Informs That Response to Generic Ltr 88-14 Acceptable for Meeting Generic Guidance Re Instrument Air Supply Sys
ML20245L127
Person / Time
Site: Fermi 
Issue date: 04/26/1989
From: Kelly L
Office of Nuclear Reactor Regulation
To: Sylvia B
DETROIT EDISON CO.
References
GL-88-14, TAC-71659, NUDOCS 8905050288
Download: ML20245L127 (4)


Text

,.. _ _ _ _ -. _ _ _ _ _ _. -. _ _ _ _ _ _ _ _ _ _

p 9s Vl

?"[,

'o UNITED STATES

.3

?,j p' 3[

g NUCLEAR REGULATORY COMMISSION'

' WASHINGTON, D. C. 20666 s

);E Doc Mt No. 50-341

~

Mr. B. Ralph Sylvia Senior Vice President - Nuclear Operation Detroit Edison Company 6400'N. Dixie Highway Newport, Michigan 48166

Dear Mr. Sylvia:

SUBJECT:

FERMI-2 NUCLEAR POWER PLANT:

RESPONSE TO NRC GENERIC LETTER 88-14 (TAC NO. '71659)

The staff has reviewed your March 1,'1989 (NRC-89-0046) and April 24, 1989 (NRC-89-0091) responses to Generic Letter (GL) 88-14 concerning Detroit Edison's (DECO) design and operations verification of the instrument air system at Fermi-2.

The April 24, 1989 letter identified a correction to the March 1, 1989 submittal.

' The March.1,1989 letter identified the following commitments that Detroit Edison

-has made to meet _our generic guidance.

Please confirm that this list matches your understanding of all outstanding GL 88-14 items for implementation by Deco.

-(1) DECO has committed to change the testing frequency for the dew point check of the noninterruptible control air system, Division:II, under procedure NRP 35.622.002 from a quarterly to a monthly activity by March 31, 1989 (part of response to GL 88-14 Item No. 1).

Under this same procedure, the check of the dew point at the outlet of the dryers will be changed from a quarterly to a monthly activity.(part of response to GL 88-14 item No. 2).

(2) DECO has committed to develop surveillance procedures, by the first-

=

refueling outage, to test the isolation capabilities for the accumulators of the noninterruptible control air system (part of response to GL 88-14 item No. 2).

This surveillance is to be included in the Inservice Testing program, i

l (3) Deco has committed to install a permanent heatless air dryer for the 1

interruptible control air system under EDP 5323 by the first j

refueling outage (part of response to GL 88-14 item No. 2).

(4) Deco has committed to establish and/or revise additional PMs for the station air system by the fir't r.efeeling outage when the compressors, aftercoolers, and receiver tanks drain improvement is completed (part of response to GL 88-14 item No. 2).

(5) DECO has committed to install a permanent parallel interruptible control air dryer to the station air system when EDP 5323 is implemented (part of response to GL 88-14 item No. 2).

(6) DECO has stated that requalification classes have been updated to include discussion and simulation of loss of instrument air scenario.

DECO has scheduled to complete these requalification classes by April 14, 1989 (part of response to GL 88-14 item No. 2).

Ahhk$$$h42 m

.3

.. (7) By June 30, 1989, Deco has connitted to having maintenance personnel complete their reading of Generic Letter 88-14 and Fermi-2's response to it (part of response to GL 88-14 item No. 2).

(8) Deco has connitted to testing of the ADS, LLS & MSIV accumulators to assure acceptable check valve leakage rates under surveillance procedures 43.137.02 and 43.201.01 during refueling outages. The procedures are presently'being developed and are scheduled.for issuance by Apr11.15, 1989 (part of response to GL 88-14 item No. 3).

The ' staff finds your response to Generic Letter 88-14 to be acceptable for meeting our generic guidance concerning instrument air supply system problems affecting safety-related equipment.

Please notify us when you have completed your implementation' of the identified outstanding GL 88-14-consitments.

Sincerely, W

Lynn Kelly,, Project Manager Project Directorate III-1 Division of Reactor Projects - III, IV, V and Special Projects cc: See next page

)1STRLBUT.0N Hmckaufred NRC & Local'PDRs GHolahan MVirgilio PShuttleworth

@I

'.RIngram LKelly

'JStang GEdison WLefave OGC EJordan BGrines ACRS(10)

PD31 Gray File LA/PD3 jl:DRSP PM/PD31:DRSP P I 3~1:DRSP (A)D 1:DRSP ShW1Teworth LKelly L1C J

J

)E6MO 4/l8'/89 4/f6/89 4

89 a 89 i

OFFICIAL RECORD COPY

3 l,

(7) By June 30, 1989, DECO has committed to having maintenance personnel complete their reading of Generic Letter 88-14 and Fermi-2's responsetoit(partofresponsetoGL88-14itemNo.2).

(8) Deco has committed to testing of the ADS, LLS & KSIV accumulators to assure acceptable check valve leakage rates under surveillance procedures 43.137.02 and 43.201.01 during refueling outages. The procedures are presently being developed and are scheduled for issuance by April 15, 1989 (part of response to GL 88-14 item No. 3).

The staff finds your response to Generic Letter 88-14 to be acceptable for meeting our generic guidatice concerning instrument air supply system problems affecting safety-related equipment. Please notify us when y&u nave completed

- your implementation of the identified outstanding GL 88-14 commitunts.

Sincerely,

/

Lynn Kelly, Project Manager Project Directorate 111-1 1

Division of Reactor frojects - III, j

IV, Y and Special Projects cc: See next page I

R 1

l..

Mr. B. Ralph Sylvia.

Fermi-2 Facility Detroit Edison Company cc:

-Mr. Ronald C. Callen Ms. Lynn Goodman Adv. Planning Review Section Supervisor - Licensing Michigan Public Service Commission Detroit Edison Company 6545 Mercantile Way Fermi Unit 2 P. O. Box 30221 6400 North Dixie Highway Lansing, Michigan 48909 Newport, Michigan 48166 John Flynn, Esq.

Senior Attorney Detroit Edison Company 2000 Second Avenue.

Detroit, Michigan 48226 Nuclear Facilities and Environmental

. Monitoring Section Office Division of Radiological Health P. O. Box 30035 Lansing, Michigan 48909 Mr. Thomas Randazzo Director,-Regulatory Affairs Detroit Edison Company Fermi Unit 2 6400 North Dixie Highway Newport, Michigan 48166 Mr. Walt Rogers U.S. Nuclear Regulatory Commission Resident Inspector's Office 6450 W. Dixie Highway Newport, Michigan 48166 Monroe County Office of Civil Preparedness 963 South Raisinville Monroe, Michigan 48161 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 799RooseveltRpad Glen Ellyn, Illinois 60137 l

[