Requests Completion of Radiochemical Analyses of Liquid Samples Spiked W/Radionuclide within 60 Days of Receipt of Samples
ML20245G317
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 06/13/1989
From: Dan Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Hairston W
ALABAMA POWER CO.
References
NUDOCS 8906290094
Download: ML20245G317 (2)


Text

.

O[k/CIQl JUN i 31989 Alabama Power Company ATTN: Mr. W. G. Hairston, III Senior Vice President-Nuclear Operations P. O. Box 2641 Birmingham, AL 35291-0400 Gentlemen:

SUBJECT:

DOCKET N05.50-34R AND 50-364 As part of the NRC Confirmatory Measurements Program, liquid samples spiked with radionuclides will be sent to the Farley facility for radiochemical analyses. These samples are to be analyzed for tritium, iron-55, strontium-89, and strontium-90 in accordance with your approved procedures for analysis of liquid waste samnles. If routine analyses of this type are normally performed by a vendor, this vendor should be used to analyze the spiked samples. The spiked samples, with instructions, will be sent under separate cover from the Department of Energy's Radiological and Environmental Sciences Laboratory, within approximately 30 days.

We request that the analyses be completed as soon as practicable, but no later than 60 days from receipt of the samples. Results should be sent to: U. S.

Nuclear Regulatory Commission, ATTN: Mr. D. M. Collins. Our evaluation of your results will be discussed with your staff and transmitted in a letter.

Spiked samples will be sent to you on an annual basis as part of our routine inspection program.

If you have any questions regarding this program, please contact Mr. Collins at 404-331-5586, or Ms. Adamovitz at 404-331-4774.

Sincerely.

0Qinal3fgffad By D. M. Co!! irs Douglas M. Collins, Chief Emergency Preparedness and Radiological Protection Branch Division of Radiation Safety and Safeguards cc: (See page 2) l l

8906290094 090613 ~

P PDR ADOCK 05000340 PNV p

. l

,jo e

Alabama Power Company 2 cc: B. M. Guthrie, Executive Vice President D. N. Morey, General Manager -

Nuclear Plant J. D. Woodard, Vice President -

Nuclear Generation J. W. McGowan, Manager-Safety Audit and Engineering Review S. Fulmer, Supervisor-Safety Audit and Engineering Review D. Grissette, Chemistry and Environmental Supervisor State of Alabama bec: NRC Resident Inspector E. Reeves, Project Manager, NRR Document Control Desk f 7.'I DSeymour SAdamovitz - .(I I" F C,b@gt 6/[V89 6/(7/ 89 6/ /89 g , .j , 7,)

l

<