Text

_ _ _ - _ _ - _ _ _ _ _ _ _ _

DEC 241987 Docket No. 50-266 50-301 Point Beach Nuclear Plant ATTN: Mr. Dave Stevens Emergency Planning Coordinator 6610 Nuclear Rd.

Two Rivers, WI 54241 Gentlemen:

Based on the December 14, 1987, telephone conversation between you and Mr.' Gary Shear of my staff, it is my understanding that January 5 and 6,1988, was agreed upon as dates for our site visit to tour your emergency response facilities.

Recent experience in the Federal Field Exercise identified the need for Region III to evaluate each licensee's emergency response facilities to determine if the NRC's Expanded Activation Site Team can be adequately accommodated.

IE Information Notice No. 86-18 described the planned composition and location of the NRC Site Team that would respond to a major-nuclear power plant accident.

Region III does not expect licensees to backfit to provide increased facility space.

Facilities that have been constructed and approved under current regulations and guidance may not have the capability to accommodate the NRC Expanded Site Team as outlined in Information Notice 86-18.

Our goal is to consider with each licensee, ways of making more efficient use of available space, of providing adequate communications, and of identifying alternate space where relevant data could be made available in a timely, reliable manner.

Attached to this letter is an outline of the areas we will be reviewing.

If there are questions regarding any of the above, please contact me at (312) 790-5513 or Gary Shear of my staff at (312) 790-5620.

Sincerely,

" Original cigned by U. Snell" William Snell, Chief Emergency Preparedness Section

Attachment:

As stated cc wo attachment:

J. A. Hind j

W. D. Shafer 7

5 f

ear /ib Snell l.l 8801040057 871224 PDR ADOCK 05000266

_____b_______--__

l ATTACHMENT

~

OUTLINE FOR EVALUATING LICENSEE ACCOMMODATIONS FOR NRC SITE TEAM I.-

Communications A.

Telephone Capabilities 1.

Number of Available Phones 2.

Location of Available Phones 3.

Type of Phone Service (e.g., voice activated)

B.

Computer Compatibility

.i II. Size and Layout of TSC and EOF A.

Space Availability for Expanded Site Team B.

Seating and Desk Arrangements for Expanded Site Team C.

Location of Key Counterpart Licensee Personnel D.

Conferencing Space for NRC Personnel III. Alternate Space l

)