ND-20-1003, Fourteenth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)

From kanterella
(Redirected from ML20244A158)
Jump to navigation Jump to search
Fourteenth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)
ML20244A158
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 08/28/2020
From:
Southern Nuclear Operating Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML20244A156 List:
References
EA-12-049, ND-20-1003
Download: ML20244A158 (4)


Text

Southern Nuclear Operating Company ND-20-1003 Enclosure Vogtle Electric Generating Plant Units 3 and 4 Fourteenth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Bevond-Desiqn-Basis External Events (EA-12-049)

(This enclosure consists of 4 pages including this cover page)

ND-20-1003 Enclosure Fourteenth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049) 1 Introduction Vogtie Eiectric Generating Plant - Units 3 and 4 developed an Overall integrated Plan (Reference 1 In Section 8), documenting the diverse and flexible strategies (FLEX), in response to Nuclear Regulatory Commission Order EA-12-049 (Reference 3), followed by an Updated Overall Integrated Plan (Reference 2). This status report provides an update of milestone accomplishments since the last six-month update, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.

2 Milestone Accomplishments In addition to the submittal of status reports, the following milestone(s) directly related to FLEX implementation have been completed since the last six-month update (Reference 4),

and are current as of August 22, 2020:

Develop FLEX training 3

Milestone Schedule Status The following table provides an update to the milestone schedule with the activity status of each item and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed. The revised milestone target completion dates do not impact the Order implementation date.

Milestone Target Completion Date Activity Status Revised Target Compietion Date (Aug 22, 2020 data date)

Submit 60 Day Status Report Oct2012 Complete N/A Submit Overall Integrated Plan (OIP)

Aug 2013 Complete N/A Submit 6 Month Status Report Feb 2014 Complete N/A Submit 6 Month Status Report Aug 2014 Complete N/A Submit 6 Month Status Report Feb 2015 Complete N/A Submit 6 Month Status Report Aug 2015 Complete N/A Submit 6 Month Status Report Feb 2016 Complete N/A Submit 6 Month Status Report Aug 2016 Complete N/A Submit 6 Month Status Report Feb 2017 Complete N/A Submit 6 Month Status Report Aug 2017 Complete N/A Submit 6 Month Status Report Feb 2018 Complete N/A Submit 6 Month Status Report Aug 2018 Complete N/A Submit 11"^ 6-Month Status Report Feb 2019 Complete N/A Submit 12"^ 6-Month Status Report Aug 2019 Complete N/A Staffing Analysis Complete Unit 3 Oct2019 Complete N/A Submit 13"" 6-Month Status Report Feb 2020 Complete N/A Submit 14"^ 6-Month Status Report Aug 2020 Complete N/A Page 2 of 4

ND-20-1003 Enclosure Fourteenth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)

Milestone Target Completion Date Activity Status Revised Target Completion Date (Aug 22, 2020 data date)

Develop FLEX training May 2020 Complete N/A Initiate Phase 3 Equipment Procurement -

Units 3 and 4 Feb 2020 Complete N/A Ensure remaining BDB Nuclear Management Procedure (NMP) revisions and program documents (e.g., EOF, TSC, and SEC responses, EP procedures) include necessary information Apr 2020 In Progress Oct 2020 Ensure Operations' BDB procedures (e.g.,

FSGs/SIGs) include necessary information Jun 2020 In Progress Oct 2020 Develop Response Plan with NSRC (storage plan and procedural guidance for strategy/maintenance) -

Units 3 and 4 Aug 2020 In Progress Sept 2020 Training complete and documented for Phase 3 to include connection and use of redundant offsite equipment for Ancillary Equipment.

Oct 2020 In Progress Nov 2020 National SAFER Response Center (NSRC)

Operational for Units 3 and 4 Aug 2020 In Progress Oct 2020 Submit Order EA-12-049 Compliance Report for Unit 3 Nov 2020 In Progress N/A Submit 15'*^ 6-Month Status Report Feb 2021 Not started N/A Submit 16'^ 6-Month Status Report Aug 2021 Not started N/A Staffing Analysis Complete Units 3 and 4 May 2021 In Progress N/A Submit Order EA-12-049 Compliance Report for Unit 4 and Final Integrated Plan (FIP)

Sept 2021 Not started Oct 2021 4

Changes to Compliance Method There are no changes to the compliance method as documented in Reference 2.

5 Need for Relief/Relaxation and Basts for the Relief/Relaxation Vogtle Electric Generating Plant - Units 3 and 4 expects to comply with the order implementation date and no relief/relaxation is required at this time.

6 Open Items from Overall Integrated Plan and Draft Safety Evaluation The following tables provide a summary of the open items documented in the Overall Integrated Plan or the Draft Safety Evaluation (SE) and the status of each item.

Page 3 of 4

ND-20-1003 Enclosure Fourteenth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)

Overall Integrated Plan Open Item Status N/A N/A Draft Safety Evaluation Open Item Status Draft Safety Evaluation not received N/A 7

Potential Draft Safety Evaluation Impacts A Draft Safety Evaluation has not been received.

8 References The following references support the updates to the Overall Integrated Plan described in this enclosure.

1. SNC Letter ND-13-1702, Vogtle Electric Generating Piant Units 3 and 4 Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis Externai Events (Order Number EA-12-049), dated August 22, 2013.
2. SNC Letter ND-20-0164, Vogtie Eiectric Generating Piant Units 3 and 4 Updated Overaii Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order EA-12-049), dated May 15, 2020.
3. NRC Order Number EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis Externai Events, dated March 12, 2012.
4. SNC letter ND-20-0165, Vogtie Eiectric Generating Plant -

Units 3 and 4 Thirteenth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049), dated February 28, 2020.

Page 4 of 4