Forwards SE Authorizing Relief Request NDE-R020 Re Third 10-yr ISI Interval of Plant,Per 10CFR5.55a(a)(3)(i)
ML20236V997
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 07/29/1998
From: Bellamy R
NRC (Affiliation Not Assigned)
To: Leslie Liu
IES UTILITIES INC., (FORMERLY IOWA ELECTRIC LIGHT
Shared Package
ML20236V999 List:
References
TAC-MA1576, NUDOCS 9808050017
Download: ML20236V997 (4)


Text

. .

July 29, 1998 Mr. LC3 Liu Chiirman of th] Botrd cnd Chief Executive Officer {

IES Utilities Inc. '

200 First Street, SE P.O. Box 351 Cedar Rapids, IA 52406-0351

SUBJECT:

EVALUATION OF RELIEF REQUEST NDE-R020 - DUANE ARNOLD ENERGY CENTER (TAC NO. MA1576)

Dear Mr. Liu:

By letter dated April 26,1996, IES Utilities Inc. (lES) submitted its inservice inspection (ISI) plan for the third 10-year inservice inspection interval of the Duane Arnold Energy Center (DAEC). By letter dated March 23,1998, the NRC provided its evaluation of the DAEC ISI plan and its associated relief requests. In its evaluation, the NRC staff stated that the review of relief request NDE -R020 would be evaluated in a separate report.

Based on discussions with the staff, IES submitted a revision to relief request NDE-R020 on May 15,1998. The staff has reviewed and evalaated relief request NDE-R020 as documented in the enclosed safecy evaluation. The staff has determined that the proposed alternative to use the DAEC Technical Specification requirements for visual examination and functional testing for snubbers provides an acceptable level of quality and cafety. Accordingly, the alternative is authorized pursuant to 10 CFR 50.55a(a)(3)(i).

I Sincerely, 1 Original signed by: l 1

Ronald R. Bellamy, Acting Director Project Directorate 111-3 '

Division of Reactor Projects Ill/IV Office of Nuclear Reactor Regulation  !

Docket No. 50-331

Enclosure:

Safety Evaluation cc w/ encl: See next page DISTRIBUTION:

Docket File m

ACRS u , . .: t: :ii' k RLaufer jJ OGC I EAdensam (EGA1)

PUBLIC GGrant, Rlli PD3-3 R/F Me ' D /

GTracy GHill (2)

THarris (SE only) g)

DOCUMENT NAME: G:\DUANEARN\MA1576.RR

  • No te9]hd eppghs to sE OFF.cE PD3-3 LA lE PD3-3 PM lE EMEB- l OGCI I/v F PD3-3 (A)PD l NAME EBarnhtli fb RLaufer F KManoty* i f /Mitu1 RBellami '"

DATE 'iQYA SnW8 7/20/98 fd@8 7 Vt98 i OFFIC'AL RECORD COPY l

! 9808050017 980729 l t

PDR ADOCK 05000331 {

l 0 PDR L

July 29, 1998

, Mr. Leo Liu Chairm:n of tha Bo:rd cnd Chief Executive Officer I lES Utilities Inc.

200 First Street, SE P.O. Box 351 Cedar Rapids, IA 52406-0351

SUBJECT:

EVALUATION OF RELIEF REQUEST NDE-R020 - DUANE ARNOLD ENERGY CENTER (TAC NO. MA1576)

Dear Mr. Liu:

By letter dated April 26,1996, IES Utilities Inc. (lES) submitted its inservice inspection (ISI) plan for the third 10-year inservice inspection interval of the Duane Amold Energy Center (DAEC). By letter dated March 23,1998, the NRC provided its evaluation of the DAEC ISI plan and its associated relief requests. in its evaluation, the NRC staff stated that the review of relief request NDE -R020 would be evaluated in a separate report.

Based on discussions with the staff, IES submitted a revision to relief request NDE-R020 on May 15,1998. The staff has reviewed and evaluated relief request NDE-R020 as documented in the enclosed safety evaluation. The staff has determined that the proposed attemative to use the DAEC Technical Specification requirements for visual examination and functional testing for j snubbers provides an acceptable level of quality and safety. Accordingly, the altemative is i authorized pursuant to 10 CFR 50.55a(a)(3)(i).  !

)

Sincerely, Original signed by:

{

Ronald R. Bellamy, Acting Director {

Project Directorate 111-3 Division of Reactor Projects Ill/IV Office of Nuclear Reactor Regulation Docket No. 50-331 l

l

Enclosure:

Safety Evaluation

]

cc w/ encl: See next page DISTRIBUTION: I Docket File ACRS i RLaufer OGC EAdensam (EGA1)

PUBLIC GGrant, Rlli PD3-3 R/F l GTracy GHill(2)

THarris (SE only)

DOCUMENT NAME: G:\DUANEARN\MA1576.RR

  • No,tdd eM to SE OFFICE PD3-3 LA lE PD3-3 PM IE EMEB- l OGCI f/ FPD3-3 (A)PD l *-

NAME EBamNil 9127 RLaufer F KManoly* i t'/M14uf RBellamy F DATE 1/>%8 >SW8 7 /20/98, fdh98 4' V$18 OFFICIAL RECORD COPY

M*to

? k UNITED STATES I f g j NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 3000H201 g%[4. . . . . p$

1 l

July 29, 1998 Mr. Lee Liu Chairman of the Board and  ;

Chief Executive Officer j IES Utilities Inc.  !

200 First Street, SE  !

P.O. Box 351

. Cedar Rapids, lA 52406-0351

SUBJECT:

EVALUATION OF REllEF REQUEST NDE-R020 - DUANE ARNOLD ENERGY CENTER (TAC NO. MA1576) l i

Dear Mr. Liu:

l By letter dated April 26,1996, IES Utilities Inc. (lES) submitted its inservice inspection (ISI) plan for the third 10-year inservice inspection interval of the Duane Amold Energy Center (DAEC). By letter dated March 23,1998, the NRC provided its evaluation of the DAEC ISI plan and its associated relief requests. In its evaluatio,1, the NRC staff stated that the review of relief request NDE -R020 would be evaluated in a separate report.

Based on discussions with the staff, IES submitted a revision to relief request NDE-R020 on May 15,1998. The staff has reviewed and evaluated relief request NDE-R020 as documented in the enclosed safety evaluation. The staff has determined that the proposed attemative to use )

the DAEC Technical Specification requirements for visual examination and functional testing for snubbers provides an acceptable level of quality and safety. Accordingly, the attemative is authorized pursuant to 10 CFR 50.55a(a)(3)(i).

Sincerely, j

.\

Ronald R. Bellamy, Acting Director Project Directorate 111-3

{

1 Division of Reactor Projects lil/IV Office of Nuclear Reactor Regulation Docket No. 50-331

Enclosure:

Safety Evaluation

, cc w/ encl: See next page i

i Lee Liu Duane Amold Energy Center IES Utilities Inc.

cc:

Jack Newman, Esquire Al Gutterman, Esquire Morgan, Lewis, & Bocklus 1800 M Street, NW.

Washington, DC 20036-5869 Chairman, Linn County Board of Supervisors Cedar Rapids,IA 52406 IES Utilities Inc.

ATTN: Gary Van Middlesworth Plant Superintendent, Nuclear 3277 DAEC Road Palo,IA 52324 John F. Franz, Jr.

  • Vice President, Nuclear Duane Amold Energy Center 3277 DAEC Road Palo,IA 52324 Ken Peveler Manager of Regulatory Performance l Duane Amold Energy Center j 3277 DAEC Road Palo,IA 52324 U.S. Nuclear Regulatory Commission Resident inspector's Office RuralRoute #1 Palo,IA 52324 Regional Administrator, Rill U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4531 i

Parween Baig '

- Utilities Division Iowa Department of Commerce Lucas Office Building,5th floor Des Moines,IA 50319 r

i