Provides Revised Response to Item 2 to IE Bulletin 79-15, Deep Draft Pump Deficiencies. Review of Operating & Maint History Shows No Significant Design,Assembly or Installation Problems W/Pumps Since Initial Operation
ML20246L048
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 07/11/1989
From: William Cahill
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
IEB-79-15, TXX-89426, NUDOCS 8907180332
Download: ML20246L048 (3)


Text

. _.

l.

-=

K Log # TXX-89426 L

J File # 10119 Ref. # IEB 79-15 1UELECTRIC July 11, 1989 l-1.

I' U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C.

20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET KOS 50-445 AND 50-446 IE BULLETIN 79-15:

DEEP DRAFT PUMP DEFICIENCIES REF: TUGCo Letter TXX-3430 from Mr. R. J. Gary to Mr. H. R. Denton of NRC, dated October 26, 1981 Gentlemen:

The referenced letter provided the CPSES response to the NRC staff's request for additional information concerning IE Bulletin 79-15 and the programs implemented to ensure long-term reliability of the Service Water pumps.

Item

2) in that response reads as follows:

" Radial vibration readings will be taken on the top three pump. bearings at regular intervals to detect changes in operating parameters. Complete signature trace analysis will be conducted as necessary in order to trend overall equipment performance."

Based on a recent review of this response and the inaccessibility of the pump bearings TU Electric provides the following' discussion and revised response to Item 2):

" Radial vibration readings will be taken on the upper and lower motor bearings and axial vibration readings will be taken on the upper motor bearing.

Complete signature trace analysis will be conducted as necessary in order to trend overall equipment performance."

Discussion:

The Unit I and Unit 2 pumps were initially operated in 1982 and 1986 respectively. Both sets of pumps have been run extensively since their initial operation.

A review of the operating and maintenance history of the pumps shows that there have been no significant uesign, assembly, or installation problems with the pumps since their initial operation.

TU Electric considers that measuring and trending vibration transmitted through the rigid flange type motor / pump coupling provides an acceptable

'j method of monitoring pump and shaft bearing conditions. Additionally, the vibration of operating Service Water pumps is monitored at nominal six-week intervals, which exceeds the quarterly monitoring requirement of our Inservice Testing program. The increased monitoring frequency provides added assurance that any bearing degradation woul,d be detected prior to pump failure.

8907180332 890711 jh$d m mr Danas. Texm 7520 PDR ADOCK 05000445 Q

PDC t\\

...',?

, i TXX-89426' July 11,.1989 Page 2 of 3 In an effort-to determine the common industry practice for monitoring such pumps TU Electric has contacted several.other _ nuclear power plents with deep draft Service Water pumps., All the plants contacted reported that vibration readings'for their Service Water pumps are taken only at the motor end of the pump / motor train.-

Sincerely, I

6%

William J. Ca1111, Jr.

HCP/vid c

.Mr. R. D. Martin, Region IV Resident Insper. tors, CPSES (3) l l

1 1

]

I' ^

~

p...., -

1. :. ; -.. ;

TXX-89426 July 11, 1989 Page 3 of 3 r

UNITED STATES OF AMERICA-NUCLEAR REGULATORY COMMISSION In the Matter of

)

)

Texas Utilities Electric Company

)

Docket Nos, 50-445

)

50-446' (Comanche Peak Steam Electric

)

' Station,. Units 1 & 2)

)

AFf'IDAVIT William J. CaH11 being duly swcrn, hereby deposes and says that he is Executive Vice President, Nuclear of TU Electric..the Applicant herein;-that he is' duly authorized to sign and file with the Nuclear Regulatory Commission this additional response to IE Bulletin 7P-15 that he is familiar with the content thereof;.and that the matters set forth therein are true and correct.

to 'the best of his knowledge, information and belief.

WilliamJ.Cafil

//'

Executive Vice President, Nuclear STATE OF TEXAS

)

)

COUNTY OF DALLAS

)