Informs That 870603 Changes to Initial Test Program Described in Chapter 14 of Util FSAR Acceptable,Except Change 1,deletion of RHR Steam Condensing Mode Testing. Change 1 Acceptable Only When Listed Actions Taken
ML20235V938
Person / Time
Site: Clinton 
Issue date: 07/16/1987
From: Muller D
Office of Nuclear Reactor Regulation
To: Spangenberg F
ILLINOIS POWER CO.
References
NUDOCS 8707230362
Download: ML20235V938 (3)


Text

s 1

July 16,1987 DISTRIBUTION I

NDocRet',Fileg RRameriz

'NRC & L6 cal PDRs TCollins PDIII-2 Rdg. File CNorelius Reg.'III I

GHolahan RKnop Reg. III M0'Brien MMcCormick-Barger BSiegel Reg. III OGC-Bethesda ACRS (10)

EJordan PDIII-2 Plant File-JPartlow Docket No. 50-461 Mr. Frank A. Spangenberg Manager - Licensing and Safety Clinton Power Station P.O. Box.678 Mail Code V920 Clinton, Illinois 61727

Dear Mr. Spangenberg:

SUBJECT:

CHANGES TO CLINTON INITIAL TEST PROGRAM (FACILITY OPERATING LICENSE NPF-62, CONDITION 2.C.8)

Pursant to Facility Operating License NPF-62, Condition 2.C.8, by letter dated June 3,1987 you reported three changes to the initial test program described-in Chapter 14 of the Clinton Power Station Final Safety Analysis Report. Change 1 deletes all reference to the testing of the steam condensing mode of the residual heat removal system (RHR), change 2 clarifies that some leakage from the turbine gland seal system may occur, but t1 will not be significant and change 3 allows for the individual control rod times test to be performed in either Test Londition 1 or 2.

The NRC staff has reviewed these three changes and find them acceptable, however, the deletion of the testing of the steam condensing mode of RHR (change 1) is acceptable only if the following actions are taken; a.

Administrative controls are instituted and the appropriate valves are locked out to preclude inadvertent operation of the RHR in the steam condensing mode.

l b.

Plant procedures are revised to reflect that operation in the steam 1

condensing mode of RHR is not permitted, c.

The NRC is informed prior to performing the deleted test should you decide to use the steam condensing mode of RHR at a later date.

l 1

i 8707230362 870716 PDR ADOCK 05000461 P

PDR

Mr. Frank A. Spangenberg

  • Illinois Power Company If you have any questions regarding this subject please contact the Project Manager, for your facility, Byron Siegel at (301) 492-7764.

Sincerely, l

Original Signed by/

Daniel R. Muller, Director l

Project Directorate III-2 Division of Reactor Projects - III, IV, V and Special Projects Office of Nuclear Reactor Regulation cc: See next page a

l l

PDIII-2:P PDIII-2:D BSiegel:bj DMuller 47 //5 /87 7 //(> /87 1

1 1

Mr. Frank A. Spangenberg Clinton Power Station Illinois Power Company Unit 1 i

cc:

i Mr. L. Larson l

Project Manager l

l Mr. D. P. Hall General Electric Company

)

Vice President 175 Curtner Avenue, N/C 395 Clinton Power Station San Jose, California 95125 P. O. Bnx 678

)

l Clinton, Illinois, 61727 Regional Administrator, Region III 799 Roosevelt Road I

I Mr. Wilfred Connell Glen Ellyn, Illinois 60137 Manager-Nuclear Station Engineering Opt.

Clinton Power Station Chairman of Dewitt County P. O. Box 678 c/o County Clerk's Office Clinton, Illinois 61727 DeWitt County Courthouse Clinton, Illinois 61727 Sheldon Zabel, Esquire

]

Schiff, Hardin & Waite Illinois Department 7200 Sears Tower of Nuclear Safety 233 Wacker Drive Division of Engineering I

Chicago, Illinois 60606 1035 Outer Park Drive, 5th Floor Springfield, Illinois, 62704 Resident Inspector U. S. Nuclear Regulatory Commission Mr. Donald Schopfer RR 3, Box 229 A Project Manager Clinton, Illinois 61727 Sargent & Lundy Engineers 55 East Monroe Street Chicago, Illinois 60603

[