Monthly Operating Repts for Mar 1987
ML20237K534
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 03/31/1987
From: Dietz C, Harrison F
CAROLINA POWER & LIGHT CO.
To: Scroggins R
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
References
BSEP-87-0381, BSEP-87-381, NUDOCS 8708190299
Download: ML20237K534 (12)


Text

_

CP&L CO PLANT PERFORMANCE DATA SYSTEM PAGE 2'

RUN DATE 04/07/87 OPERATING DATA REPORT RPD36-COO RUN TIME 14:57:01 DRUNSWICK UNIT 2 DOCKET NO. 050-0324 COMPLETED BY FRANCES HARRIS 0N' OPERATING STATUS TELEPHONE (919)457-9521

____________.q_.________________-

1.

UNIT NAME: BRUNSWICK UNIT 2 i NOTES l

2.

REPORTING PERIOD: JANUARY 87 1

1 3.

LICENFED THERMAL POWER (MWT): 2436 I

i 4.

NAMEPLATE RATING (GROSS MWE): 867.0 l

I 3.

DESIGN ELECTRICAL RATING (NET MWE): 821.0 1

I 6.

MAX DEPENDADLE CAPACITY (GROSS MWE): 815.0 1 1

7.

MAX DEPENDABLE CAPACITY (NET MWE): 790.0 8.

IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THRU 7) SINCE LAST REPORT, GIVE REASONS:

9.

POWER LEVEL TO WHICH RESTRICTED IF ANY (NET MWE):

10. REASONS FOR RESTRICTION IF ANY:

THIS YR TO CUMUL MONTH DATE ATIVE

11. HOURS IN REPORTING PERIOD 744.00 744.00 98592.00
12. NUMBER OF HOURS REACTOR CRITICAL 567.26 567.26 59312.19
13. REACTOR RESERVE SHUTDOWN HRS

.00

.00

.00

14. HOURS GENERATOR ON LINE 493.12 493.12 55533.43
15. UNIT RESERVE SHUTDOWN HOURS

.00

.00

.00

16. GROSS THERMAL ENER0Y GEN. (MWH) 1106781.98 1106781.98 112065430.06
17. GROSS ELEC. ENERGY GEN. (MWH) 359130.00 359130.00 36197456.00
18. NET ELEC. ENERGY GENERATED (MWH) 346787.00 346787.00 34645270.00
19. UNIT SERVICE FACTOR 66.28 66.28 56.33
20. UNIT AVAILABILITY FACTOR 66.28 66.28 56.33
21. UNIT CAP. FACTOR (USING MDC NET) 59.00 59.00 44.48
22. UNIT CAP. FACTOR (USING DER NET) 56.77 56.77 42.80
23. UNIT FORCED OUTAGE RATE 33.72 33.72 15.13
24. SHUTDOWNS SCHED. OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START UP:
26. UNITS IN TEST STATUS (PRIOR TO COMMTiFCIAL OPERATION): FORECAST ACHIEVED INITI AL CRITICA' ITY INITIAL ELECTRICITY COMMERCIAL OPERATION 8708190299 G70331

[][p'.

N4, PDR ADDCK 05000324 R

PDR

\\ \\,.

L PP&L'C0 PLANT PERFORMANCE DATA SYSTEM PAGE 2

l..RUN DATE. 04/07/87 OPERATING DATA REPORT RPD36-000i RUN TIME. 14:58:24 DRUNSWICK UNIT 2 1

DOCKET NO. 050-0324 COMPLETED BY FRANCES HARRISON-OPERATING STATUS TELEPHONE (919)457-9521 1.

UNIT NAME: BRUNSWICK UNIT 2 i NOTES I

2.

REPORTING PERIOD: FEBRUARY 87 I

i 3.

LICENSED THERMAL POWER (MWT): 2436 I

i 4.

NAMEPLATE RATING (GROSS MWE): 867.0 I

i 5.

DESIGN ELECTRICAL RATING (NET MWE): 821.0 1

I 6.

MAX DEPENDABLE CAPACITY (GROSS MWE): 815.0 l I

7.

MAX DEPENDABLE CAPACITY (NET MWE): 790.0 8.

IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THRU 7) SINCE LAST REPORT, GIVE REASONS:

9.

POWER LEVEL TO (4'ICH RESTRICTED IF ANY (NET MWE):

10. REASONS FOR RES1RICTION IF ANY:

THIS YR TO CUMUL MONTH DATE ATIVE

11. HOURS IN REPORTING PERIOD 672.00 1416.00 99264.00
12. NUMBER OF HOURS REACTOR CRITICAL 592.25 1159.51 59904.44
13. REACTOR RESERVE SHUTDOWN HRS

.00

.00

.00

14. HOURS GENERATOR ON LINE 557.70 1050.82 56091.13
15. UNIT RESERVE SHUTDOWN HOURS

.00

.00

.00

16. GROSS THERMAL ENERGY GEN. (HWH) 1306272.84 2413054.82 113371710.90
17. GROSS ELEC. ENERGY GEN. (MWH) 426380.00 785510.00 36623836.00
18. NET ELEC. ENERGY GENERATED (MWH) 413312.00 760099.00 35058582.00
19. UNIT SERVICE FACTOR 82.99 74.21 56.51
20. UNIT AVAILABILITY FACTOR 82.99 74.21 56.51
21. UNIT CAP. FACTOR (USING MDC NET) 77.85 67.95 44.71
22. UNIT CAP. FACTOR (USING DER NET) 74.91 65.38 43.02
23. UNIT FORCED OUTAGE RATE 2.41 20.12 15.02
24. SHUTDOWNS SCHED. OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START UP:
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): FORECAST ACHIEVED INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION 1.16 - 9

DOCKET NO.:

050-0325 UNIT:

Brunswick 1 DATE: April 1987 COMPLETED BY: Frances Harrison OPERATIONS

SUMMARY

BRUNSWICK UNIT 1 The unit was removed from service on February 14, 1987, for refueling /mainte-nonce outage.

There are*1400 BWR and 160 PWR spent fuel bundles in the Brunswick Unit 1 fuel pool.

  • 560 bundles in the core during refueling.

l

nin i DiR t

c 0 u ra 9 c

L 5 r or1 f

i c

g r o r 0 BAF 9 e

e e

u v

o n

a t

nf(

s tc e

t O EEYE e or u

Inoi ts r

MTBN run c r

s t

e AA D O t

u O

N ar e Gah E H Co e e,

T N D pSR iR c

ib r y n

t e

E K T T P

&t E

c C N L L eA t

a i Pr n1 E

n n

h tn I

s e

e x

r O U P E u

v t

o T

a e

n EfEE0 D

M C

P r

i O

a C

M 4

/gn i

l

~

eu fe R

SN O

X X

I 0-m E%?.

T n

e

_ aS l

C D

hu r

U u

ci F

St 7

E 8

l l a a R

9 I

duu 1

onnt R

t,Y0 h a a u h

teMMA E

c C

W r

juN R

M1 23 a

O M

r P

D H

3 N

T A

N O

S r

e N

M et tr s

n W

T n e o e v p O

R c

A iE e

/

D O

L R

N T

P I

E IH R

S IT

.E 55 =!6 N

5'Ed

)

1 in U

7, a

di 27 lp x

E (t

h2N e e s

C rluT i fa o s

F s

e e

c E9@

r tnn g

ea

!-i[

o mn n

r el i p

. pt el a ninu u o uif s qa e aEMR e - -

,r O S

RABCD 4

te 1

a 2

D 0

d 7

e 8

l d u ed c e r h o

c 5

F S 0

0 W

F5 6

8 I

7,_____-

PLANT PERFORMANCE DATA SYSTEM PAGE~

1 CP&L CO

' APPENDIX B - AVERAGE DAILY POWER LEVEL ~

RPD39-000 R U N - D'A T E. ' 04/07/87 q

RUN TIME 14:58:27 BRUNSWICK UNIT 11 9

. DOCKET NO. 050-0325 COMPLETED BY FRANCES HARRISON TELEPHONE (919)457-9521

' MARCH 1987 1

DAYE AVG. DAILY POWER LEVEL DAY AVG. DAILY POWER LEVEL (MWE-NET)

(MWE-NET)-

l 1

-5 17

-4 i

2

-5 18

-5 3

-5 19

-4 4

-5 20

-5 5

-5 21

-4 6

-5 22

-4 7

~4 23

-4 8

-- 5 24

-4 9

-4 25

-4

-10

-4 26

-4 11-

-4 27

-4 12

-5 28

-4 13

-5 29 14

-5 30

-4

.15

-4 31

-4 16

-4 l.

1.16 - 8

CP&L CO PLANT PERFORMANCE DATA SYSTEM PAGE 1

RUN DATE 04/07/87 OPERATING DATA REPORT

~RPD36-0C0

' RUN TIME 15:16:17 BRUNSWICK UNIT 1 DOCKET NO. 050-0325 COMPLETED BY FRANCES HARRISON OPERATING STATUS TELEPHONE (919)457-9521 1.

UNIT NAME: BRUNSWICK UNIT 1 i NOTES 1.

2 REPORTING PERIOD: MARCH 87 I

l-3.

LICENSED THERMAL POWER (MWT): 2436 I

I 4.

NAMEPLATE RATING (GROSS MWE): 867.0 l

I 5.

DESIGN ELECTRICAL RATING (NET MWE): 821.0 l

I 6.

MAX DEPENDABLE CAPACITY (GROSS MWE): 815.0 l l

7.

MAX DEPENDABLE CAPACITY (NET MWE): 790.0 8.

IF CHANGES DCCUR IN CAPACITY RATINGS (ITEMS 3 THRU 7) SINCE LAST REPORT, GIVE REASONS:

9.

POWER LEVEL TO WHICH RESTRICTED IF ANY (NET MWE):

10. REASONS FOR RESTRICTION IF ANY:

THIS YR TO CUMUL MONTH DATE ATIVE

11. HOURS IN REPORTING PERIOD 744.00 2160.00 86833.00
12. NUMBER OF HOURS REACTOR CRITICAL

.00 1063.50 56218.72

13. REACTOR RESERVE SHUTDOWN HRS

.00

.00 1647.10

14. HOURS GENERATOR ON LINE

.00 1058.95 53274.27

15. UNIT RESERVE SHUTDOWN HOURS

.00

.00

.00

16. GROSS THERMAL ENERGY GEN. (HWH)

.00 2092181.01 111134205.90

17. GROSS ELEC. ENERGY GEN. (MWH)

.00 668550.00 36586402.00

18. NET ELEC. ENERGY GENERATED (MWH)

-3306.00 640581.00 35154587.00

19. UNIT SERVICE FACTOR

.00 49.03 61.35

20. UNIT AVAILABILITY FACTOR

.00 49.03 61.35

21. UNIT CAP. FACTOR (USING MDC NET)

.56 37.54 51.25 3

22. UNIT CAP. FACTOR (USING DER NET)

.54 36.12 49.31

23. UNIT FORCED OUTAGE RATE

.00

.00 18.02

24. SHUTDOWNS SCHED. OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START UP: 06/20/07 26 UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): FORECAST ACHIEVED

\\

INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION 1.16 - 9

r-j l

DOCKET NO.:

050-0324 UNIT:

Brunswick 2 DATE: April 1987 COMPLETED BY: Frances Harrison OPERATIONS

SUMMARY

BRUNSWICK UNIT 2 Brunswick Unit 2 operated at a 87.16 percent capacity factor and a 91.51 percent availability factor. There was one off-line outage and one power reduction.

Details are in the Unit Shutdowns and Power Reductions sheet.

There are 756 BWR and 144 PWR spent fuel bundles in the Brunswick Unit 2 fuel pool.

i

CP&L CO PLANT PERFORMANCE DATA SYSTEM PAGE 2;

l RUN DATE 04/07/87 APPENDIX B - AVERAGE DAILY POWER LEVEL RPD39-000' l

' RUN TIME 15:16:15 BRUNSWICK UNIT 2 DOCKET NO. 050-0324 COMPLETED BY FRANCES HARRISON TELEPHONE (919)457-9521 MARCH 1907 DAY AVG. DAILY POWER LEVEL DAY AVG. DAILY POWER LEVEL (MWE-NET)

(MWE-NET) 1 781 17 780 2

775 10 780 3

775 19 778 4

774 20 776 5

775 21 761 6

776 22 775 7

773 23 774 8

777 24 773 9

776 25 773 10 775 26 773 11 91 27 764 12

-12 28 570 13 37 29 721 14 601 30 768 l

15 754 31 767 16 777 1.16 - 0

.s

(

\\

CP&L CO PLANT PERFORMANCE DATA SYSTEM PAGE 2i

,RUN DATE 04/07/87' OPERATING DATA REPORT RPD36-000, RUN TIME' 15:16:17 BRUNSWICK UNIT 2 DOCKET NO. 050-0324 L

COMPLETED BY FRANCES HARRIS 1

i OPERATING STATUS TELEPHONE (919)457-9521 q

1.

UNIT NAME: BRUNSWICK UNIT 2 I NOTES I i 2.

REPORTING PERIOD: MARCH 87 I

I 3.

LICENSED THERMAL POWER (MWT): 2436 I

I J 4.

NAMEPLATE RATING (GROSS MWE): 867.0 l

I l 5.

DESIGN ELECTRICAL RATING (NET MWE): 821.0 1

1 6.

MAX DEPENDADLE CAPACITY (GROSS MWE): 815.0 l I

7.

MAX DEPENDABLE CAPACITY (NET MWE): 790.0 8.

IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THRU 7) SINCE LAST REPORT, GIVE REASONS:

9.

POWER LEVEL TO WHICH RESTRICTED IF ANY (NET MWE):

10. REASONS FOR RESTRICTION IF ANY:

THIS YR TO CUMUL MONTH DATE ATIVE

11. HOURS IN REPORTING PERTOD 744.00 2160.00 101159.00
12. NUMBER OF HOURS REACTOR CRITICAL 692.98 1852.49 60597.42
13. REACTOR RESERVE SHUTDOWN HRS

.00

.00

.00

14. HOURS GENERATOR ON LINE 680.80 1731.62 56771.93
15. UNIT RESERVE SHUTDOWN HOURS

.00

.00

.00

16. GROSS THERMAL ENERGY GEN. (MWH) 1616751.76 4029806.58 114988462.66
17. GROSS ELEC. ENERGY GEN. (MWH) 527095.00 1312605.00 37150931.00
18. NET ELEC. ENERGY GENERATED (MWH) 512321.00 1272420.00 35555237.00
19. UNIT SERVICE FACTOR 91.51 80.17 56.12
20. UNIT AVAILABILITY FACTOR 91.51 80.17 56.12 1
21. UNIT CAP. FACTOR (USING MDC NET) 87.16 74.57 44.49
22. UNIT CAP. FACTOR (USING DER NET) 83.87 71.75 42.81
23. UNIT FORCED OUTAGE RATE 8.49 15.92 14.94
24. SHUTDOWNS SCHED. OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START UP:
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): FORECAST ACHIEVED INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION 1.16 - 9 I

0 s l c) me iDiR c

- ni n9 et tc L

0 u r a1 vl uf 4

5 r p r9 e

e oi or v

c rf r

0 B A F(

i n

p s nf(o tc e

m s no t

'. EEYE e or i i I i t

O r

s MTBN t

u r

- ta e r

N r

r e A A D O un c d b Gah E H Co e o e T

pSR-N D iR rd ib r y E

t K T T P e

&t rd i Pr E

c t

E C N L L eA n o n h

tn I

s e

f a x

r O U P E u

v o

D M

C r

r g EfEE0 T

a e

e n P

O wi C

ot 4

p se d t ec e u v d l e a R v SN O

I T

L u

m U

E$

ou aS C

rci D

St 7

E 8

l l a a R

9 duu 1

onnt R

ha a u 5'MUi M1 23 h

t eMMA t

E c

v W

ra O

M P

D H

3 N

T A

N O

C e

S N

M

" tn t

5 r

W T

" e o

' v p A

O R

'iE e

/

D O

l R

N T

P U

E H

R S

T

.._2 3eg5 c NI

-. gm

)

5 5

in U

rhE3 la p

x E

(t

.{0x e e s

B rluT r

iao F

ec 1:

tnn ea

=53c 0

mn el 0

pt el a ninu o uif g s qa e aEMR 1c e - -

5 RABCD 7

c 2

i, 3

)

0 7

d 8

le d u ed rc e h

1 o

c 6

F S 3

0 FS 7

8 t

oa e 3 s l c) yp iDiR c

- nin9 r u tcfL 0 u ra 1 a r 5 r pr9 e

e t r u

v c

n e r or 0 B AF (

i n

et ts n f

O.EEYE tc e

mn no MT8N r torr oi I i ts e

ta e mn r

u N

A u

r e A

D 0 on c o

Gah T N D e

Co t e f

Ef iR t

p S E

h ie K IT T P

&t E

ct et b r yt E

eA n u

i Pr n L

h t

C N L

s e

d f r

O U P E u

v o

x o T

a e

m EfEE0 D :

M C

P r o r

a n O

ci C

st 4

p r u.

o r y t rl c e p a t p e n u R i s SN O

IT

.?0 m

C a

r o@u c

U D

S E

8

l l 7

a R

9 d uu 1

onnt R

h a au

?G h

h teMM E

c 3#

W r

O M

t M1 2 a

P l

3 D

i N

T A

N O

S e

r N

M e

tn t

4 s

r W

T n

e o 0

e v p 0

O R

ic E e D

O L

R 7

T P

8 U

E

-2 R

i lS T

=

5 :!6 N

I

)

U E j, 3

ia n

j 3e lp x

r E

o tt O E uT s

,r h{$

H e e p r r

l f i o a

F e

?E@

2 tnn 0

i e s ij mn 3

[

6

pt e ninu o uif s qa e aEM e - -

F RABC t

1 ia 1

3 D

0 d

7 e

8 lu d

ed c e 1

r h

o c

F S 0

3 0

FS 7

8 l

i

U W

i Cp&L Carolina Power & Light Company Brunswic'c Steam Electric Plant

'P. O. Box 10429 Southport, NC 28461-0429 April 7, 1987

' FILE: B09-135100-SERIAL:

BSEP/87-0381 Mr. R.'M.

Scroggins, Director Office of Resource Management U.S. Nuclear Regulatory Commission Washington, DC 20555 BRUNSWICK STEAM ELECTRIC PLANT UNITS 1 AND 2-DOCKET NOS. 50-325 AND 50-324 LICENSE NOS. DPR -71 AND DPR MONTHLY OPERATING REPORT

Dear Mr. Scroggins:

In accordance with Technical Specification 6.9.1.6 for the Brunswick Steam Electric Plant, Units 1 and 2, Carolina Power & Light Company herewith submits the report of operating statistics and shutdown experience for the month of March 1987.

A correction was made to the number of reactor critical hours credited to Unit 2 in January. This change is seen as an additional 51.14 hours1.62037e-4 days <br />0.00389 hours <br />2.314815e-5 weeks <br />5.327e-6 months <br /> in line No. 12--year to date and cumulative.

Very truly yours, 0.&

C..R. Dietz, General Manager Brunswick Steam Electric Plant FH/cb MSC/85-0014 Enclosures cc: