Summarizes Util Commitments Made During 871217 Telcon W/Nrc Re IGSCC Insp Rept.Augmented Leakage Monitoring Program Will Continue Per Generic Ltr 84-11 Requirements.List of Telcon Participants Also Encl
ML20237E241
Person / Time
Site: Quad Cities 
Issue date: 12/17/1987
From: Johnson I
COMMONWEALTH EDISON CO.
To: Murley T
Office of Nuclear Reactor Regulation
References
3999K, GL-84-11, NUDOCS 8712280229
Download: ML20237E241 (3)


Text

_.

M*

4s

[~'N

/

^

) Commonwealth Edison One Fir;t N:.tional Plaza, Chicago, Illinois k

E~?

Address Re#y to: Post OMce Box 767

\\

Chicago, Illinois 60690 0767 December 17, 1987 Mr. Thomas E. Murley, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555

Subject:

Quad Cities Station Unit 1

" Fall 1987 Intergranular Stress Corrosion Cracking Inspection (IGSCC) - Generic Letter 84-11" NRC Docket No. 50-254

Reference:

Letter from I.M. Johnson to T.E. Murley dated December 10, 1987

Dear Mr. Murley:

In the above referenced letter, Commonwealth Edison provided its final report detailing the results of the Quad Cities Unit 1 Pall 1987 IGSCC susceptible piping inspection. A conference call was held on December 17, 1987 with members of your staff regarding the subject report. A list of conference call participants can be found as Attachment A to this letter.

In the course of our conference call, commonwealth Edison indicated and/or reiterated its commitment to the following actions:

(1) Commonwealth Edison agrees to build up the leak barrier weld overlays associated with welds 02BS-S9 and 02BS-SS to full structural overlays in a subsequent refueling outage.

(2) Quad Cities Station agrees to continue its augmented leakage monitoring program pursuant to the requirements of Generic Letter 84-11.

The Station has procedures which administrative 1y require that pump flow monitoring and recording be performed once per four hours.

Oh

(

1 1 8712280229 871217

~

PDR ADOCK 05000254 0

DCD

'c-t, T.E. Murley December 17, 1987 (3) Commonwealth Edison agrees to include weld 10BD-S13 in our next Quad cities Unit 1 Inspection Plan (currently scheduled for 6/89).

Please direct any questions you may have regarding this matter to this office.

Very truly yours,

.!?

I. M. Johns Nuclear Licensing Administrator 1m Attachment cc: Quad Cities Resident Inspector A.B. Davis - NRC RIII Admin.

3999K

w-

'.) = ' Q E'

ATTACHMD*T A CONFERENCE CALL w/NRR ON UNIT 1 FALL '87 IGSCC INSPECTION 12/17/87 1:30 CST.

NAME ORG.

I. Johnson CECO /

Nuclear Licensing.

H. Do CECO /

Prod.: Serv.:Eng. Dept.

R. Tamminga CECO /

Prod.' Serv. Eng. Dept.

T. Tamlyn Ceco /

Quad cities Station J. Tagatz Ceco /

Quad Cities Station' K. Medulan Ceco /

Quad Cities' Station l

D. Thayer CECO /

-Quad Cities Station J. Brown NUTECH C. Froehlich NUTECH N. Cofie NUTECH T. Gianuzzi Structural Integrity D. Pitcairn Structural Integrity T. Ross NRR/BD III-2 B. Koo NRR l

399K