Notice of Violation from Insp on 890607-30.Violation Noted: Procedure 0P0P04-RP-0001 Did Not Provide Adequate Guidance Re Expected Failure of Reactor Protection Pressure Channel During Low Temp Low Pressure Operations
ML20245J528
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 08/10/1989
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20245J525 List:
References
50-498-89-15, 50-499-89-15, NUDOCS 8908180058
Download: ML20245J528 (2)


Text

_ _ - _ _ _ . -_ ., . - - .

p. k% k. i,1 b

-f . j [

~

gm'1 APPENDIX A.

NOTICE OF VIOLATION' Houston O ghting & Power Company' ' Dockets: 50-498

. South Texas Project, Units-1 and 2 50-499 Operating Licenses: :NPF-76 n NPF-80

< During an NRC inspection' conducted'during the period June 7-30. 1989, a violation of NRC requirements was identified. The violation involved inadequate: procedures for abnormal operating conditions.: In accordance with the " General Statement 2, , of Policy and Procedure for NRC Enforcement Actions," 10 CFR' Part 2. Appendix C :

(1988),theviolationislistedbelow: >

Inadequate Abnormal Procedures Technical. Specification 6.8.1 requires, in part, that procedures shall be established-and implemented covering . . . a. the' applicable procedures recommended in Appendix A of Regulatory GCde 1.33. Revision 2 February 1978.

s Appendix A of Regulatory Guide 1.33, Sections 5 and 6, require, in part, that procedures for safety-related activities should be' established which address abnormal, off-normal, alarm, and emergency /other significant events / conditions.

South Texas Project FSAR,.Section 13.5.2, paragraph 3. "Off-Normal Operating Procedures," addresses this requirement by stating that necessary

. instructions / procedures for restoring an operating variable to its normal operating. condition will be-provided when the controlled value departs from the normal. range or following a perturbation which could degrade if proper

. :n action were not taken. A minimum list of plant off-normal operating procedures to.be prepared initially was provided-in the FSAR. The list.

included the following items:

Loss of~ automatic pressurizer control Malfunction of rod control system Turbine'lond rejection

. Contrary to the above.

1. Procedure OPOPO4-RP-0001, " Loss of Automatic Pressurizer Pressure ,

, ' Control," did not provide adequate guidance regarding the expected failure of a reactor protection pressere channel during low temperature-low pressure operations.

2. Procedures OPOP04-RP-0001 " Loss of Automatic Pressurizer Pressure Control," and OPOPO4-RP-0002, " Loss of Automatic Pressurizer Level Control," ~did not address the failure of a reactor protection channel (pressurizer pressure or level channels, respectively) if the failed channel'was not selected for the control function.

8908180058 890810 I DR ADOCK 05000498

= -

3 - -- -

1 ' f-c 2 l ~4 4

- 3. ~A; written procedure had not been provided addressing the failure of a reactor coolant' system temperature protection / control channel.

1

4. 'A written procedure had not been provided' addressing the malfunction of the' automatic reactivity control system.

This is a Severity Level IV' violation. .(Supplements)(498/8915-01; 499/8915-01)

Pursuant to the provisions of 10 CFR 2.201, Houston Lighting & Power Company.is hereby required to submit to this office, within 30 days.of the date. of the letter transmitting this Notice, a written statement or explanation-in reply,

'. including .for each violationr (1) the reason,for the violation if admitted, (2) the corrective steps which have been taken and the results achieved, (3) the corrective steps.which will be taken-to avoid further violations, and (4) the date when full compliance will be achieved.= Where good cause is shown, consideration will be given,to extending the. response time.

Dated at Arlington.. Texas, this /@ day of g 1989 2____-__-____-__-_ -- ._