ML20246C146

From kanterella
Jump to navigation Jump to search
Forwards Insp Repts 50-445/89-36 & 50-446/89-36 on 890503- 0606.No Violations or Deviations Noted
ML20246C146
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 06/28/1989
From: Warnick R
Office of Nuclear Reactor Regulation
To: William Cahill
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
Shared Package
ML20246C149 List:
References
NUDOCS 8907100262
Download: ML20246C146 (4)


See also: IR 05000445/1989036

Text

_

-

-

-

.

% .

..

,

,

M 2 81989

' In Reply Refer To:

Dockets:

50-445/89-36

50-446/89-36

Mr. W. J. Cahill

>

Executive Vice President

TU Electric

400 North Olive Street, Lock Box 81

Dallas, Texas

75201

Dear Mr. Cahill:

This refers to the inspection conducted by Mr. R. M. Latta and an

,

'

NRC consultant during the period May 3 through June 6, 1989, of

activities authorized by NRC Construction Permits CPPR-126 and

CPPR-127 for the Comanche Peak Steam Electric Station, Units 1

and 2, and to the discussion of our findings with you and other

members of your staff at the conclusion of the inspection. .

The enclosed copy of our inspection report identifies areas examined

during the inspection.

Within these areas, the inspection consisted

of selective examination of procedures and representative records,

interviews with personnel, and observations by the inspectors.

Within the scope of the inspection, no violations or deviations were

identified.

In accordance with 10 CFR 2.790 of the Commission's regulations,-a

copy of this letter and the enclosed inspection report will be

placed in the NRC Public Document Room.

Should you have any questions concerning this inspection, we will be

pleased to discuss them with you.

Sincerely,

- '

ORIGINAL s:cngD BY R F. WARNICT

R. F. Warnick, Assistant Director

for Inspection Programs

l

Comanche Peak Project Division

'

Office of Nuclear Reactor Regulation

l

Enclosure:

Inspection Report 50-445/89-36; 50-446/89-36

cc w/ enclosure:

See next page

IP:CPPDJ:

IP:CPPD:NRR

AD:IP:CPPD:NRR

'

RLatta g/

HLivermore

RWarnick RFR>

0'

6/#6/89

6/77/89

6/27/89

7

\\ \\

<

'

8907100262 890628

l

PDR

ADOCK 05000445

G

PNU

-

_ _ -

b< .

(

o attu(Io,

UNITED $TATES -

.. .

,

1. -

NUCLEAR REGULATORY COMMISSION

o

l-

.y,-

<E

WASHINGTON, D. C. 20655

,

f

j

JUN 2 81989

'

.....

In Reply Refer To:

Dockets:

50-445/89-36

4

50-446/89-36-

l

.i

!

!

Mr. W.

J. Cahill

Executive Vice President.

4

TU Electric

I

'400 North Olive Street, Lock Box 81

Dallas, Texas

75201

Dear Mr. Cahill:

This refers to the inspection conducted by Mr. R. M. Lutta and an

NRC consultant during the period May 3 through June 6, 1989, of

activities authorized by NRC Construction Permits CPPR-126 and

CPPR-127 for the Comanche Peak Steam Electric Station, Units 1

and 2, and to the discussion of our findings with you and other

members of your staff at the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas exarained

during the inspection.

Within these areas, the inspection consisted

of selective examination of procedures and representative records,

interviews with personnel, and observations by the inspectors.

Within the scope of the inspectics, no violations or deviations were

identified.

In accordance with 10 CFR 2.790 of the Commission's regulations, a

copy of this letter and the enclosed inspection report will be

placed in the NRC Public Document Room.

Should you have any questions concerning this inspection, we will be

pleased to discuss them with you.

' Sincerely,

.

R F k)wunkk

R. F. Warnick, Assistant Director

for Inspection Progrmns

I

Comanche Peak Project Division

Office of Nuclear Reactor Regulation

Enclosure:

j

Inspection Report 50-445/89-36; 50-446/89-36

J

!

cc w/ enclosure:

]

See next page

!

i

l

m

?

..

.

W.

J. Cahill

-

.

'

cc:

-Roger D. Walker

TU. Electric

,

Manager, Nuclear Licensing

c/o Bethesda Licensing

TU Electric

3 Metro' Center,. Suite 610

Skyway Tower

Bethesda, Maryland

20814

400 North Olive Street, L.B.

81

i

Dallas ,1DC

75201

E.

F. Ottney

P. O. Box 1777

Juanita Ellis

Glen Rose, Texas

76043

President - CASE

1

1426 South Polk Street

Joseph F. Fulbright

Dallas, TX

75224

Fulbright & Jaworski

1301 McKinney Street

Susan M. Theisen

Houston, Texas

77010

Assistant. Attorney General

Environmental Protection Division

George A. Parker, Chairman

P.O. Box 12548,-Capitol Station

Public Utility Committee

Austin, TX- 78711-1548

Senior Citizens Alliance of

Tarrant County, Inc.

GDS Associates, Inc.

6048 Wonder Drive

1850 Parkway Place, Suite 720

Fort Worth, Texas

76133

Marietta, GA

30067-8237

Jack R. Newman, Esq.

Lanny A. Sinkin

Newman & Holtzinger, P.C.

Christic Institute

Suite 1000

l

1324 N. Capitol Street

1615 L.. Street N.W.

i

Washington, DC

20002

Washington, D.C.

20036

Ms. Billie Pirner Garde, Esq.

Garde Law Office

104 East Wisconsin Avenue

Appleton, WI

54911

Regional Administrator, Region IV

U.S. Nuclear Regulatory Commisaion

611 Ryan Plaza Drive, Suite 1000

Arlington, Texas

76011

William A. Burchette, Esq.

Counsel for Tex-La Electric

Cooperative of Texas

i

Heron, Burchette, Ruckert & Rothwell

1025 Thomas Jefferson St., NW

,

!

Washington, DC

20007

l

l

I