Requests Deferral of NRC Equipment Qualification Insp Until After Late Sept 1987,when Unit 1 Recovery from Steam Generator Steam Tube Rupture Will Have Been Completed
ML20237H750
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 08/05/1987
From: Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
87-469, NUDOCS 8708170340
Download: ML20237H750 (2)


Text

_ _

\\

+

VIHOINIA EI.ECTHIC AND POWEH COMPANY HIcnwonn,VIROINIA 20261 August 5, 1987

\\0 05 Y, Is. bTE WA NT VICS I'RENIDENT w

Nocteau oramations Regional Administrator Serial No.87-469 N0/RCB:jmj Region II Docket Nos.

50-338 U.S. Nuclear Regulatory Commission

.101 Marietta Street 50-339 Suite 2900 License Nos.

NPF-4 Atlanta, CA 30323 NPF-7 Centlemen:

. VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNITS 1 ANTO EQUIPMENT QUALIFICATION INSPECTION

.Your letter. dated July 24, 1987 provided confirmation of the dates of August 31 - September 4,

1987, for the NRC equipment qualification (EQ) inspection for North Anna Units 1 and 2.

These dates had been established in a telephone conversation between members of our staffs on July 21, 1987. At that time,' we were in the initial phases of the recovery from the Unit 1 steam generator tube rupture and believed that Unit I could be returned to service before commencement' of the inspection. We now project that the recovery will extend until late September, 1987.

Since Unit 2 is scheduled ~to begin a refueling outage in mid-August, 1987, both units will be in outages during the period scheduled for the inspection. The two simultaneous outages will fully utilize the resources available at the station as well as those of our corporate staff.'

It is requested, therefore, that the NRC EQ inspection be deferred until some time after the Unit I recovery has been completed. For planning purposes, we are currently projecting that Unit I will return to service on September 25, 1987, and Unit 2 in early to mid October, 1987. The next refueling outages are tentatively scheduled for late 1988 for Unit 2 and for early 1989 for Unit 1.

If you require additional information, please contact me.

Very truly yours,

&N W. L. Stewart 8708170340 870005 PDR ADOCK 05000338 0