Monthly Operating Repts for June 1987
ML20235T976
Person / Time
Site: Turkey Point, 05000000
Issue date: 06/30/1987
From: Grant N
FLORIDA POWER & LIGHT CO.
To:
Shared Package
ML20235T937 List:
References
NUDOCS 8707220320
Download: ML20235T976 (8)


Text

. _ _ _ _ _ - _

e AVERAGE DAli,Y UNIT POWER LEVEL -

l DOCKET N0. 50-250 __

UNIT Turkey Point Unit 3 DATE July 15.1987 I C(WLETED BY N.W. Grant TELEPHONE (305) 694-4432 MONTH June 1987 DAY AVERAGE DAILY POWER LEVEL  :

(NMe-Ret) 6/ 1/87 -1 6/ 2/87 -1  !

4 6/ 3/87 -1 6/ 4/07 -1 6/ 5/87 -1 6/ 6/87 -1 6/ 7/87 -1 6/ 8/87 -1 6/ 9/87 -1 6/10/97 -1 6/11/87 -1 6/12/87 -1 6/13/87 -1 -)

6/14/87 -1  ;

6/15/87 -1 6/16/87 -1 1 1

6/17/87 -1 6/18/87 -1 6/19/87 -1  !

6/20/87 -1 6/21/87 -1 6/22/87 -1 6/23/87 -1 6/24/87 -1 6/25/87 -1 6/26/87 -1 '

6/27/87 -1 6/28/87 -1 6/29/97 -2

-2 i 6/30/87 B707220320 870615 "

PDR ADOCK 05000250 -

R PDR

._-.-__________a

OPERATING DATA REPORT

. DOCKET HD 50 - 250 DATE 7/14/87 i COMPLETED BY N. W.-GRANT l TELEPHONE 305/694/4432 I OPERATING STATUS

1. UNIT NAME! TURKEY POINT UNIT 3 l
2. REPORTING PERIOD: JUNE 1987 I 3.. LICENSED THERMAL POWER (MWT)* _____________. 2200 ,
4. NAMEPLATE. RATING (GROSS MWE)* ______________ 760 l
5. DESIGN ELECTRICAL RATING (NET MWE)* ________ 693  !
6. HAXIMUM DEPENDABLE CAPACITY (GROSS MWE)! ___ 699
HAXIMUM DEPENDABLE CAPACITY (NET'MWE)! _____ 666  !
8. IF CHANGES OCCUR IN CAPACITY' RATINGS (ITEMS NUMBER 3 THROUGH 7)

CINCE LAST REPORT, GIVE REASONS! ________________________________________

9. POWER LEVEL TO WHICH RESTRICTEDr IF ANY (NET MWE)______________2_________
10. REASONS FOR RESTRICTIONS, IF ANY: _______________________________________

MONTHLY -YTD- CUMULATIVE i

11. HOURS IN REPORT PERIOD: _________________ 720 4343 127712.6 l
12. NUMBER OF HOURS REACTOR WAS CRITICAL _____ 0.0 1428.0 87493.8 1
15. REACTOR RESERVE SHUTDOWN HOURS __________ 0.0 0.0 844.4
14. HOURS GENERATOR ON-LINE _________________ 0.0 1326.5 86593.9
15. UNIT RESERVE SHUTDOWN HOURS _____________ 0 0 121.8
16. GROSS THERMAL ENERGY GENERATED (MWH) ____ 0 2761598 179607005 i
17. GROSS ELECTRICAL ENERGY GERERATED (MWH) - 0 910710 57545561
18. NET ELECTRICAL ENERGY GENERATED (MWH) ___ -1488 856393 54479033
19. UNIT SERVICE FACTOR _____________________ 0.0 30,5 67.8
20. UNIT AVAILABILITY FACTOR ________________ 0.0 30.5 67.9
21. CAPACITY FACTOR (USING MDC NET) _________ 0.0 29.6 65.5
22. CAPACITY FACTOR (USING DER NET) _________ 0.0 28.5 61.6 4
23. UNIT FORCED OUTAGE RATE _________________ 0 19.9 8.2 1
24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS :

?5. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: 7/29/07- .

I l

  • 1

. - - - - _ _ _ _ _ - . _ - ~ _ _ _ - - . - - _ _ . I

o P . r9 y1 a4 5 r: 6 ra rr s a e e el si N

I

) oe et nF yt r5 ft i t a e) c n c DiR t

rl 0 u 3 e e ni wa ufLE r

orL JN( v c om t s o nonf I

- i t n d c e is r t

EEYE e or r td ue I

- ta e t o MTBM r r t u Gahe r ep A ADO NDEN Caome iR c hl su t i e pSR d br yt 1 T EF &tct d e ipr n1 h e6 E

L L eAn s e eh x r o tnv1 E u v nc EfEE0 rT t C a

P e

r i s a

O md 4 C e n r a .

3 g

  1. n i

t l i e nu U f o

S N

X . sm) n O

I X mcid i a

T ".3U L aSl r epu C ~ Eg E ct mn U 7 U StaE D R F  : lae l mIr E o donnt uu oe R l h R haaut Ct E a C t

eMMA) 4- -

W m PTO {e R MI23945 O l' P -

3 D H T

N A N e S O e e

s N M sn n t

w t

W T e ev p t O R iEc e

D O l R 1 P U E H R S

T I

.EiE g6 i

)

N E%g i n

U 4 la

-_j2j p m n o

E i I t ee s t c

3iE C rut r

i tr liao F R e

e 0 c y EgI tnn e a go r

0 nt

!3f 2 mni

pt el a el at 7

muifnu s

i i qa e e aEMRR e

,gH S RABCDE 2

1 1

te 3 a

D 0 7

d 8 d leu ed ce nh i t F S

o. F5 5

N 0 I I llil

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO. 50-250 UNIT Turkey Point Unit #3 DATE July 15, 1987 COMPLETED BY N. W. Grant TELEPHONE (305) 694-4432 REPORT MONTH June 1987 Unit #3 remained shutdown for refueling and scheduled maintenance.

l- .

i AVERAGE DAILY UNIT POWER LEVEL l

DOCKET N0. 50-251 UNIT Turkey Point Unit 4 DATE July 15, 1987 COWLETED BY N.W. Grant TELEPHONE __

(305) 694-4432 MNITH June 1987 DAY AVERAGE DAILY POWER LEVEL (N lie-Ret) 6/ 1/87 -11 6/ 2/87 -7 6/ 3/87 -11 6/ 4/87 -14 3 6/ 5/87 -7 6/ 6/87 -6  ;

6/ 7/87 -5 6/ 8/87 -5 6/ 9/87 ~5 6/10/87 -10  ;

6/11/87 -16 l

'6/12/87 -17 6/13/87 -15 6/14/07 -14 )

6/15/87 -14 6/16/87 -14 6/17/87 -14 .

6/18/87 -14 l 6/19/87 -15 6/20/87 -16 6/21/87 -21 6/22/87 -12 6/23/87 -10 '

6/24/87 -10 6/25/87 -12 6/26/87 -15 6/27/87 -19 6/28/87 -20 6/29/87 -19 6/30/87 -20

-i l

V -

l L i OPERATING DATA-REPORT DOCKET: NO 50 - 251- ,

DATE .

7/14/87 COMPLETED BY . N. W. GRANT:

. TELEPHONE 305/694/4432 OPERATING STATUS-g l

1. UNIT NAME*' TURKEY POINT UNIT.4
2. REPORTING PERIOD: JUNE 1987
3. LICENSED THERMAL POWER (MWT)! ______________ 2200 l 4. NAMEPLATE RATING.(GROSS MWE): ______________ .760
5. DESIGN ELECTRICAL RATING (NET MWE)* ________ 693
6. NAXIMUM DEPENDABLE CAPACITY (GROSS MWE)* ___- 699
7. MAXIMUM DEPENDABLE CAPACITY (NET MWE)! _____ 666
3. IF CHANGES OCCUR-IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7)

SINCE LAST. REPORT, GIVE REASONS! ________________________________________

9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE)________________________

10.' REASONS FOR RESTRICTIONS, IF ANY: __________________. .._,.________________

t MONTHLY -YTD-- CUMULATIVE

11. HOURS IN REPORT PERIOD: _________________ 720 4343 121444.0-
12. NUMBER - OF- HOURS REACTOR WAS CRITICAL _____ 0.0 1551.9 82235.2
13. REACTOR RESERVE SHUTDOWN HOURS __________ 0.0 0.0 166.6
14. H0fCF GENERATOR ON-LINE _________________ 0.0 1531 5 79418.6
15. UNZT RESERVE SHUTDOWN HOURS _____________ 0 0 32.1 a6. GROSS THERMAL ENERGY: GENERATED (MWH) ____ 0 3237635 168001223-
17. GROSS ELECTRICAL ENERGY GERERATED (MWH) _ 0 1064270 53549118
18. NET ELECTRICAL ENERGY ~ GENERATED (MWH)

___ -10012 988782 50671494

19. UNIT SERVICE FACTOR _____________________ 0.0 35.3 65.4
20. UNIT AVAILABILITY FACTOR ________________ O.0 35.3 65.4
21. CAPACITY FACTOR (USING'MDC-NET) _________ 0.0 34.2. 64.0
22. CAPACITY FACTOR (USING DER NET) _________ 0.0 32.9 60.2
23. UNIT FORCED OUTAGE RATE _________________ 100.0 64.7 9.5
24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS 3
25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: 7/8/87 l

r, S

o ... . . . . . . . . . . . .. .. . - . , . .

_..a

lI m.ljj 4

t .

i tr, -

7 G t

n 3 E _

t n n o

'^>

I da -

R U

,i n = 4 s m-t N e I -

P p y$~

t5 E 9 6 ot n psy a i s ani e e el e

's I

N- t or -

-U 5 1

osm t

gr iDAR t

nt rF oae) e me 0 c S 0

r u

1 3

e e ene ui rh ufIE r orL o e _

L~U

( t MO 5 T v c d snf I m _

i t n oto no Ii tst t a c e dt r S

.EEYE eoe r i a

r ep e o e nd N MTBM r t v d on Gahe i AADO Csa iR ee e n

ern a t

i e pSR t ib TNDEN &t t t .

br yt ipr n8 5

i T EF xnns h T

W EL E L eAc.

e eeee h

EiEE0 xmnv1 t e6 E

s gmi t NU 0 l NT 0 O w

s 7

i. eo gr e v ad ci t yat i

4 5 C l c uhpa o t e 4 nr ec

  1. egn d t in a n cpn i i Uapt cie n

. i o

S m t N ,ra i

n c O X X

m aSlaed c id u I

T 3U E r cpue C f P cimnR U 7

- I la StaEi D 8 P  :

asmI deu oe rna td E 9 onnt hoe R 1 heaut C L R n *,T0 tMMAO e - - - - -

E n B M123945 W u E uA B O J 3 P

D H N T N

A r S O e et 8

N M s sr i W Y n e veo p m O R c iEe t i

t D O L R a n

T F U E H R im.

u S I T

I N

TIlcEsg g6 )

n s e t 4

i la n in a

U .);j p s

e t

l p

m E mt s It e es t

i u&

c g l

I r

3l7e i e 1 1

l rT u

iao r

r t

s m eneei vI a ol r

m Fec RsyTo tal alp i 0 tnn gr i mu E28 ea t 0 mnnto ,o s nl ptelelat a i mt i i

!E$ 2  :

a, r e

7 ur gemeh muifinu s qa e e pdpt i

F aEMRROAOO e

EC RABCDErGI I 2

1 3

e t

0 7

h 8 J I le du ed t e r

o hc FS 7

)

7 7 0 I' 5 1 N t l

l ll llllllllll

l f

SUMMARY

'OF OPERATING EXPERIENCE '

i

. DOCKET NO. . 50-251 UNIT - Turkey Point Unit #4 DATE- July 15. 1987 COMPLETED BY N. W. Grant l:

' TELEPHONE (305) 694-4432 REPORT MONTH ' June 1987 See the " Unit Shutdown and Power Reductions" report.

-)

,i

\

2 l

_.