ML20238A664

From kanterella
Jump to navigation Jump to search
Responds to NRC Re Violations Noted in Insp Repts 50-338/87-12 & 50-339/87-12.Corrective Actions:Employees Instructed Re Storage Requirements for Category 1 Matls & Welding Procedures Will Be Revised by 870930
ML20238A664
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 08/26/1987
From: Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
87-459, NUDOCS 8708310163
Download: ML20238A664 (5)


Text

_ _

10'CFR 2.201 s

VIHOINIA ELI!CTRIC AND l'OWEH COMPANY l

RicitMOND,VIHOINIA 200 61

~

  • ' L 8" *"

August 26, l87 vice r..msn Nrcs.mAu oF N HATSONE 1

U. S. Nuclear Regulatory Commission Serial No.87-459 Attn: Document Control Desk NAPS /JHL Washington,.D. C. 20555 Docket Nos. 50-338 l

l 50-339 License Nos. NPF-4 NPF-7 Gentlemen:

VIRGIN 1A ELECTRIC AND POWER COMPANY l

NORTH ANNA POWER STATION UNIT NOS. 1 AND 2 NRC INSPECTION REPORT NOS. 50-338/87-12 AND 50-339/87-12 We have reviewed your letter of July 21, 1987 which referred to the inspection-conducted at North Anna between May 4 - 8, 18 - 22, and June 3 - 5, 1987 and reported -in inspection Report Nos. 50-338/87-12 and 50-339/87-12. As agreed

with Mr. R.

Croteau of your staff during a telephone communication on August 21,

1987, this response was delayed to no later than August 27, 1987.

The response to the Notice of. Violation is addressed in the attachment.

j i

We have no objection to this inspection report being made a matter of public record.

If you have any further questions, please contact us.

Very truly yours.

L' l

W. L. Stewart Attachment l

8708310163 870026 PDR ADOCK 05000338 j

G PDR g

h til 1

i l

1

cc:

U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, N. W.

Suite 2900 Atlanta, Georgia 30323 Mr. J. L. Caldwell NRC Senior Resident Inspector North Anna Power Station l

s

' };

+

V ATTACHMENT EESPONSE 'lV THE NOTICE OF VIOLATION REPORTED DURING THE NRC-INSPEi: TION CONDUCTED BETWEEN MAY 4 - 8, 18 - 22, - AND JUNE 3 - 5, 1987.-

~~

INSPECTION REPORT NOS. 50-338/87-12 AND 50-339/87-12

.NRC COMMENT:

~

During the Nuclear Regulatory Commission.(NRC) inspection conducted on May 4 -

8,.18 - 22, and June 3 -

5, 1987, a violation of NRC requirements wag identified.

The violation involved a failure to maintain control of safety related. materials as required by approved site procedures and regulatory

request.

In-accordance -with the " General. Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2 Appendix C (1986), the l violation is listed belew:

10 CFR 50,-

Appendix B,

-Cr'iterion V, as implemented by the Virginia Electric and Power Company QA Topical Report (VEP-1-4A),' requires that the activities.affecting quality shall be prescribed by documented instructions, procedures or drawings of. a type appropriate! to circumstances and shall be accomplished in' accordance with these

. instructions, procedures or drawings.

. Administrative. Procedures ADM-8.0, paragraph requires that.

safety-related ' material stored in a designated " Safety-Related.(SR)

Field Storage Area" if not being worked, fabriacted or installed; also,-

.AUM-9.4 requires that all unused electrodes or bare welding rods,....

-must be returned to the welding foreman.... upon completion of, the ' j ob l

or shift. Strict accountability must be maintained.

-Contrary to the above, on May 20, 1987, control over safety-related materials including welding consummables, was not being maintained in that a substantial amount of unused 308L 3/32 "d,

Heat #C53271 l

stainless steel filler metal wire and three 3/4" d class 1 globe' valves 1

1-SI-189, 1-SI-27 and 1-SI-272 had been left unattended overnight on the ground level inside "C" cubicle, i

{.

This is a Severity Level IV violation (Supplement I) and applies only Unit 1.

l.

l i

I

. l

RESPONSE

1. ' ADMISSION OR DENIAL OF THE ALLEGED VIOLATION:

I The violation is correct as stated.

2.. REASON FOR THE VIOLATION:

I The violation was caused by personnel failing to designate or create a Safety Related Field Storage Area for the implementation of Engineering Work Request (EWR)87-365 which replaced drain valves in the Unit.1 safety injection system.

The replacement of the drain valves in the safety injection system.was originally ~ scheduled to be completed within one day.

Since the piping took longer to drain than expected, the job could not be completed within the scheduled timeframe.

The valves and welding material were kept in the basement of the containment for several days, until the piping was completely.

drained, before welding the valves into the safety injection system.

l 3.

CORRECTIVE STEPS WHICH HAVE BEEN TAKEN AND THE RESULTS ACHIEVED:

l At the time the NRC Inspector identified the discrepancy, on May 20, 1987, the installation of the valves was being completed. There was no need to create a Safety Related Field Storage Area at this time. The condition of the welding materials and valves used during the job, even though they were not stored in a Safety Related Field Storage Area, was satisfactory. The bare welding wire (stainless steel wire) was sealed in a bag to prevent corrosion, and the valve assemblies were capped until they were installed.

In addition, the welding materials and valves were inspected by the craft prior to installation and

)

found acceptable for use (i.e.

the materials were not damaged and were traceable to

. ;hase documentation). After the valves were installed, the welds were inspected visually by QC and a dye penetrant test was performed to verify that the welds were acceptable.

The welding foreman and work crew for the job were instructed on the proper storage requirements for category 1 materials that are required at a jobsite.

Welding crews were instructed, on August 11, 1987, on the proper storage requirements of category 1 materials that are required at a jobsite.

The procedural requirements of ADM-8.0, ADM-9.6, and ADM-13.4 were addressed.

I

a l >.

4.

CORRECTIVE STEPS WHICH WILL BE TAKEN TO AVOID FURTHER VIOLATIONS:

The appropriate welding procedures will be revised to require the creation of a Safety Related Field Storage Area if a job is not completed during one shift or if materials will be left unattended.

5.

THE DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED:

The revision to the appropriate welding procedures will be completed by September 30, 1987.

'i ; '

A.

I t

=

4 b

th '

[y(

v% /:%

N Ng

,t,

9 4

! r

'x

. r-s 4

~

t.

.y,

,, - {

g%

p.

s.i f"*!

t,

,#~

h4 es,

, I./

r

,, 3 ~

.Y

' ~ -.

..:.;y

~~:

<Q f

/

u

,,a

~,

hb,'

j

/

o

- - - - - - - - -. _ _ _ _