coded EAL classification flow charts in the ERFs were not annotated as to

title, revision, or source, The above examples were uncontrolled

documents that could contain erroneous information. The appraisal team

determined;that' operational instructions should be included in_the

applicable procedures and that design information should be verified

correct and then controlled. Job aids, such as EAL classification

schemes, snould be marked with the latest revision /date and compared to

centro 11ed document inventory lists before use.

The plant specific emergency operating procedures (EOPs) were contained in

binders entitled " Emergency Response Guidelines," which were noted to be

the title of generic vendor guidelines from which the plant specific E0Ps

were. derived. The. binders should use correct titles to be readily

identifiable.

Based on the above findings, the following items are identified as

significant appraisal findings:

Complete the review and revision of the EAL/ Emergency Classification

procedure.

(445/8943-28; 446/8943-28)

Revise procedures to assign a staff member other than the STA to

perform dose assessment functions until the CR is relieved of the

function by the TSC. (445/8943-29; 446/8943-29) (See also

G5/8943-02; 446/8943-02.)

In addition to the above findings, the following matter is considered

an improvement item:

Review and revise emergency procedures to correct errors and

discrepancies. (445/8943-30; 446/8943-30)

.

5.2 Emergency, Alarm, and Abnormal Condition Procedures

The appraisal team reviewed the alarm response procedures (ALPS), the

abnormal condition procedures (ABNs), and the emergency response

guidelines pursuant to the requirements of 30 CFR 50.47(6) and (8);

10 CFR 50, Appendix E, paragraph IV.E; and the criteria in NUREG-0654,

.

_

LSection II.H.

The appraisal team noted that the ALPS did not refer to the EP,or EP

. procedures.

-

_ _ _ _ _ _ _ _ _ _ _

_ _ _ . __ _--_ -

- _ _

_ ____ _ _ _ _ -

i

'

.,

..

.

.

'

.,

.

-21-

-

..

Some of the ABNs that would be entered in response to conditions requiring

activation of the EP, had no specific reference to the EP or an EP

procedure. The ABNs reviewed were:

1.

ABN-103A, "High Reactor Coolant Activity"

2.

ABN-803A, " Response to a Fire in the Control Room or Cable Spreading

Room"

3.

ABN-804A, " Response to Fire in the Safeguards Building"

4.

ABN-805A, " Response to Fire in the Auxiliary Building or the Fuel

Building"

5.

ABN-806A, " Response to Fire in the Electrical and Control Building"

6.

ABN-807A, " Response to Fire in the Containment Building"

7.

ABN-808A, " Response to Fire in the Service Water Intake Structure"

8.

ABN-809A, " Response to Fire in the Turbine Building"

~ Based on the above findings, the following matters are considered

improvement items:

Review the ALPS and include appropriate references to

Procedure EPP-201.

(445/8943-31; 446/8943-31)

Correct inconsistencies in referencing the EP in abnormal condition

procedures.

(445/8943-32; 446/8943-32)

5.3 Implementing Instructions

The appraisal team reviewed implementing instructions pursuant to the

requirements of 10 CFR 50.47(b)(5) and (6); 10 CFR 50, Appendix E,

paragraph IV.D; and criteria in NUREG-0654, Sections II.E, F, H, and J.

The appraisal team reviewed implementing instructions to determine if they

adequately implemented the provisions of the EP; provided the EC with an

adequate scope of authority and non-delegable responsibilities; provided

EALs based on observable information with-required response actions; and

directed the implementation of specific procedures required for effective

overall emergency response.

The appraisal team reviewed the applicant's procedure for formulating and

providing PARS with respect to the guidance of IE Information Notice 83-28

and NUREG-0654.

Procedure EPP-304 was reviewed for content, format, and

the method for formulating and communicating PARS during sever.e accidents.

. _ - _ _ _ _ _ _ _ _ _ - _ _ _ - - _ - _ _

--

__- -

,-

.

.

s

,

~22-

The appraisai team noted that Procedure EPP-304 did not incorporate the

guidance provided in IE Information Notice 83-28 because the procedure

failed to provide adequate instructions for developing PARS based on

operational assessment of plant conditions, that is, PARS based on the

precursors of a release, such as reactor core and reactor building

containment conditions. All PARS which were developed using EPP-304,

except baseline PARS, were based primarily on dose assessments, either

,

actual or projected.

Further, Procedure EPP-304 did not include a

decisionmaking flow chart to facilitate decisionmaking similar to that

shown in IE Information Notice 83-28.

The appraisal team al:c noted that Procedure EPP-304 included unnecessary

considerations for developing and communicating PARS that could result in

unnecessary delays.

Information used by offsite agencies to implement

corrective actions such as weather conditions, population distributions,

special facilities like nursing homes, hospital, prison, and offsite

evacuation routes were included in the applicant's process for

recommending protective actions.

In addition, the appraisal team noted that Procedure EPP-304 required that

decisionmakers review PARS with the Texas Department of Health before

recommending PARS to local officials, which further compromises the

applicant's ability to recommend protective actions within 15 minutes.

Based on the above findings, the following item is identified as

a significant appraisal finding:

Revise Procedure EPP-304 to add guidance for developing offsite

PARS based on operational assessment of plant conditions.

Incorporate, in Procedure EPP-304, a decisionmaking aid such as the

" logic tree" shown in IE Information Notice 83-28, Figure 1, " Flow

Chart for General Emergency Offsite Protective Decisions." Delete,

from Procedure EPP-304, those considerations (such as weather,

special fac ties, and population distributions) that are not

germane to etrectively developing and recommending a protective

action.

Revise Procedure EPP-304 to eliminate the need to discuss

PARS with the state or counties until after the PARS are made to

offsite agencies.

(445/8943-33; 446/8943-33)

5.4 Implementing Precedures

5,4.1

Notifications

The appraisal team reviewed notification procedures with respect to

the requirements of 10 CFR 50.47(b)(5); 10 CFR 50, Appendix E,

paragraph IV.D; and NUREG-0654, Sections II.E and F.

The appraisal team reviewed Procedures EPP-202, " Emergency

Communications," and EPP-203, " Notifications," for adequate

implementation of EP requirements; correlation of notification

.

_ _ _ _ . _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ . _ _

_ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_ _ _ _ _ _ _ _ . _

_.

.

._

_

. _ _

_ _ _ _ _

_

__

_-

__

__ _ _ _

m w .'

.

.

,

i

1 .

-23-

requirements with EALs; adequacy of instructions regarding message

content and equipment use; for provisions for required phone numbers;

and reference to an authentication scheme for initial notifications

to offsite authorities.

Based on the above review, this portion of the applicant's program

appears to be adequate.

5.4.2

Assessment Actions

5.4.2.1

Dose Assessment

The appraisal team reviewed dose assessment procedures against the

requirements in 10 CFR 50.47(b)(9); 10 CFR 50, Appendix E,

paragraph IV.B; NUREG-0654,Section II.I; and Supplement I to

NUREG-0737.

The appraisal team reviewed Section 7.0 of the applicant's EP;

Procedures EPP-206, " Activation and Operation of the EOF," EPP-300,

" Manual Calculation of Offsite Dose Rates," EPP-303, " Micro-Computer

Based Emergency Dose Assessment," and EPP-304, " Protective Action

Guides;" and the documentation of the applicant's dose assessment

system.

In addition, the appraisal team conducted interviews with

key personnel who would have dose assessment responsibility during an

emergency.

The appraisal team noted that the applicant's dose assessment model

used a straight-line Gaussian atmospheric dispersion model which will

not account for' wind shifts nor calculate cumulative doses at

downwind locations. Current state-of-the-art dose assessment models

in the nuclear industry have segmented plume atmospheric dispersion-

models which account for wind shifts and provide the basis for

calculating cumulative doses and doses resulting from ground

deposition.

The appraisal team noted that an audit performed by the applicant

'

revealed that the normalized dispersion parameters (Xu/Q) used in

EDAM were not documented.

The appraisal team noted that the vendor

provided revised Xu/Q to the applicant, but that these values still

need to be formally documented and included in dose assessment

Procedures EPP-300 and EPP-303.

The radiation protection coordinator and the offsite radiological

assessment coordinator have a responsibility to calculate population

dose as defiried in Procedure EPP-206.

Interviews with emergency

response personnel, who would fill these positions in an emergency,

showed that personnel were not cognizant of the methodology to

calculate population doses.

,

The appraisal team noted that Procedure EPP-206 references

.

Procedure RPI-304, "Populatien Dose Assessment," which is no longer

i

_ - _ . _ _ - _ _ _ _ _ _ _ . _ _ _ _ _

.'

'

.

, ..

,

'

-24-

an active procedure for calculating population dose. Since the

applicant no longer has the capability te calculate population dose

and there is no requirement for performing population dose early in

an accident, the applicant should consider deleting this function

from Procedure EPP-206.

The appreisal team compared the units on the DRMS with those that

would be inputted to the EDAM computer program, and noted that the

containment high range area monitor (CTE-116) read in counts per

minute on the RM-11 while EDAM required the input in mR/h. Moreover,

the containment high range area Monitor-Train B was listed as CTW-117

on the RM-11 and CTE-117 in Procedures EPP-300 and EPP-303.

Based on the above findings, the following matters are considered

improvement items:

Enhance the emergency dose assessment program with a segmented

plume atmospheric dispersion model that will take wind shifts

into account.

(445/8943-34; 446/8943-34)

Complete the documentation of the Xu/Q values using the dose

assessment model and document these values into procedures.

(445/8943-35; 446/8943-35)

Delete the reference to the calculation of total population dose

from Procedure EPP-206.

(445/8943-36; 446/8943-36)

Ensure that units on the DRMS monitors used for dose assessment

calculations are consistent with those in the RM-11 system, and

the dose assessment model.

(445/8943-37; 446/8943-37)

5.4.2.2

Offsite Radiological Surveys

The appraisal team reviewed offsite radiological survey procedures

pursuant to the requirements of 10 CFR 50.47(b)(8) and (9);

10 CFR 50, Appendix E, paragraphs IV.B and E; and criteria in

NUREG-0654, Sections II.H, I, and K.

In addition, the appraisal team

reviewed Sections 6.13.11, 7.3.2, and Appendix J and H of the EP and

EPP-309, "Offsite Radiological Monitoring." Discussions were also

held with applicant's emergency planning staff cognizant of offsite

radiological monitoring.

The appraisal team noted several areas where pian and procedural

improve.nents could be made. Section 7.3.2 of the EP incorrectly

states that the TSC is in communications with the offsite monitoring

teams. Procedure EPP-309, Section 4.4.7.1 states that samples

returned to the NOSF from the field shall be logged in by the offsite

monitoring personnel on Form EPP-109-1. A review of Form EPP-109-1

showed it to be an emergency organization activities log ' sheet which

-

does not appear to be adequate for logging in ramples from the field.

i

- - _ _ _ _

_ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

-

-_

_--

'

3

. . -

-

. _ .

.

- .=

.

'

-25-

LThe. appraisal teat

nducted a walk-through with an offsite monitoring

' team (see Section ..z.6) and noted that samples collected in.the

field would sometimes be transported back to the NOSF via a runner;

hwever, nowhere in Procedure EPP-309 was there any discussion of the

ese'of a runner.

The . laboratory in the NOSF has the capability of performing more

detailed' analyses of environmental samples brought back from the

field using.the Na1 detector counting system (see Section 4.1.1.5).

No procedures exist for routine maintenance and operability checks on.

this system.

In addition, there are no procedures for use of the

system during an emergency which would include information such as

handling, preparation, and counting of the samples, recording of

sample results, and disposition of samples when sampling is complete.

Based on the above findings, the following matters are considered

improvement items:

Rev'se Section 7.3.2 of the EP to indicate the actual

communication link between emergency facilities and the offsite

monitoring teams.

(445/8943-38; 446/8943-38)

Develop a procedure for the routine maintenance and operability

check on the NaI detector system, and describe counting

procedures for environmental samples and the activ * ton of the

countingLlaboratory. (445/8943-39: 446/8943-39)

o.4.2.3

Onsite Out-of-plant Radiological Surveys

The. appraisal team reviewed onsite (out-of-plant) survey procedures

pursuant to the requirements of 10 CFR 50.07(b)(8) and (11);

10 CFR 50, Appendix E, paragraph IV.E; and :riteria fr, NUREG-0654,

'Section II.K.

In addition, the appraisal team revi ved Sections 7.3,

7.3.1, and 8.3 of the EP; Procedure EPP-310, 'O.m te and In-Plant.

Radiological Surveys;" and Procedure EPP-316, " Emergency Repair and

Damage Control." Interviews were held with cognizant members of the

radiation protection staff.

Based on the above review, this portion of the applicant's program

appears to be adequate.

5.4.2.4

In-Plant Radiological Surveys

The appraisal team reviewed in plant survey procedures pursuant to

.the requirements of 10 CFR 50.47(b)(8) and (11); 10 CFR 50,

Appendix E, paragraph IV.E; and criteria in NUREG-0654,Section II.K.

In addition.-the appraisal team reviewed Sections 7.3, 7.3.1, and 8.3

of the EP; Procedures EPP-310, "Onsite and In-Plant Radiological

,

Surveys," and EPP-316, " Emergency Repair and Damage Control," and

.

,

.

_ _ . _ . _ _ _ _ - _ . _ _ _ _ _ _ _

______._______

_ _ _ _ _ .

_ _ _ _ _ _ -

l-

-

,

,

f

.

.,

,

-

-26-

-

..

interviewed radiation protection technicians and radiation protection

supervisors having emergency response duties.

Based on the above review, this portion of the applicant's program

appears to be adequate.

5.4.2.5

Radiological and Environmental Monitorinq_ Program

The appraisal team reviewed the environmental monitoring program

pursuant to the requirements of 10 CFR 50.47(b)(8), (9), and (11);

10 CFR 50, Appendix E, paragraphs IV.B and E; and criteria in

NOREG-0654, Sections II.H, I, and K.

In addition, the appraisal team

reviewed Sections 6.13.11, 7.3.2, and Appendix J and H of the EP and

Procedure EPP-309, "Offsite Radiological Monitoring," and held

discussions with the emergency planning staff cognizant of off:.ite

radiological monitoring.

The appraisal team noted that the map in Attachment I to

Procedure EPP-309, showing the locations of environmental TLDs, was

.

not legible, and additional training of radiation protection

technicians may be necessary to assist them in finding TLD locations.

Based on the above findings, the following matter is considered

an improvement item:

Provide legible maps showing environmental TLD locations in

Procedure EPP-309 including specific descriptions on how to

reach these locations.

(445/8943-40; 446/8043-40)

5.4.3

Protective Actions

5.4.3.1

Radiation Protection During an Emergency

The appraisal team reviewed the radiation protection program for

emergencies pursuant to the requirements of 10 CFR 50.47(b)(11);

10 CFR 50, Appendix E, paragraph IV.A; and criteria in NUREG-0654,

Section II.K.

In addition, the appraisal team reviewed Sections 9.0,

9.1, 9.2, and 9.3 of the EP, Procedures EPP-305, " Emergency Exposure

Guidelines and Personnel Dosimetry," and EPP-306, "Use of Thyroid

Blocking Agents," and held interviews with radiation protection

personnel.

The appraisal team noted that Procedure EPP-305 instructed the staff

to issue TLDs in the EOF to document personnel exposure, and gave the

EOF radiation protection coordinator the responsibility to issue TLDs

under specific emergency conditions, rather than the routine issuance

of TLD upon the arrival of each person at the EOF.

.

E _ _ _ _ _ . _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ._

._.

_

_

. - _ _ _.

.'

.'

~

.

,

..

.

-27-

Based on the above findings, the following matter is considered an

improvement item:

Consider issuing dosimetry to personnel as they enter the EOF.

(445/8943-41; 446/8943-41)

5.4.3.2

Evacuation of the Owner-Controlled Area

The appraisal team reviewed the applicant's plans for personnel

evacuation of the OCA pursuant to the requirements of

10 CFR 50.47(b)(10) and criteria contained in NUREG-0654,

Section II.J.

In addition, the NRC team reviewed the EP,

Section 8.0, and Procedure EPP-314.

The appraisal team noted that the applicant had a method to promptly

initiate the evacuation of tne exclusion area upon initiation of an

evacuation order.

The method used staged evacuation in three phases:

building evacuatien within the PA, evacuation of non-essential

personnel to assembly areas located adjacent to the PA access control

points, and evacuation of all non-essential personnel from the OCA.

The applicant designates the OCA as the " exclusion area." The

appraisal team noted that the applicant had not tested its ability to

evacuate the OCA in a timely manner.

The appraisal team noted that Procedure EPP-314, " Evacuatien and

Accountability," provided for a " sweep" of the OCA within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.

However, this procedure did not include the search of approximately

300 buildings in the OCA which are routinely occupied during working

. hours. The appraisal team noted that the method used by the

applicant to conduct the " sweep" of these buildings consisted of

security vehicles driving through the areas with a voice amplifier

announcing a warning to personnel to evacuate.

>

The appraisal team noted that under certain accident scenarios and

due to the prevalent wind direction on the site, a large number of

buildings and personnel in the OCA could be exposed to the

radioactive plume.

Based on the above findings, the following item is idertified as

a significant appraisal finding:

Demonstrate that the evacuation of the OCA, including all

"

buildings, can be accomplished in a thorough and timely manner.

(445/8943-42; 446/8943-42)

5.4.3.3

Personnel Accountability

The appraisal team reviewed personnel accountability capabilities

pursuant to the requirements of 10 CFR 50.47(b)(10) and the criteria

. - _ _ _ - _ _ _ _ _ _ _ - _ _ -

_

_

..'

..

.

-

.

d.

.

-28-

.

.

,.

..

in NUREG-DC54.Section II.J.

In addition, the appraisal team

reviewed Proceouca-EPP-314, inspected access control points,

equipment, and held discussions with security and emergency

L

preparedness personnel.

The appraisal team noted that the applicant had not yet demonstrated

the capability to perform personnel accountability of all personnel

in the PA within 30 minutes.

Based on the above findings, the following 1 tem is identified as a

significant appraisal finding:

,

Demonstrate the capability of performing personnel

accountability of all personnel within the PA within 30 minutes.

(445/8943-43; 446/8943-43)

5.4.3.4

Personnel Monitoring and Decontamination

The appraisal team reviewed the personnel monitoring and

decontamination program pursuant to the requirements of

10 CFR 50.47(b)(11); 10 CFR 50, Appendix E, paragraph IV.A; and the

criteria in NUREG-0654, Sections II.J and K.

In addition, the

appraisal team reviewed Section 8.3 of the applicant's EP;

'

Procedures EPP-313, " Medical Response," RPI-402, " Personnel

.

Decontamination," EPP-307, " Radiological Monitoring of Site

L

Evacuees," and RPI-108, " Skin Contamination Worksheet;" and conducted

interviews with the radiation protection staff responsible for this

program.

Based on the above review, this portion of the applicant's program

appears to be adequate.

5.4.3.5

Onsite First-Aid / Rescue

The appraisal team reviewed onsite the first-aid / rescue program with

respect to the requirements of 10 CFR 50.47(b)(12); 10 CFR 50,

Appendix E, paragraph IV.E; and the criteria in NUREG-0654,

Section II.L. The appraisal team reviewed Section 10.2 and 10.3 of

the EP and Procedures EPP-308, " Transporting Contaminated, Injured

Personnel;" EPP-205, " Activation and Operation of the Operations

Support Center;" and EPP-313, " Medical Response." In addition, the

appraisal team interviewed representatives of the applicant radiation

protection staff, fire and medical staff, and industrial safety

staff.

The appraisal team noted that the applicant was in the process of

replacing first-aid team members with emergency medical

technicians (EMTs). Discussion with applicant's. representatives

revealed that there would be a minimum of five EMTs avairable on any

shift. Procedure EPP-313 did not specify the use of EMTs as

first-aid team members.

.

m

m.

-

._.

_m_

_____._--____-__--______m_--_____---__._.__.____

m-

.___ _

f ., > ;,

'

.

.

,

  • '

-29-

Based on the above findings, the following matter is considered

an improvement item:

Review and revise Procedure EPP-313 to specify the use of EMTs

j

as first-aid team members.

(445/8943-44; 446/8943-44)

5.4.4

Security During Emergencies

The appraisal team reviewed security during emergencies pursuant to

the requirements of 10 CFR 73, Appendix C.

In addition, the

a ,2raisal team reviewed the applicant's security contingency plan

rand procedures, inspected security facilities, and held interviews

with selected members of the security organization.

The appraisers confirmed that there were an adequate number nf

security officers to implement the security contingency plan and to

perform security tasks pertaining to emergency response.

The

appraisers also noted that the security officers were aware of their

responsibilities during emergencies.

Based on the above review, .his portion of the applicant's program

appears to be adequate.

5.4.5

Repair / Corrective Actions

The appraisal team reviewed the repair and corrective actions program

with respect to the requirements of 10 CFR 50.47(b)(13); 10 CFR 50,

Appendix E, paragraph IV.H; ant; the criteria in NUREG-0654,

Section II.K.

In addition, the appraisal team reviewed

Procedure EPP-116, " Emergency Repair and Damage Control," for the

logistics involved in repair operations, the identification of a team

leader, and the presence of instructions to assure adequate

radiological and technical briefings of emergency repair personnel.

Based on the above review, this portion of the applicant's program

appears to be adequate.

5.4.6

Recovery Phase

The appraisal team reviewed recovery phase planning with respect to

the requirements of 10 CFR 50.47(b)(13); 10 CFR 50., Appendix E,

paragraph IV.H; and the criteria in NUREG-0654,Section II.M.

In

addition, the appraisal team reviewed Procedure EPP-121, " Reentry,

Recovery and Closeout," for identification of key positions in the

recovery organization; the d?lineation of organizational authority

for entering the recovery phase; and provisions for evaluating plant

conditions as well as radiological conditions when deciding if the

recovery phase is appropriate.

,

Based on the above reviev, tH s portion of the applicant's program

appears to be adequate.

,

4

m_._

__ _._.__

_

. - _ _ .

l 31 77

7-

~

.

-30-

5.5 Supplementary Procedures

5.5.1

inventory, Operational Checks, and Calib-ation of Emergency Equipment

)

The appraisal team reviewed inventory, operational checks, and

calibration procedures pursuant to the requirements of

,

10 CFR 50.47(b)(8); 10 CFR 50, Appendix E, paragraph IV.E; and the

- criteria.in NUREG-0654,Section II.H.

In addition, the appraisal

team reviewed inventory and maintenance procedures applicable to

emergency equipment.

The appraisal team noted that inventories, calibration, and

performance testing had been adequately performed on a timely basis;

test results had been properly documented; and clear lines of

responsibilities were in place.

Based on the above review, this portion of the applicant's program

appears to be adequate.

5.5.2

. Drills and Exercises

The appraisal tem, reviewed the applicant's drills and exercise

program with respect to the requirements of 10 CFR 50, Appendix E,

paragraph IV.F and the criteria contained in NUREG-0654, Planning

Standard N.

.The' appraisal. team reviewed selected drill and exercise files;

observer and participant comments; the management controls for

assigning responsibility for tracking and correcting findings

identified in the drills and exercises; and the provisions for

conducting communications, medical, radiological monitoring, and

health physics drills.

Based on the above review, this portion of the applicant's program

appears to be adequate.

5.5.3

Review, Revision, and Distribution

The appraisal team reviewed the applicant's methods for performing

~

.the review, revision, and distribution of the EP and EPPs pursuant to

.

the requirements of 10 CFR 50.47(b)(16); 10 CFR 50.54(q) and (t);

10 CFR 50, Appendix E, paragraph IV.G and V; and the criteria in

NUREG-0654,Section II.P.

,

The appraisal team noted that the EPM was responsible for verifying

that all emergency response telephone numbers were correct on a

quarterly basis and revising the emergency response organization

roster as necessary. The team noted that the telephone directory had

the latest date of its review and revision on the cover. " The rate of

change of numbers showed that the document was undergoing revision

approximately monthly. Checks of several telephone numbers verified

that the sampled numbers were correct.

+

'

. _ _ _ _ _ _ _ _

- _ - -

_ - _

-.

!:

. , p ;. .

>

+

.

.

,"

%

1

-31-

-

..

l

In addition, the appraisal team noted that periodic revisions to the

emergency procedures were initiated based upon changes in the

-

program; that program users could readily initiate recommendations

for changes; and controlled documents contained properly revised and

updated procedures.

Based on the above review, this portion of the applicant's program

appears to be adequate.

5.5.4

Audits of Emergency Preparedness

The appraisal team reviewed the applicant's audit program of

emergency preparedness against the requirements of 10 CFR SC.54(q)

and (t) and criteria in NUREG-0654,Section II.P.9.

In addition, the

appraisal team reviewed Revision 2 of Procedures NQA 3.07, " Quality

Assurance Audit Program," and CHP-2.03, " Emergency Preparedness

Program Review," and held discussions with audit program personnel.

The appraisal team nuted that the applicant had conducted two

independent audits of the emergency preparedness program prior to the

appraisal. One of the audits was performed by a contractor and the

other by their corporate quality assurance audit staff. The

appraisal team noted that both audits had been performed within the

last 12 months preceding the appraisal; the audits were

comprehensive; and identified a number- of significant areas that

needed improvement.

In addition, the appraisal team determined that

the applicant had a system in place to follow up on corrective

actions related to each finding identified by the auditors.

Based on the above review, this portion of the applicant's program

appears to be adequate.

6.0 COORDINATION WITH OFFSITE GROUPS

The applicant's contacts and coordination with the offsite support

agencies were reviewed pursuant to the requirements of 10 CFR 50.47(b)(3)

and criteria in NUREG-0654, Sections II.A, B, E, and L.

The appraisal team reviewed Sections 5.0, 5.1, and 5.2 of the applicant's

EP and Procedure TRA-105, " Emergency Preparedness Training." In addition,

the team interviewed the applicant's Public Information Coordinator and

selected representatives of offsite agencies. These contacts verified

that the applicant had contacted the responsible offsite agencies for the

purpose of providing training and conducting drills.

Further, these

contacts indicated that they had copies of the applicant's EP and

procedures, and understood their responsibilities during a CPSES

emergency. The training records reviewed indicated that a significant

amount of training had been conducted in the past 6 months on topics

~

appropriate to the response of each agency. The applicant stated that

original records of training are forwarded to the state of Texas for

their review and determination of adequacy. The appraisal team was unable

to determine which offsite agencies needed to be trained, the subjects to

train on, and the status of completion.

___

_ _ _ _ _ _ _ _ _ _ - _ - _ _ _ _

. --

,,.

-

_

. _ _ _

- - _ _ - _

_ _ -

'

  • .: <

.

l

...e,

L

.

.

-

-32-

.

The appraisal team also reviewed Letters of Agreement with the offsite

support agencies. Although 17 letters were on file, some were not current

and needed to be updated.

The appraisal team noted that a current emergency information brochure had

~

been provided to persons within the 10-mile EPZ and posters to inform

transients were posted-at public and business locations.

Based on the above findings, the following matters are considered

improvement items:

Update the. Letters of Agreement with the offsite support agencies.

(445/6943-45; 446/8943-45)

Prepare a matrix that would indicate what offsite agencies are to be

trained, the subject to be trained on, and the status of completion.

(445/8943-46; 446/8943-46)

7.0 DRILLS, EXERCISES, AND WALK-THROUGHS

7.1 Walk-Throughs Observations

The appraisal team performed walk-throughs to evaluate the performance of

selected teams of the emergency response organization with respect to

recognizing EAL entry conditions (emergency detection), correlating entry

conditions with the appropriate action level (classification), notifying

offsite agencies and emergency responders (notification), and formulating

PARS for consideration by offsite agencies.

The appraisal team conducted walk-throughs based on prepared scenarios of

postulated events. Personnel evaluated were given information such as

plant alarms, reports of hypothetical events, and changes in key

parameters to simulate events. When decisions required information that

would normally be available, the information was provided by the appraisal

team.

The appraisal team designed scenarios for the operating teams in order to

test the ECs ability to respond to " fast breaking" severe accidents

conditions requiring initial classification, escalation, and

recommendation of protective actions. Additionally, scenarios provided

events requiring dose assessment and notification from the CR as well as

the use of E0Ps for event mitigation. Scenarios began with normal

conditions and degraded to accident conditions requiring emergency

classification. The walk-throughs were conducted in the CR and operating

teams were allowed access to procedures and equipaent.

The format used for the walk-throughs was that of a " table-top" discussion

except that procedures, checklists, and notification forms were actually

used.

.

_ - _ - _ _ _ _ _ _ _ _ _ _ . _ _ _ . _ _ _ _ _ - _ - - _ _ . _ _ _ _ . _ _ - - -

[15.~;oc.J' -

]

<

,

m J. '

->

-

a ;'"

.

.

-33-

il

7.1.1

Emergency Detection

p

The. appraisal team communicated degrading plant conditions to the'CR-

operating team by orally identifying alarms and changes in pertinent

parameters; the operators.were expected to then use appropriate

procedures and.to simulate performing required actions.

Based on the above review, this portion of the applicant's program

appears to be-adequate.

7.1. 2 ~

Emergency Classification

l

The appraisai team postulated a fire in the "A" train diesel

generator as the event' requiring shift supervisors (SSs) to activate

the EP. Three of four crews classified the emergency correctly as an

alert; one crew over-classified the event as a site area emergency.

Although all classifications.were made in a timely manner, some minor

problems were observed during use of the " fire" EAL. Uncertainty

existed regarding whether the' diesel fire must meet the notification

of. unusual event criterion by burning for more than 10 minutes before

it could be considered a fire potentially affecting safety systems.

Additionally, one SS failed to discriminate between a fire affecting

a safety system and a fire causing the loss of a safety function.

,

'

The appraisal team noted that all escalations performed by the

CR crew, the TSC group, and the EOF group were correct in accordance

with Procedure EPP-201 and were issued within 15 minutes of receiving

the initiating conditions.

Based on the above findings, the following matter is considered

an improvement item:

. Review the materials for EAL training and revise, as necessary,

!-

to ensure that CR decisionmaking personnel fully understand the

application of the " fire" EAL.

(445/8943-47; 446/8943-47)

7.1. 3 -

Notification

The Lppraisal team expected the SS to assign communicators and

authorize notification messages. The communicators were instructed

-

to simulate required notifications.

In the TSC and EOF, the

procedures, special considerations, and personnel assignments for

notifying offsite agencies were discussed, and the notification forms

were filled out.

.

. \\

Bused on the above review, this portion of the applicant's program

appears to be adequate.

.

4

_--.__-___.A-_-.-___

_ - _ ~ _ . - - _ _ _ _ _ _ . - _ . _ _ _

.

. - -

y

.

.

.

.

c .y

*,

'

s

&

h

-34-

l

'

7.1.4

Dose Calculations

-!

'

'

The appraisal team noted that the STA performed dose calculations

based on data provided by the appraisal. team-in accordance with

Procedure EPP-303, " Micro-Computer Based, Emergency Dose Assessment."

!

L

The appraisal team noted that during scenarios that resulted in a

large source term in containment but no. release, the STAS used

containment design leak rate for. performing dose projections, even

through plant conditions implied an eventual containment failure due

to overpressure.

(See-Section 5.3 of this report, " Implementing

Instructions" and 7.2.11, " Protective Action Decisionmaking.")

The appraisal' team conducted walk-throughs with three computer

operators.(two in the EOF and one in the TSC) who were responsible

for performing the dose calculations during an emergency. Based on

the walk-throughs, the training received acpeared to be adequate in

this area, however, the procedure was found not to include default

release rates.

Based on the above findings, the following matter is considered

an improvement item:

Revise Procedure EPP-303 to include instructions for using a

default release rate based on the most likely containment

failure mode. .(445/8943-48; 446/8943-48)

7.1;5

Protective Action Decisionmaking

The appraisal team used two types of scenarios: one resulting in a

general emergency with core damage and a radiological release.

Another scenario resulted in a general emergency with buildup of.a

-large source term in containment, no release in progress, and

degrading plant conditions that were precursors to a probable

radiological release.

The appraisal team noted that the PARS developed, based on dose

projections associatod with a potential release, were correct and

baseline PARS were used appropriately for initial recommendations;

however, PARS based on core and containment conditions were not

incorporated in the decisionmaking process.

(See 5.3, " Implementing

Instructions.")

Based on the above findings, the following item is identified as

a significant appraisal finding:

Modify training materials to incorporate PARS based on core and

containment conditions and retrain all personnel having

responsibilities to formulate PARS.

(445/8943-49; (46/8943-49)

. _ _ _ _ _ _ _ _

. _ - - _ _ _ - _ _ - _ _ _ _ _ _ _ - _ - - - _ _ _ _ _ _

.

__

- _ . _ - _ _ _ - - -

__ _ _ _ _ _ _ _ _ ,

ll g&s ',\\

,

n..

9.-

'

-

.R 0 : * .

,

.

' 35 '

-

-

..

'

7.1'. 6 -

Offsite, Onsite, and In-Plant Radiological Monitoring

'

The ap'praisal.teatii performed a walk-through for one offsite

,

,

. radiological monitoring team. -Activities observed during the

walk-through-included assembly of. the team, equipment and' supplies,

plume monitoring techniques, air sampling:and analysis methods,

environmental sampling procedures, and recordkeeping. Performance of

C

the. team was adequate.

,

Based on the above' review, this portion of the applicant's program

appears-to be' adequate.

8.0 EXIT MEETING

.At the conclu'sion of the appraisal, the appraisers reviewed the

findings identified in this report and the applicant agreed to take

corrective actions.

The applicant did not identify as proprietary

any of'the materials provided to or reviewed by the appraisers during the

appraisal.

.

O

_ _ _ _ . _

. _ _ . . _ _ _ . _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ .

_ _ _ . - - . _ - - _ --

.

___

_ -_ _- _ __ ._ -

. _ _

_ - _ .

_.

_ - _ _ - . _ _ _ _ _ _

. _ _ . .

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _

o ,5 ' ,

m.

?

,

y

.

-36-

1

-9.0

PERSONS CONTACTED

L. Barnes, Operations Coordinator

D.-Basinger, Balance of Plant Operator

T. Beaudin, Shift Supervisor

R. Beleckis, Senior Emergency Planner

,

M..Blevins, TSC Manager

T. Carden, Staff Emergency Planner

W. Carden, Radiation _ Protection Technician

a

D. Carlson, Auxiliary Operator

B. Clark, Shift Technical Advisor

T. Clouser, Balance of Plant Operator

V. Cornell, Licensing Engineer

C. Cotton, Assistant Shift Supervisor

D.' Curry, Balance of Plant Operator

J. Curtis, Radiation Protection Supervisor

S. Cyphen, Auxiliary Operator

T. Daskam, Shift Supervisor

P. Daugherty, Auxiliary Operator

D. Davis, Engineering Team Coordinator

K. Davis, Assistant Shift Supervisor

N. Eggenmayer, Assistant Shift Supervisor

R. Fishencord, Radiation Protection Supervisor - Rad Waste

E. Floyd, Radiation Protection Technician

R. Garces, Health Physics Technician

D. Goodwin, Shift Technical Advisor

B. Grace, Radiation Protection Coordinator

N. Harris, Senior Quality Assurance Technician

S. Harvty, Shift Superviser

W. Hise, Industrial Safety Supervisor

T. Jenkins, Engineering Support Coordinator

S. Johnson, Results Systems Engineer

J. Kelly, TSC Manager

M. Kertz, Reactor Operator

W. Knowles, Radiation Protection Technician

J. Laughlin, Emergency Coordinator Advisor

M. Lucas, Electrical Engineering Supervisor

.

J. Luna, Radiation Protection Technician

C. Mansfield, Staff Health Physicist

R. McCamey, Staff Chemist

J. McInvale, Shift Technical Advisor

J. McMahon, Communications Coordinator

.

L. Meller, Auxiliary Operator

W. Melton, Emergency Coordinator Advisor

M. Mitchum, I & C Supervisor

D. Moore, Operations Coordinator

R. Muncy, Auxiliary Operator

L. Nace, EOF Manager

M. Niemeyer, Communications Coordinator

~

W. Nix, Senior Emergency Planner

,

_

_ __ _ - _ _ _ _ _ _ - - _ - - _ - _ - _ - _ _ _

,

_

. _ _ _ _ . _ _ _ _ _ - _ _ _ . _ _ .

-

__ ____- _

___

-

_-

. - - _ - _ _ _ _ - _ - - _

.

' 3_.;,_c

-

-

ry o,r o

!,j dL

. *

.o

-37-

-

.

-

G.'Nuchow, Reactor _ Operator

P. Olson, Auxiliary Operator

L. Pope, TSC Advisor

A. Redlow,~ Radiation Protection Supervisor

A. Reiff, Radiation Protection Training Coordinator

C. Rickgauer, Engineering Team Coordinator

T. Robinson, Emergency Preparedness Specialist

D. Ross, Reactor Operator

,,

T. Rucker, Balance of Plant Operator

J.LSalsman, Site Emergency Planning Coordinator

B. Scanlon,.TSC Advisor

E. Schmidt, Radiation Protection' Manager

E. Sirois, Senior Engineer

<

R. Smith, Shift Technical Advisor

M. Smith, Shift Supervisor

B. Smith, Assitant Shift Supervisor

T. Spalding, Staff Chemist

M. Stakes, Staff Engineer,. Technical Support

W. Stengar,' Staff Emergency Planner

,

i-

P. Stevens, Engineering Support Coordinator

T. Stewart, Auxiliary Operator

F. Sutherland, Reactor Operator.

J. Taylor, Master Pcrts List Supervisor

N..Terrell, Operations Engineering Supervisor

D. Walden, Site Coordinator, Fire and Medical

J. Warkentin, Principal Engineer, Nuclear Engineering

J. Wise, Auxiliary Operator

NRC also held discussions with other station and curporate personnel in

the areas' of security, health physics, operations, training, and emergency

i

response,

In addition, NRC contacted representatives of offsite agencies.

,

9

1'

9

9

l.

e-

_

_ _ . _ . _ . _

. _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ - _ _ _ _ . _ . _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _