i NARRATIVE
SUMMARY
OF MONTHLY OPERATING EXPERIENCE MARCH, 1987 l
March 1 The Station was in ' Operational Mode 1 with ' reactor through power at a nominal 100 percent and the Reacto r March 17-Coolant-System at a normal. ope rati ng pressure and tempe ra tu re.
March'.18 At 1220 hours0.0141 days <br />0.339 hours <br />0.00202 weeks <br />4.6421e-4 months <br />, following control rod. insertion during an incore/excore calibration test, rod position i ndicato rs -
for control rods H-2 and P-8. indicated a possible misalignment of greater than 12 steps.. At 1515' hours, following the completion of the calibration test and rod I
withdrawal, the rod position' indicators for all control rods were verified to be within 12 steps of their group demand counters.
Power level remained at a nominal 100 percent throughout the day.
March 19 The Station was in Operational Mode 1 with reactor power-through at a nominal 100 percent and the Reactor Coolant System 1
March 31 at a normal operating pressure and temperature.
i 4
B708190249 070331 DR ADOCK O 34 1
y.-
' OPERATING DATA REPORT DOCKET NO.:
50-334 REPORT DATE:
04/06/87 COMPLETED BY: P.A. SMITH TELEPHONE:
(412) 643-1825 OPERATING STATUS
- 1. UNIT NAME: BEAVER VALLEY POWER STATION, UNIT 1 Notes
- 2. REPORTING PERIOD: MARCH 1987
- 3. LICENSED THERMAL POWER (MWt):
2660
- 4. NAMEPLATE RATING (Gross MWe):
923
- 5. DESIGN ELECTRICAL RATING (Net MWe):
835
- 6. MAX. DEPENDABLE CAPACITY (Gross MWe):
860
- 7. MAX. DEPENDABLE CAPACITY-(Net MWe):
810
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS SINCE LAST REPORT, GIVE REASONS:
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (Net MWe):
None
- 10. REASONS FOR RESTRICTIONS, IF ANY:
N/A THIS MONTH YEAR TO DATE CUMULATIVE
- 11. HOURS IN REPORTING PERIOD:
744,0 2160.0 95688.0
- 12. NO. OF HRS. REACTOR WAS CRITICAL:
744.0 2126.4 53971,2
- 13. REACTOR RESERVE SHUTDOWN HOURS:
0.0 0.0 4482.8
- 14. HOURS GENERATOR WAS ON LINE:
744.0 2117.4 52448.7
- 15. UNIT RESERVE SHUTDOWN HOURS:
0.0
-0.0 0.0 t
- 16. GROSS THERMAL ENERGY GEN. (MWH):
1952434.0 5540110.0 124064516.5 I
- 17. CROSS ELECT. ENERGY GEN. (MWH);
642740.0 1826430.0 39699660.0
~l
- 18. NET ELECTRICAL ENERGY GEN. (MWH):
606430.0 1722160.0 37026963.0
- 19. UNIT SERVICE FACTOR: (PERCENT) 100.0 98.0 57.2
- 20. UNIT AVAILABILITY FACTOR:(PERCENT) 100.0 98.0 57.2
100.6 98.4 51.2 l
- 22. UNIT CAPACITY FACTOR (DER): PCT 97.6 95.5 49.7
- 23. UNIT FORCED OUTAGE RATE: (PERCENT) 0.0 2.0 21.1
- 24. SHUTDOWNS SCHEDULED OVER NEXT SIX MONTHS (TYPE,DATE,AND DURATION OF EACH):
Control Room Wall Removal Outao.e. April 24.1987. Scheduled 23 Days j
i
- 25. IF SKUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
N/A 26 UNITC IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):
FORECAST ACHIEVED INITIAL CRITICALITY N/A N/A INITIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A j
l
s
,. ~ ^
AVERACE DAILi UNIT ?OWER LEVEL DOCKET NO.
30-33' UNIT 375 Di: d I-DATE April 7, 1987 COMPLETED BY P. A. Smith 1TLEPHONE (412) 543-1825 MONTH MARCH DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVE.L iMWe-Neti IMWe Net) 817 g7 821 2
817 13 817 817.
3 g9 813 4
821 20 813 3
821 817 gg 6
820 22 817 7
806 33 808 3
821 24 804,,
9 814 3
817 10 820 3
813 g
'821 804 g
g3 817 804
,y 13 825 804
,9 14 821 30 813 33 817 33 817 16 817 INSTRUCTIONS On this format.!ist the average daily unit power lese!in MWe Net far each day in the reportine month. Cuennute to Ihe nearest whole megawatt.
t(II77) i
'k,
TAl5 Telephone (412) 393 6000 Nuclear Group P.O. Box 4 Shippingport, PA 15077-0004 April 7,1987 F
L Beaver Valley Power Station, Unit No.1 Docket No. 50-334 License No. DPR-66 Monthly Operating Report U. S. Nuclear Regulatory Commission Director, Of fice of Management Information & Program Cantrol Washington, D. C. 20555 Gentlemen :
In accorda nce with Appendix A,
Technical Speci fications, the Monthly Operating Report is submitted for the month of March,1987.
Very truly yours, J'
0 8
e 4-
- d. D. Sieber t
Vice President Nuclear Operations Imd Enclosures cc: NRC Regional Office King of Prussia, PA y
I 1
l l
'^
2_
I
^
DUQUESNE LIGHT COMPANY Beaver Valley Power Station Nuclear Group i
DISTRIBUTION LIST MONTHLY OPERATING REPORT J. J. Carey J. O. Crockett J. D. Si e be r N. R. Tonet R. E. Ma rtin C. E. Ewing H. R. Caldwell W. S. Lacey J. W. McIntire K. D. Grada T. P. Noonan R. F. Balcerek L. A. Gattuso J. M. Sasala (2)
M. F. McGuire (PS&B)
T. G. Zyra V. Turriziani (2)
P. A. Smith W. Troskoski - NRC M. Ccppula, SAPS Planning & Scheduling Coordinator (BV,A)
Electricity' De France T. E. Murley, U.S. N.R.C.
C. A. Roteck, Ohio Edison J. D. Wilson, Ohio Edison INP0 Records Center A. D. Rossin, Nuc. Saf. Analy. Center Richard Janati, PA. Dept. of Environmental Resources F. R. Allison, 29-6 0xford Centre S. J. McNutrie, 29-4 0xford Centre G. R. Brandenberger, 27-3 0xford Centre Central File (2)
_ _