Forwards Insp Rept 50-267/87-17 on 870701-31.Violations Noted.Enforcement Conference Scheduled for 870910 to Discuss Util Understanding of Violations,Reasons for Occurrence & Corrective Actions.Meeting Agenda Also Encl
ML20238B459
Person / Time
Site: Fort Saint Vrain 
Issue date: 08/28/1987
From: Gagliardo J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Robert Williams
PUBLIC SERVICE CO. OF COLORADO
Shared Package
ML20238B462 List:
References
EA-87-167, NUDOCS 8709010231
Download: ML20238B459 (3)


See also: IR 05000267/1987017

Text

. _ _ .

,

e

AUG S 81987

'

I

i

In Reply Refer To:

i

Docket:

50-267/87-17

EA 87-167

l

J

Public Service Company of Colorsdo

{

ATTN:

Robert 0. Williams, Jr.

(

Vice President, Nuclear

j

Operations

P. O. Box 840

Denver, Colorado

80201

i

Gentlemen:

This refers to the inspection conducted by Messrs. R. E. Farrell, P. W. Michaud,

E. A. Plettner, and M. E. Skow of this office during the period July 1-31, 1987,

of activities authorized by NRC Operating License DPR-34 for Fort St. Vrain

Nuclear Generating Station, and to the discussion of our findings with you and

other members of your staff at the conclusion of the inspection.

Areas examined during the inspection included followup of licensee action on

i

previously identified inspection findings, operational safety verification, ESF

system walkdown, monthly surveillance observation, monthly maintenance observa-

'

tion, security, radiological protection and design control.

Within these areas,

the inspection consisted of selective examination of procedures and representative

records, interviews with personnel, and observations by the NRC inspectors. The

inspection findings are documented in the enclosed inspection report.

During this inspection, it was found that certain of your activities appeared to

be in violation of NRC requirements. As discussed in our telephone conversation

of August 18, 1987, with your staff, we have scheduled an enforcement conference

f

in our office at 1 p.m. on September 10, 1987, to discuss your understanding of

'

these violations, the reasons for occurrence, and your corrective actions. We

will also discuss the NRC Enforcement Policy, if appropriate. An agenda for

j

this meeting is enclosed.

We have also examined actions you have taken with regard to previously

identified inspection findings. The status of these items is identified in

paragraphs 2 and 3 of the enclosed report.

Should you have any questions concerning this inspection, we will be pleased to

discuss them with you.

Sincerely,

8709010231 870028

Original Signed Cy

PDR

ADOCK 0500

7

J. E. Gad!ardo

0

J. E. Gagliardo, Chief

Reactor Projects Branch

Enclosures:

(see next page)

RIV: SRIf8

RI W/

PIf/g/

C:hB/A

E0 DI

C:RPB,

4 REFarrell/tw pPWMichaud

MESkow

JPJaudon

DAPowers

JEGagt a do

k

0

tr/W/87

tr/ay /87

r/u/87

g M/87

y/jg/87

3/y)/ 7

t\\\\

,

_

.

. . .

. .

.

..

.

.

..

.

___________ _ ___ ,

.k

j

.

Public Service Company of Colorado

-2-

i

Enclosures:

1.

Appendix A - NRC Inspection Report

50-267/87-17

2.

Appendix B - Meeting Agenda

cc w/ enclosures:

Manager, Nuclear

,

Production Division

l

Fort St. Vrain Nuclear Generating Station

i

16805 WCR 19 1/2

Platteville, Colorado

80651

P. Tomlinson, Manager, Quality

Assurance Division

(Same Address)

Colorado Radiation Control Program Director

Colorado Public Utilities Commission

bec to DMB (IE01)

bcc distrib. by RIV:

  • RPB

R. D. Martin, RA

i

  • RRI

DRSP

  • Section Chief (RPB/A)
  • RIV File

!

  • Section Chief (RSB/ES)
  • R&SPB
  • RSTS OPERATOR
  • MIS System
  • RSB
  • Project Inspector
  • D. Weiss, RM/ALF
  • R. Hall

,

I

  • Enforcement Officer

l

l

  • w/766

1

i

k]] Eb -i V U 3d

.

.,7

e-

.