Confirms 870710 Telcon That Enforcement Discretion Granted to Delay Achievement of Cold Shutdown for Addl 42 H Beyond Util Action Statement of Tech Spec 3.7.6.Enforcement Discretion Also Granted for Util 870710 Request (Encl 2)
ML20235U710
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 07/14/1987
From: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: James O'Reilly
GEORGIA POWER CO.
References
NUDOCS 8707220563
Download: ML20235U710 (2)


Text

_

j JUL 14 1987 Georgia Power Company LATTN: Mr. James P. O'Reilly Senior Vice President-Nuclear Operations P. O. Box 4545 Atlanta, GA 30302 Gentlemen:

SUBJECT:

CONFIRMATION OF ENFORCEMENT DISCRETION REGARDING TECHNICAL SPECIFICATION 3.7.6 - DOCKET NO. 50-424 On July 10, 1987, NRC granted verbal enforcement discretion concerning Vogtle Technical Specification 3.7.6 action statement in a telephone conversation with W. Burns and G. Bockhold of your staff.

NRC received your letter dated July 10, 1987 describing the request and agreements. This GPC letter has been reviewed by the NRC staff. This letter confirms that enforcement discretion is granted to permit delaying the achievement of Cold Shutdown for an additional 42 hours4.861111e-4 days <br />0.0117 hours <br />6.944444e-5 weeks <br />1.5981e-5 months <br /> beyond your action statement of TS 3.7.6 from July 10 until July 12, 1987 at 4:22 p.m. EST.

Also, enforcement discretion is granted to permit the startup and power operation for a period of up to seven days after the "B" train is restored to operable status before removing the "A"

train from service for similar modifications.

Justification for operation in this condition is addressed in of the GPC Letter dated July 10, 1987.

Should you have any further questions regarding this letter, please contact this office.

Sincerely, 4

J. Ne son Grace Regional Administrator cc: Lf. D. Rice, Vice President, Project Director DCIW. Hayes,VogtleQuality Assurance Manacer i

uG' Bockhold, Jr.', General Manager, l

Nuclear Operations if. Gucwa, Manager, Nuclear Safety l

and Licensing (cc cont'd - see page 2)

B707220563 870714

~

PDR ADOCK 05000424 g

p PDR t

L

- mo

Georgia Power Company 2

JUL.14 1987 (Sc cont'd)

-J. A. Bailey, Project Licensing Manager B

W. Churchill, Esq., Shaw, Pittman, Potts and Trowbridge J/E. Joiner, Troutman, Sanders, Lockerman and Ashmore (Q< Kirkland, III, Counsel, Office of the Consumer's Utility Council LD( Feig, Georgians Against Nuclear Energy vt(. B. Margulies, Esq., Chairman, Atomic Safety and Licensing Board Panel J V. O. H. Paris, Administrative Judge Atomic Safety and Licensing Board jPanel vG.' A. Linenberger, Jr., Administrative Judge Atomic Safety and Licensing Board Panel bec: I Reis OGC 04f Miller, NRR M. Sinkule, RII LNRC Resident Inspector Document Control Desk State of Georgia l

l RII RII RII RII f

7%h g,gd w LRe[yes Y

MCNst j%VLBrowniee I g JRogge:jw j

7/(3/87 7/.3 /87 7/p /87 7//p/87 l&7

_