Letter Sequence Other |
---|
|
Results
Other: ML20151L878, ML20215B790, ML20215B804, ML20215G101, ML20215G650, ML20215G653, ML20234D077, ML20236D570, ML20236F145, ML20236F153, ML20236F168, ML20236M855, ML20236M871, ML20237J052
|
MONTHYEARML20236X2381987-06-0404 June 1987 Kerotest Valve Flow Test, Subtask Rept,Accumulator Fill Line Failure.Chronology & Action Plan Encl Project stage: Other ML20215B7901987-06-11011 June 1987 Forwards Evaluation Rept of Main Steam Pipe Wall Thickness, Describing Fatigue & Finite Element Analyses Performed on Affected Piping,Per ASME Boiler & Pressure Vessel Code.Affected Piping Will Be Reexamined in 1988 Project stage: Other ML20215G6531987-06-11011 June 1987 Trojan Nuclear Plant Evaluation of Main Feed Line Seismic Restraint Failure Project stage: Other ML20215G1011987-06-12012 June 1987 Forwards Evaluation of Displacement at Main Feedwater Restraint SR4 in Trojan Nuclear Plant & Trojan Nuclear Plant Evaluation of Main Feed Line Seismic Restraint Failure, as Result of Failure During 1987 Refueling Outage Project stage: Other ML20215B8041987-06-30030 June 1987 Evaluation Rept of Trojan Nuclear Plant Main Steam Pipe Wall Thickness Project stage: Other ML20215G6501987-06-30030 June 1987 Evaluation of Displacement at Main Feedwater Restraint SR4 in Trojan Nuclear Plant Project stage: Other ML20234D0771987-06-30030 June 1987 Advises That Util Agrees to Complete One of Three Listed Actions Re Resolution of Main Steam Line Wall Thickness Issue Before Startup from 1989 Refueling Outage Project stage: Other ML20236F1531987-07-17017 July 1987 Final Rept Trojan Nuclear Plant SR8 Failure Root Cause Evaluation Steam Condensation-Induced Water Hammer Project stage: Other IR 05000344/19870261987-07-27027 July 1987 Insp Rept 50-344/87-26 on 870706-10.No Violations or Deviations Noted.Major Areas Inspected:Licensee Action on Previous Insp Findings,External & Internal Exposure Control, Control of Radioactive Matls & Contamination & ALARA Project stage: Request ML20236F1451987-07-27027 July 1987 Forwards Bechtel Western Power Corp Final Rept, Trojan Nuclear Plant SR8 Failure Root Cause Evaluation Steam Condensation-Induced Water Hammer & Impell Corp Summary Rept, Independent Review of Action Plan Items.. Project stage: Other ML20236D5701987-07-27027 July 1987 Advises That Util Plans to Resolve Issue Re Code Acceptability Applications Prior to 871201.Util Will Perform Necessary Design & Order Matls to Repair or Replace Unacceptable Main Steam Line Wall Thickness Areas Project stage: Other ML20236L3451987-07-30030 July 1987 Summary of 870617 Meeting W/Util,Bechtel & Impell Re Results of Analyses Concerning Accumulator Fill Line Failure,Main Feedwater Failure & Main Steam Line Thin Wall at Plant.List of Attendees & Viewgraphs Encl Project stage: Meeting ML20236F1681987-07-31031 July 1987 Rev 1 to Summary Rept, Independent Review of Action Plan Items to Resolve Trojan Main Feedwater Piping Restraint Failure Issue Project stage: Other ML20237J2151987-08-21021 August 1987 Advises That Technical Issues Re Accumulator Fill Line Failure & Main Feedwater Pipe Restraint Failure Adequately Addressed by Licensee.Summary of 870617 Meeting Encl.W/O Encl Project stage: Meeting ML20237J0521987-08-21021 August 1987 Responds to Util Proposing to Resolve Issue Re Main Steam Line Wall Thicknesses Which Did Not Meet Min Requirements.Util Adequately Demonstrated That Safe Operation of Plant Until May 1989 Will Not Be Compromised Project stage: Other ML20238C3451987-09-0404 September 1987 Forwards Response to NRC Request for Addl Info Re Accumulator Fill Line Nozzle Stress Calculation.Areas Discussed Include Estimate of Previous Nozzle Loading & Fatigue Usage Factors Project stage: Request ML20236M8371987-11-11011 November 1987 Forwards SERs Re Main Feedwater Line Restraint Failure & Accumulator Fill Line Failures at Plant.Repairs Proposed by Util Acceptable to Ensure Integrity of Damaged Sys for Continuing Plant Operation Project stage: Approval ML20236M8551987-11-11011 November 1987 SER Supporting Util Repairs Proposal Re Main Feedwater Line Restraint Failure Project stage: Other ML20236M8711987-11-11011 November 1987 SER Supporting Util Repairs Proposal Re Accumulator Fill Line Failures Project stage: Other ML20236X2261987-12-0303 December 1987 Forwards Presentation Handout & Subtask Rept Describing Backflow Test Conducted to Verify Postulated Failure Mode of Accumulator Fill Line & Recovery Action Plan Project stage: Other ML20151L8781988-04-15015 April 1988 Forwards Addl Info Re Six Open Items/Recommendations Noted in NRC 871111 Safety Evaluation of Failure of Main Feedwater Sys Restraint SR-8,per Commitment During Audit of long-term Pipe Support Design Verification Program in Jan 1988 Project stage: Other 1987-07-17
[Table View] |
|
---|
Category:SAFETY EVALUATION REPORT--LICENSING & RELATED ISSUES
MONTHYEARML20206H4501999-05-0505 May 1999 Safety Evaluation Supporting Amend 201 to License NPF-1 ML20206C9751999-04-23023 April 1999 Safety Evaluation Supporting Amend 200 to License NPF-1 ML20206C9351999-04-23023 April 1999 Safety Evaluation Supporting Amend 199 to License NPF-1 ML20155E0561998-10-29029 October 1998 SER Approving Two Specific Exemptions Under 10CFR71.8 for Approval of Trojan Reactor Vessel Package for one-time Shipment to Us Ecology Disposal Facility Near Richland,Wa ML20148K3541997-06-0909 June 1997 Safety Evaluation Supporting Amend 198 to License NPF-1 ML20148D2681997-05-23023 May 1997 Safety Evaluation Supporting Amend 197 to License NPF-1 ML20141H3181997-05-19019 May 1997 Safety Evaluation Supporting Amend 196 to License NPF-1 ML20136D5591997-03-0606 March 1997 Safety Evaluation Approving Merger Between Util & Enron Corp ML20134M3381996-11-20020 November 1996 SER Approving Physical Security Plan for Proposed Trojan ISFSI ML20134F1211996-10-31031 October 1996 Safety Evaluation Supporting Amend 195 to License NPF-1 ML20058K1391993-12-0606 December 1993 Safety Evaluation Supporting Amend 193 to License NPF-1 ML20057D9951993-09-30030 September 1993 Safety Evaluation Accepting Licensee Request for Exemption from Certain 10CFR50 Requirements for Emergency Planning for Plant ML20057D0791993-09-22022 September 1993 Safety Evaluation Supporting Amend 192 to License NPF-1 ML20127P5801993-01-26026 January 1993 Safety Evaluation Supporting Amend 189 to License NPF-1 ML20125B8071992-12-0404 December 1992 Safety Evaluation Supporting Amend 188 to License NPF-1 ML20127L4221992-11-19019 November 1992 SE Accepting IST Program Requests for Relief for Pumps & Valves ML20059D1031990-08-30030 August 1990 SER Accepting Util 880311,0401 & 1223 & 900319 & 0622 Responses to NRC Bulletin 88-002, Rapidly Propagating Fatigue Cracks in Steam Generator Tubes ML20059C7981990-08-27027 August 1990 Safety Evaluation Supporting Amend 162 to License NPF-1 ML20058L5641990-08-0202 August 1990 Safety Evaluation Concluding That Operable Instrumented Ammonia Detection Capability Unncessary for Protection of Control Room Personnel in Event of Spill of Anhydrous Ammonia in Vicinity of Plant ML20055C7531990-06-18018 June 1990 Safety Evaluation Supporting Amend 161 to License NPF-1 ML20245H4141989-08-10010 August 1989 Safety Evaluation Approving on-line Functional Testing of Reactor Trip Sys,Per Generic Ltr 83-28,Item 4.5.3, Reactor Trip Sys Reliability for All Domestic Operating Reactors ML20245E8091989-06-20020 June 1989 Safety Evaluation Supporting Amend 154 to License NPF-1 ML20247M9331989-05-24024 May 1989 Safety Evaluation Supporting Amend 153 to License NPF-1 ML20247H9571989-05-15015 May 1989 Safety Evaluation Supporting Amend 152 to License NPF-1 ML20247F1911989-03-17017 March 1989 Safety Evaluation Supporting Amend 151 to License NPF-1 ML20235T5351989-02-28028 February 1989 Safety Evaluation Supporting Amend 150 to License NPF-1 ML20151T4191988-08-0505 August 1988 Safety Evaluation Supporting Elimination of Postulated Primary Loop Pipe Ruptures as Design Basis for Facility ML20151X8581988-08-0303 August 1988 Safety Evaluation Supporting Amend 149 to License NPF-1 ML20151H3041988-07-14014 July 1988 Safety Evaluation Supporting Amend 148 to License NPF-1 ML20151L4391988-07-11011 July 1988 Safety Evaluation Supporting Amend 147 to License NPF-1 ML20151E4551988-07-11011 July 1988 Safety Evaluation Supporting Amend 147 to License NPF-1 ML20196G0421988-06-23023 June 1988 Safety Evaluation Supporting Amend 145 to License NPF-1 ML20196C1571988-06-22022 June 1988 Safety Evaluation Supporting Amend 144 to License NPF-1 ML20196F9471988-06-16016 June 1988 Safety Evaluation Supporting Amend 143 to License NPF-1 ML20154D4931988-05-11011 May 1988 Safety Evaluation Supporting Amend 142 to License NPF-1 ML20154A1151988-05-0303 May 1988 Safety Evaluation Supporting Amend 141 to License NPF-1 ML20148S6491988-04-11011 April 1988 Safety Evaluation Supporting Amend 140 to License NPF-1 ML20151B3821988-03-31031 March 1988 Safety Evaluation Supporting Amend 139 to License NPF-1 ML20236X5311987-12-0101 December 1987 Safety Evaluation Supporting Amend 137 to License NPF-1 ML20236S4021987-11-12012 November 1987 Safety Evaluation Supporting Exemption from Requirements of 10CFR50,App R,Section III.G.2 Re Fire Protection of Safe Shutdown Capability Requirements ML20236M8711987-11-11011 November 1987 SER Supporting Util Repairs Proposal Re Accumulator Fill Line Failures ML20236M8551987-11-11011 November 1987 SER Supporting Util Repairs Proposal Re Main Feedwater Line Restraint Failure ML20236M9931987-11-0909 November 1987 Safety Evaluation Supporting Amend 136 to License NPF-1 ML20236A9151987-10-13013 October 1987 Safety Evaluation Concluding That Corrective Actions for Design Deficiencies in Main Steam Line Pipe Supports Adequate & Acceptable & That Commencement of Heatup & Return to Power Safe ML20235V6121987-10-0202 October 1987 Safety Evaluation Supporting Amend 135 to License NPF-1 ML20238B0181987-09-0101 September 1987 Safety Evaluation Supporting Amend 134 to License NPF-1 ML20237G8351987-08-25025 August 1987 Safety Evaluation Re Util 870723 Request for Relief from 4 H Test Pressure Hold Time Requirement of Section XI of ASME Code,1974 Edition Through Summer 1975 Addenda ML20237G8421987-08-24024 August 1987 Safety Evaluation Re Ultrasonic Insp of RCS hot-leg Elbow (Loop B).Ultrasonic Exam Performed Acceptable W/Exception of Ultrasonic Beam Spread Correction Procedures Used to Estimate Indication Size.Continued Operation Permissible ML20236P6731987-08-0707 August 1987 Safety Evaluation Supporting Amend 133 to License NPF-1 ML20236H5581987-07-30030 July 1987 Safety Evaluation Supporting Amend 132 to License NPF-1 1999-05-05
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20210F8701999-07-22022 July 1999 Rev 1 to PGE-1076, Trojan Reactor Vessel Package Sar ML20209C6531999-07-0606 July 1999 Rev 8 to Defueled SAR, for Trojan Nuclear Plant ML20206H4501999-05-0505 May 1999 Safety Evaluation Supporting Amend 201 to License NPF-1 ML20206C9351999-04-23023 April 1999 Safety Evaluation Supporting Amend 199 to License NPF-1 ML20206C9751999-04-23023 April 1999 Safety Evaluation Supporting Amend 200 to License NPF-1 ML20207G9881999-03-0303 March 1999 Rev 6 to Trojan Nuclear Plant Decommissioning Plan ML20207J0781999-02-28028 February 1999 Update to Trojan ISFSI Sar ML20202G4511999-02-0202 February 1999 Rev 0 to PGE-1076, Trojan Reactor Vessel Package Sar ML20207C6981998-12-31031 December 1998 1998 Annual Rept for Trojan Nuclear Plant. with ML20195J2501998-11-17017 November 1998 Rev 7 to Trojan Nuclear Plant Defueled Sar ML20155E0561998-10-29029 October 1998 SER Approving Two Specific Exemptions Under 10CFR71.8 for Approval of Trojan Reactor Vessel Package for one-time Shipment to Us Ecology Disposal Facility Near Richland,Wa ML20155E0411998-10-27027 October 1998 Amend 7 to Quality-Related List Classification Criteria for Tnp ML20154R4121998-10-0202 October 1998 Requests Commission Approval,By Negative Consent,For Staff to Grant Two Specific Exemptions from Package Test Requirement Specified in 10CFR71 for Trojan Reactor Vessel Package & to Authorize one-time Transport for Disposal ML20237B6121998-08-13013 August 1998 Revised Trojan Reactor Vessel Package Sar ML20151W5471998-08-13013 August 1998 Rev 22 to PGE-8010, Poge Nuclear QA Program for Trojan Nuclear Plant ML20236Y2691998-08-0808 August 1998 Revised Trojan Rv Package Sar ML20249B4081998-06-17017 June 1998 Rev 6 to Trojan Nuclear Plant Defueled Sar ML20203E6291998-02-28028 February 1998 Trojan Nuclear Plant Decommissioning Plan ML20198T1741998-01-0404 January 1998 Rev 5 to Trojan Nuclear Plant Decommissioning Plan ML20248K6891997-12-31031 December 1997 Enron 1997 Annual Rept ML20203J3821997-12-31031 December 1997 Annual Rept of Trojan Nuclear Plant for 1997 ML20248K6931997-12-31031 December 1997 Pacificorp 1997 Annual Rept. Financial Statements & Suppl Data for Years Ended Dec 1996 & 97 Also Encl ML20203B0341997-11-26026 November 1997 Rev 5 to Trojan Nuclear Plant Defueled Sar ML20199F8141997-10-21021 October 1997 Requests Approval of Staff Approach for Resolving Issues Re Waste Classification of Plant Rv ML20216F4291997-07-25025 July 1997 Requests Commission Approval of Staff Approach for Reviewing Request from Poge for one-time Shipment of Decommissioned Rv,Including Irradiated Internals to Disposal Site at Hanford Nuclear Reservation in Richland,Wa ML20141F2311997-06-24024 June 1997 Rev 3 to PGE-1061, Tnp Decommissioning Plan ML20148K3541997-06-0909 June 1997 Safety Evaluation Supporting Amend 198 to License NPF-1 ML20148E8631997-05-31031 May 1997 Amend 6 to PGE-1052, Quality-Related List Classification Criteria for Trojan Nuclear Plant ML20148D2681997-05-23023 May 1997 Safety Evaluation Supporting Amend 197 to License NPF-1 ML20141H3181997-05-19019 May 1997 Safety Evaluation Supporting Amend 196 to License NPF-1 ML20140D9451997-03-31031 March 1997 Tnp First Quarter 1997 Decommissioning Status Rept ML20137K5811997-03-31031 March 1997 SAR for Rv Package ML20136D5591997-03-0606 March 1997 Safety Evaluation Approving Merger Between Util & Enron Corp ML20134B6231997-01-15015 January 1997 Draft Rev 3 of Proposed Change to Trojan Decommissioning Plan ML20217M2381996-12-31031 December 1996 Portland General Corp 1996 Annual Rept ML20217M2471996-12-31031 December 1996 Pacific Power & Light Co (Pacifcorp) 1996 Annual Rept ML20217M2551996-12-31031 December 1996 1996 Enron Annual Rept ML20135C3521996-12-31031 December 1996 Annual Rept of Trojan Nuclear Plant for 1996 ML20132G2831996-12-19019 December 1996 Rev 2 to PGE-1061, Trojan Nuclear Plant Decommissioning Plan ML20132H0011996-12-12012 December 1996 Rev 20 to PGE-8010, Portland General Electric Nuclear QA Program for Trojan Nuclear Plant ML20132B8491996-12-12012 December 1996 Rev 20 to PGE-8010, Trojan Nuclear Plant Nuclear QA Program ML20135B5241996-11-27027 November 1996 Rev 4 to Trojan Nuclear Plant Defueled Sar ML20135B5341996-11-25025 November 1996 Trojan ISFSI Safety Analysis Rept ML20134M3381996-11-20020 November 1996 SER Approving Physical Security Plan for Proposed Trojan ISFSI ML20134K6621996-11-11011 November 1996 Decommissioning Plan,Tnp ML20134F1211996-10-31031 October 1996 Safety Evaluation Supporting Amend 195 to License NPF-1 ML20134F4661996-10-30030 October 1996 Final Survey Rept for ISFSI Site for Trojan Nuclear Plant ML20134P4321996-09-30030 September 1996 Tnp Quarter Decommisioning Status Rept,Third Quarter 1996 ML20137K5321996-09-0505 September 1996 Rev 0 to H Analysis of Residue Protocol ML20137K5091996-06-28028 June 1996 Summary Rept Poge Tnp SFP Project 1999-07-06
[Table view] |
Text
p. _
'y. j ENCLOSURE A I SAFETY EVALUATION REPORT ,
4 MAIN FEEDWATER LINE RESTRAINT FAILURE TROJAN NUCLEAR PLANT l DOCKET NO. 50-344 j 1
l t
- 1.0 Description of Event l t . i During the 1987 Refueling outage, a seismic restraint (SR8) on the Loop B feed-water piping inside containment was found to have a failed structural attachment to the concrete. 'The restraint had been inspected during the 1986 outage and was found to be intact at that time. The restraint is located on the first vertical The desi j run of p)iping inside containment.(thermal , 5.246
. The kipsis(0BE) restraint oriented andin8.761 the (SSE)gn loaj east-west direction and consists of a pipe clamp, a rigid sway strut (Bergen- l Paterson RSSA-10), and end attachment, a supplementary steel frame structure .. ;
(W6x20 vertical member, W4x13 knee brace) with two 1/2" base plates each attached l to the concrete with 4-5/8".phillips red head concrete expansion anchor bolts and 1 2.5" embedment lengths. The failure consisted of pullout in one irregular shaped !
cone of the concrete under the baseplate for the knee brace and broken concrete i under the vertical member baseplate. 1 1
2.0 Licensee's Efforts l 2.1 Root Cause Evaluation A. Evaluation of possible events The Bechtel report enclosed in Reference 1 evaluated a number of possible events which could have contributed to a significant load on the feedwater l system. Bechtel performed several analyses which demonstrated that normal I operating loads in conjunction with postulated snubber malfunction, excessive strut preload, and constraint expansion due to the Integrated Leak Rate Testing could not have generated forces large enough to cause the damage.
l observed. The load required to cause support failure was estimated to be not less than 40 kips. Bechtel concluded that the damage to SR8 most likely occurred as a result of a water hammer. Bechtel also determined that thermal l bowing of the long run of horizontal piping due to low flow thermal strati-i fication could have been a contributing factor that could coexist with a postulated water hammer resulting in additional loads to the pipe supports.
B. Verification of. Stresses in Design Conditions The portion of feedwater piping,inside containment was reanalyzed. The calculated piping and support loads were confirmed to be within design allowables. Calculations also found that loads remain within allowables '
even without SR8.
C. Post Event Inspection 8711130311 871111 gDR ADOCK O y4
The inspections included visual, radiographic and ultrasonic examinations of the B loop feedwater piping, valves and supports, similar but less extensive examinations of the A loop and visual and surface examinations of the C and D feedwater lines. With the exception of the damaged support, only chatter and scrape marks on three B loop hangers were the only other observed abnormal indications considered to be associated with the failure of SR8. Piping integrity was maintained after the SR8 damage.
D. Calculations for a hypothetical water hammer loads A hydraulic analysis was performed to establish water hammer forces resulting from normal plant trip with valve closures, and with a possible stuck open check valve or inadvertent delays in control valve and isolation valve closures. Water hamer forces resulting from conden-sation of postulated steam bubbles in the feedwater line steam generator j feed ring were also calculated.
l E. Piping analysis for response to hypothetical water hamer loads l
A linear elastic time history analysis was performed to evaluate the feedwater piping and support response to the hypothetical water hamer loads. Piping with and without SR8 support were both evaluated. The dynamic response and maximum stress values were similar for both cases.
The analysis verified that SR8 would be expected to be the first to fail due to lower anchorage capacity and being the only rigid support in the system. The failures of SR8 indicates that the occurrence of a water hamer was likely.
l In sumary, the above evaluations concluded that the damage to SR8 likely occurred as a result of water hamer and possibly in conjunction with thermal stratification loads, and the anchorage of SR8 was the limiting component of the system. However, the damage of SR8 did not affect the integrity of the feedwater system, and system integrity remains even without SR8. ,
2.2 Corrective Actions A. Support modifications Repairs to SR8 have been completed. The modified SR8 has a new anchorage system consisting of stronger bolts passing through the whole thickness of the slab, which is over 30 inches instead of 2.5 inches embedment in the original design. Thus capacity of SR8 is much enhanced.
B. System operation changes By modification of system operating procedures, flow rate in feedwater line and steam generator water level can be better controlled to minimize the possible occurrences of the condensation induced water hammer event.
I s
o
~ e e
P 9
C. System maintenance testing The main and auxiliary feedwater check valves will be checked for back leakage during startups from each refueling outage, and a maintenance inspection of these valves will be performed once every two years.
D. Dynamic load monitoring Instrumented monitoring for possible oce m ences of water hammer type dynamic lords to the feedwater system will be impleerti Dressure trans-ducers, pressure indicator alann, recorder to pipe movement, and thermo-couples will be used to ensure data collections for any major transient.
E. Third party reviews The licensee retained Impell Corporation to perform an independent review of the issues pertaining to SR8 damage, including thermal hydraulic analysis, piping analysis and support evaluations performed by Bechtel. The Impell review concurred with the Bechtel conclusions on the cause of SR8 damage with minor recommendations (Reference 3).
3.0 Staff Evaluation The staff reviewed all of the reports and calculation summaries provided by the licensee in submittals dated June 12, 1987 (Reference 1), June 16, 1987 (Reference ;
2)andJuly 27, 1987 (Reference 3). These submittals included a Bechtel report on the evaluation of the support failure, a pGE report on the evaluation of the failure, and an Impell report on their independent review of the evaluation. l l
Judging from differences in magnitudes of loads caused by various events to piping and supports as shown in the Bechtel report (Reference 1), the staff agrees with the primary conclusion in the Bechtel report that the damage to SR8 most likely occurred as a result of an unanticipated water hammer. The staff considers the review effort as described in the PGE report (Reference 2) to be comprehensive.
The action plan appears complete and its implementation has provided positive bases to support the conclusion that water hantner was the most probable cause of failure of SR8. Specifically the staff considers that the evaluations and analyses performed have adequt.tely demonstrated that bubble collapse in the feedwater line near the steam generator nozzle can generate severe transient loads to cause the failure and that the prerequisite initiators of feedwater line drain back and high refill rate existed in the time periods when failure occurred.
The staff has reviewed the post-event inspection and repair performed by the licensee and considers that the inspection was extensive enough to reveal any measurable damage caused by the SR8 failure. The staff had conducted an on site inspection of the main feedwater line. Based on evidence of actual damage observed, the staff concurs with the scope of repair. By reinstalling the undamaged SR8 support with a strengthened anchorage system, SR8 will have ample capacity to sustain much greater loads than the design intended.
o
y -'
l 4
4 4
The staff accepts the licensee's corrective actions of instituting operating ,
l L procedure changes to minimize feedwater line drain back which should minimize ' D the formation of steam bubbles in the feedwater line following a plant trip j and reduce the chance of future water hammer. !
The staff considers that the licensee's monitoring program has provided a'suf-ficient, though limited,' amount of instrumentation to monitor future dynamic events. Instrumentation consisting of rapid response and alarmed pressure ]
) transducers on the feedwater lines, linear potentiometer. displacement monitors -
l on spring supports H9.and H13 and thermocouple on the top and bottom of the..
rt m generator no nles have been installed. This instrumentation will be useful' y to monitor temperatures and peak system pressures during normal operations-ano will provide time history plots of the monitored pressures and system displacements when system pressures exceed 100 psi above steady state valuas. --IotMs regard )
the staff feels that the ~ addition of some accelerometers mounted in locations-where peak accelerations would be expected would greatly enhance the monitoring - q effort.-
The staff reviewed the July 27, 1987 PGEReport(Reference 3)whichconsistedof' i Appendices A and B. Appendix A provided a description of the water slug motion analyses performed by Bechtel as part of the Action Plan. 'As noted above.the .
~
j staff regards these analyses and the others as an~ adequate basis to support.the 1 licensee's root cause determination. The staff recommends that the table be expanded to include columns listing estimates of pipe displacements at the hanger locations and pipe stresses at key locations. This data could prove.useful in corroborating the estimates of failure loads against the observed hanger displace- 1 ments and in providing a basis for fatigue usage estimates. Appendix B is a sumary i of the independent review of Action Plan items perfonned by Impell Corporation. The staff has reviewed the Impell report and concurs with its findings and recommendations. 3 The staff requires that the licensee comply with all the Impe11- proposed actions.
Although the staff considers the Licensee's Action Plan to be well conceived- 4 and comprehensive, it has identified the following two concerns.:
l A. The feedwater system was subjected to dynamic. loads which were great enough . :
to fail the anchorage of SR8. These loads may also have caused permanent, although invisible and unmeasureable damage to the feedwater piping and its components, possibly reducing their serviceable life. This issue does not seem to have been addressed in the Action Plan. ,
i B. ItisstatedinAppendixBtothePGEreport(Reference 3).thattheallowable load for the strut in SR8 is 20 kips under faulted conditions and the inspections y of SR8 revealed no signs of distress. Assuming that-the other structural members of SR8 were also designed to meet a load of. 20. kips with a' comparable margin, it is; l questionable to expect that alllthese members could be subjected to an estimated 1
failure load of 40 kips without showing any definite indications ofidistress'. .A. ,
verification to ensure consistency between the estimated failure load of SR8 and the extent of the observed damage.is needed. '.4
_-_m m____________.__________l.5__
l0 1 . 4.0 Conclusions 1
h ~Ths statf concludes that the licenroe has ideatified the most probable cause cf failure of the seismic restraint SR8 and has taken appropriate actions to minimize the possibility of future recurrences. The inspections demonstrated that the feedwater piping and other support structures had not undergone measurable damage during the failure and, with the repair of the SR8 restraint, the system will be returned to an operable configuration with greater capacity to resist similar events in the future. The maintenance testing and inspection of main i and auxiliary feedwater check valves will enhance their operability and minimize i unanticipated transients induced by the malfunctioning of these valves. l 1
The monitoring program vill verify the effectiveness of changes in system oper- ;
ation procedures and get better understanding about the characteristics of severe transients should it recur. However, the licensee should confirm the following: ,
A. To ensure that the failure of restraint SR8 has not reduced the fatigue l life of the feedwater piping systems to unacceptable levels for continuing service.
B. To ensure consistency between the estimated failure load of SR8 and the extent of damage observed.
C. To ensure that the proposed feedwater check valve maintenance and testing program is not inconsistent with the IST program for all valves in the Trojan '
plant.
w References
- 1. Letter, PGE to NRC, " Main Feedwater Restraint Failure Engineering Analyses",
June 12, 1987.
l 2. Letter, PGE to NRC Region V, " Main Feedwater Restraint Failure", June 16, 1987.
- 3. Letter, PGE to NRC, " Main Feedwater Restraint Failure Engineering Analyses",
July 27, 1987.
i l