.c Docket No.: 50-245 Mr. Edward J. Mroczka, Senior Vice President Nuclear Engineering and Operations Northeast Nuclear Energy Company Post Office Box 270 Hartford, Connecticut 06141 0270
Dear Mr. Mroczka:
SUBJECT:
4 Re: Millstone Nuclear Power Station, Unit No. 1 The Conmission has issued the enclosed Amendment No. 6 to Facility
- j Operating License No. DPR-21 for the Millstone Nuclear Power Station, l
Unit No. 1.
This amendment is in response to your application dated i
May 21, 1987, as supported by submittals dated June 30 and July 14, 1987.
{
This amendment will revise the current minimum critical power ratio (MCPR),
linear heat generation rate (MAPLHGR) to reflect Cycle 12 operation. The core reload consists of 196 General Electric Type GE8x8EB (GE.8B) fuel assemblies.
A copy of our related Safety Evaluation is enclosed. A Notice of Issuance will be included in the Commission's next regular biweekly Federal Register notice. This completes the action on TAC No. 65534.
i Sincerely,
/s/
Cecil 0. Thomas, Director Integrated Safety Assessment Project Directorate Division of Reactor Projects III, IV, V and Special Projects
Enclosures:
DISTRIBUTION 1.
Amendment No. 6 to Docket File-ISAPD RF Dilagan License No. DPR-21 NRC & Local.PDR JPartlow TBarnhart(4) 2.
Safety Evaluation DCrutchfield Wanda Jones EButcher FSchroeder GPA/PA ACRS (10) cc w/ enclosures:
CThomas WHodges ARM /LFMB See next page M3oyle D
C #65534 8708240160 870 Bog OGC-Bethesda PDR ADOCK 05000245 Edordan L
p PDR OFC: LA:ISAPD
- PM:ISAPD : OG
- D:ISAPD p.......................................
$$![$!I"!!.S'.#S."I....[.$!![.$.......
[< [
h
- 08 [ 87 DATE:08/f/87
- 08/k/87 0FFICIAL RECORD COPY D
]
i i
j p >R 880 t
0 9'o,.
UNITED STATES j
y
^,
8 NUCLEAR REGULATORY COMMISSION n
(
WASHINGTON, D. C. 20555 August 6, 1987 Docket No.:
50-245 1
Mr. Edward J. Mroczka, Senior Vice President I
1 l
Nuclear Engineering and Operations l
Northeast Nuclear Energy Company Post Office Box 270 Hartford. Connecticut 06141-0270
Dear Mr. Mroczka:
SUBJECT:
Re: Millstone Nuclear Power Station, Unit No. 1 i
The Commission has issued the enclosed Amendment No. 6 to Facility Operating License No. DPR-21 for the Millstone Nuclear Power Station, Unit No. 1.
This amendment is in response to your application dated l
May 21, 1987, as supported by submittals dated June 30 and July 14, 1987.
This amendment will revise the current minimum critical power ratio (MCPR),
linear heat generation rate (MAPLHGR) to reflect Cycle 12 operation. The core relcad consists of 196 General Electric Type GE8x8EB (GE-88) fuel assemblies.
l A copy of our related Safety Evaluation is enclosed. A Notice of Issuance will be included in the Commission's next regular biweekly Federal Register notice. This completes the action on TAC No. 65534.
1 Sincerely,
&A0 W^&V i
Cecil 0. Thomas, Director Integrated Safety Assessment Project Directorate Division of Reactor Projects - III, IV, V i
and Special Projects 1
Enclosures:
1.
Amendment No. 6 to License No. DPR-21 2.
Safety Evaluation cc w/ enclosures:
See next page
I i
5 Mr. Edward J. Mroczka Millstone Nuclear Power Station Northeast Nuclear Energy Company
'Jnit No I cc:
Gerald Garfie.ld, Esquire Kevin McCarthy, Director Day, Berry & Howard Radiation Control Unit Counselors at Law Department of Environmental City Place Protection Hartford, Connecticut 06103-3499 State Office Building Hartford, Connecticut 06106 Waynr D. Romberg Vice President, Nuclear Operations Richard M. Kacich, Manager Northeast Utilities Service Company Generation Facilities Licensing Post Office Box 270 Northeast Utilities Service Company Hartford, Connecticut 06141-0270 Post Office Box 270 Hartford, Connecticut 06141-0270 Bradford S. Chase, Under Secretary l
Energy Division
)
Office of Policy and Management J. Stetz, Plant Superintendent 4
80 Washington Street Millstone, Unit 1 Hartford, Connecticut 06160 Northeast Nuclear Energy Company Wa er r Connecticut 06385
)
Regional Administrator, Region I i
U.S. Nuclear Regulatory Commission l
631 Park Avenue I
King of Prussia, Pennsylvania 19406 Northeast Nuclear Energy Company ATTN:
Superintendent Millstone Nuclear Power Station P. O. Box 128 Waterford, Connecticut 06385 Resident Inspector c/o l' '
NRC Millst,,1e Nuclear Power Station P. O. Box 811 Niantic, Connecticut 06357 First Selectman of the Town of Waterford Hall of Records 200 Boston Post Road Waterford, Co.nnecticut 06385 t
L--------
- - - - - -. - - _ -