Proposed Tech Specs Reflecting Revised Total Predicted Structural Settlement for G Tunnel Settlement Marker 34 & E Tunnel Settlement Marker 28
ML20237J343
Person / Time
Site: River Bend Entergy icon.png
Issue date: 08/05/1987
From:
GULF STATES UTILITIES CO.
To:
Shared Package
ML20237J333 List:
References
NUDOCS 8708180106
Download: ML20237J343 (2)


Text

cm 9l*

v TABLE 3.7.10-1 TOTAL PREDICTED SETTLEMENTS OF MAJOR STRUCTURES' i

SETTLEMENT PREDICTED i

STRUCTURE MARKER NO.

SETTLEMENT (IN.)

Reactor Building 15 4.0 16 4.0 17 4.0 Auxiliary Building 18 3.8 19 3.6 20

3. 9 21 3.7 Fuel Building 11 3.7 12 4.0 13 3.5 14 3.8 Control Building 5
3. 7 6

3.3 7

3.7 8

3.7 Diesel Generator Building 1

3.4 i

2 3.7 3

3.6 4

3.8 Standby Cooling Tow *er, Basin 30 2.7 and Pump House 31 3.2 32 2.4 BF Tunnel 9

2.1 10 2.5 Main Steam Tunnel 22 3.8 23

3. 8 E Tunnel 28

-Gre-3. 3 l

29 2.8 J

G Tunnel 33 2.6 34 6 1.3 l

8708100206 870005 DR p

ADOCK 05000458 PDR RIVER BEND - UNIT 1 3/4 7-36 j

4

~~

TABLE 3.7.10-1

)

TOTAL PREDICTED SETTLEMENTS OF MAJOR STRUCTURES SETTLEMENT PREDICTED STRUCTURE MARKER NO.

SETTLEMENT (IN.)

Reactor Building 15 4.0 16 4.0 m

17 4.0 Auxiliary Building 18 3.8 19 3.6 20

3. 9 21 3.7 Fuel Building 11 3.7 12 4.0 13 3.5 14 3.8 Control Building 5

.3.7 6

3.3 7

3.7 8

3.7 i

Diesel Generator Building 1

3.4 2

3.7 3

3.6 4

3.8 Standby Cooling Tow'er, Basin 30

,t. 7 and Pump House 31 2.2 32 2.4 BF Tunnel 9

2.1 10 2.5 Main Steam Tunnel 22 3.8 23

3. 8 E Tunnel 28

-&4-3. 3 l

29

2. 8 G Tunnel 33 2.6 34

.e,.4 1.3 RIVER BEND - UNIT 1 3/4 7-36