.IN} RESPONSE, PLEASE.-
gb.
- ** ** ~-
REFER - TO's ? M871125A~
m UNITED STATES.
?!
p g
NUCLEAR REGULATORY COMMISSION.-
dd.d',[
p%
. [
- E; W ASHINGTON, D.C. 20556
/};
DecemberL 4, 1987J
. *sses.
l OFFICE OF THE
. SECRETARY.
i MEMORANDUM.'FOR:. Victor Stello,1Jr.
Executive Director for:O-rations P y: j;-
a Samuel J.'Chilk, Secre a'
}
FROM(
SUBJECT:
STAFF REQUIREMENTS.- D SCfSSION/POSSIBLE' VOTE' ON FULL POWER OPERATINo LICENSE FOR PALO VERDE-3,'10:00 A.M.," WEDNESDAY, NOVEMBER.25, 1987, COMMISSIONERS' CONFERENCE ROOM, D.C.
OFFICE - (OPEN : TO PUBLIC ATTENDANCE)'
The-Commitsio saa briefed by the Arizona Public Service
' Company (licensee)'and the staff on:the readiness of the licensee to receive a full' power! operating license for the Palo-Verde' Unit 3 nuclear power' station.
Presentations were'made by the.following licensee representatives:
O.M.-DeMichele' President and' Chief Operating Officer
- E.E. VanBrunt Executive Vice President J. Haynes-Vice President Nuclear Production R.M.. Butler, Director Standards & Technical Support-The Commission, with all Commissioners agreeing, authorized the staff, upon completion of the remaining prerequisites, to issue a full power operating license to Arizona Public Service Company for its Palo Verde Unit 3 nuclear power station.
The Commission cautioned the licensee to be particularly mindfulvat the corporate level of the unique challenges of operating three large nuclear power stations and to minimize the burden to the control room operators in performance of their. duties (e.g., reduce the number of annunciators out of service, quiet Unit l's ventilation system, and improve the management of maintenance backlog items).
y hDR R
PDR PT9.7
~~-=::_-_---_-__
j
Ja The Commission requested the staff to monitor control room and U
corporate management activities outlined above and to consider increasing the number of resident inspectors for the three Palo.
Verde units.