ML20246G104

From kanterella
Jump to navigation Jump to search
Responds to NRC Re Violations Noted in Insp Repts 50-413/89-05 & 50-414/89-05.Corrective Actions:Procedure Changes Will Be Rewritten for CA Check Valve Leak Rate Test
ML20246G104
Person / Time
Site: Catawba  
Issue date: 04/27/1989
From: Tucker H
DUKE POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 8905150187
Download: ML20246G104 (2)


Text

-

4 4

Duke 1%utr Cornpany litt B hkr c

PO Box 33198 1' ice President Charlotte, N C. 2H242 Nw. lear Production

{701)]73st531 DUKEPOWER April 27, 1989 U. S. Nuclear Regulatory Commission Washington, D.C.

20555 Attention:

Document Control Desk

Subject:

Catawba Nuclear Station, Units 1 and 2 Docket Nos. 50-413 and 50-414 NRC Inspection Report No. 50-413,-414/89-05 Reply to a Notice of Violation i

Gentlemen:

Please find attached a reply to Violation No. 413/89-05-02 which was transmitted l

per Alan R. Herdt's, NRC Region II, Notice of Violation dated March 29, 1989.

This Severity Level IV violation involved an inadequate test procedure to ensure Auxiliary Feedwater piping is vented after filling.

Very truly yours,

/. /

/

/

g H. B. Tucker WTB43/lcs Attachment xc: Mr. S. D. Ebneter Regional Administrator, Region II U. S. Nuclear Regulatory Commission 101 Marietta St., NW, Suite 2900 Atlanta, Georgia 30323 Mr. W. T. Orders NRC Resident Inspector Catawba Nuclear Station l

}

Di l

8905150187 890427 PDR ADOCK 05000413 O

PDC u _ __

p.

DUKE POWER COMPANY REPLY TO A NOTICE OF VIOLATION 413/89-05-02 Technical Specification 6.8.1 requires that written procedures j

shall be established, implemented and maintained covering the activities referenced in Appendix A of Regulatory Guide 1.33, l

Revision 2, February 1978 which includes the requirement that instructions be prepared for filling and venting the Auxiliary Feedwater System.

Contrary to the above, PT/1/A/4200/55, "CA Check Valve Leak Rate Test" is inadequate to ensure the auxiliary feedwater suction piping is vented after filling in that during the system restoration high point vent valves 1CA-141 and 1CA-195 are closed i

prior to the line being filled.

RESPONSE

1.

Admission or Denial of Deviation Duke Power company admits the violation 2.

Reason for Deviation if Admitted Inadequate procedure.

Proper venting and filling of the CA suction piping was assumed to be in an operating procedure / instruction.

This was not the case.

3.

Corrective Actions Taken and Results Achieved There were no immediate actions as this situation was identified after the fact, and the test is a cold shutdown test.

4.

Corrective Actions to be Taken to avoid further Deviations Procedure changes will be written for both Unit 1 and Unit 2 "CA Check Valve Leak Rate Test".

5.

Date of Full Compliance The procedures will be changed by June 1, 1989 or before the test is next conducted, whichever comes first.