Text
- - - _ _ _
e
===-.
File # 10130 IR 88-43 Ref. # 10CFR2.201 1EFELECTRIC July 13, 1989 i
U. S. Nuclear Regulatory Commission l
Attn: Document Control Desk Washington, D. C.
20555
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)
DOCKET NO. 50-446 REVISED DATE OF FULL COMPLIANCE FOR NOTICE OF VIOLATION (NOV) 446/8843-V-01 REF: TU Electric letter TXX-89028 from W. J. Cahill, Jr.
to USNRC, dated January 20, 1989 Gentlemen:
The referenced letter provided TU Electric's response to NOV 446/8843-V-03.
In that response. TU Electric stated that by July 13, 1989, an update would be provided.to indi:cate a completion date for removal and examination of the spool piece from the Unit 2 Safety Injection System. The commencement of Unit 2 scheduling activities has been postponed. Therefore, this item will be scheduled to be completed six months prior to Unit 2 fuel load.
Sincerely, l
l William J. Cr. hill, Jr.
JLR/vid i
c - Mr. R. D. Martin, Region IV Resident Inspectors, CPSES (3) j i