MONTHYEARML17355A4471999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Turkey Point,Units 3 & 4.With 991008 Ltr ML17355A4121999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Turkey Point,Units 3 & 4.With 990909 Ltr ML17355A3981999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Turkey Point,Units 3 & 4.With 990809 Ltr ML17355A3841999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Turkey Point,Units 3 & 4.With 990713 Ltr ML17355A3511999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Turkey Point,Units 3 & 4.With 990609 Ltr ML17355A3331999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Turkey Point,Units 3 & 4.With 990511 Ltr ML17355A2911999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Turkey Point,Units 3 & 4.With 990414 Ltr ML17355A2551999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Turkey Point Nuclear Power Plant,Units 3 & 4.With 990315 Ltr ML17355A2261999-01-31031 January 1999 Monthly Operating Repts for Jan 1999 for Turkey Point,Units 3 & 4.With 990211 Ltr ML17355A1911998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Turkey Point,Units 3 & 4.With 990112 Ltr ML18008A0461998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Turkey Point,Units 3 & 4.With 981209 Ltr ML17354B1901998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Turkey Point,Units 3 & 4.With 981112 Ltr ML17354B1311998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Turkey Point Unit 3 & 4.With 981012 Ltr ML17354B0981998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Turkey Points,Units 3 & 4.With 980915 Ltr ML17354B0771998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Turkey Point,Units 3 & 4.W/980810 Ltr ML17354B0241998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Turkey Point,Units 3 & 4.W/980709 Ltr ML17354A9711998-05-31031 May 1998 Monthly Operating Repts for Turkey Point,Units 3 & 4. W/980611 Ltr ML17354A9231998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Turkey Point,Units 3 & 4.W/980511 Ltr ML17354A8821998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Turkey Point,Units 3 & 4.W/980409 Ltr ML17354A8311998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Turkey Point,Units 3 & 4.W/980311 Ltr ML17354A7871998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Turkey Point,Units 3 & 4.W/980209 Ltr ML17354A7581997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Turkey Point,Unit 3 & 4.W/980112 Ltr ML17354A7381997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Turkey Point,Units 3 & 4.W/971215 Ltr ML17354A7211997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Turkey Point,Units 3 & 4.W/971114 Ltr ML17354A6811997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Turkey Point,Units 3 & 4.W/971009 Ltr ML17354A6221997-08-31031 August 1997 Monthly Operating Repts for Aug 1997 for Turkey Point. W/970909 Ltr ML17354A6051997-07-31031 July 1997 Monthly Operating Repts for July 1997 for TPS.W/970806 Ltr ML17354A5731997-06-30030 June 1997 Monthly Operating Repts for June 1997 for Turkey Point,Units 1 & 2.W/970710 Ltr ML17354A5261997-05-31031 May 1997 Monthly Operating Repts for May 1997 for Turkey Point Units 3 & 4.W/970612 Ltr ML17354A5071997-04-30030 April 1997 Monthly Operating Repts for April 1997 for TPS.W/970512 Ltr ML17354A4631997-03-31031 March 1997 Monthly Operating Repts for Mar 1997 for Turkey Point Units 3 & 4.W/970408 Ltr ML17354A4351997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for Turkey Point,Units 3 & 4.W/970311 Ltr ML17354A4131997-01-31031 January 1997 Monthly Operating Repts for Jan 1997 for Turkey Point,Units 3 & 4.W/970213 Ltr ML17354A3851996-12-31031 December 1996 Monthly Operating Repts for Dec 1996 for Turkey Points Units 3 & 4.W/970110 Ltr ML17354A3631996-11-30030 November 1996 Monthly Operating Repts for Nov 1996 for Turkey Point Units 3 & 4.W/961211 Ltr ML17354A3461996-10-31031 October 1996 Monthly Operating Repts for Oct 1996 for Turkey Point,Units 1 & 2.W/961113 Ltr ML17354A2981996-09-30030 September 1996 Monthly Operating Repts for Sept 1996 for Turkey Point Units 3 & 4.W/961014 Ltr ML17353A8831996-08-31031 August 1996 Monthly Operating Repts for Aug 1996 for Turkey Point Units 3 & 4.W/960912 Ltr ML17353A8571996-07-31031 July 1996 Monthly Operating Repts for July 1996 for Turkey Point Plant Units 3 & 4.W/960813 Ltr ML17353A7731996-06-30030 June 1996 Monthly Operating Repts for June 1996 for Turkey Point Units 3 & 4.W/960710 Ltr ML17353A7301996-05-31031 May 1996 Monthly Operating Repts for May 1996 for Turkey Point Units 3 & 4.W/960612 Ltr ML17353A6971996-04-30030 April 1996 Monthly Operating Repts for Apr 1996 for Turkey Point Units 3 & 4.W/960513 Ltr ML17353A6391996-03-31031 March 1996 Monthly Operating Repts for Mar 1996 for Turkey Point Units 1 & 2.W/960415 Ltr ML17353A5971996-02-29029 February 1996 Monthly Operating Repts for Feb 1996 for Turkey Point Units 3 & 4.W/960313 Ltr ML17353A5601996-01-31031 January 1996 Monthly Operating Repts for Jan 1996 for Turkey Points 3 & 4.W/960213 Ltr ML17353A5361995-12-31031 December 1995 Monthly Operating Repts for Dec 1995 for Turkey Point Units 3 & 4.W/960112 Ltr ML17353A4831995-11-30030 November 1995 Monthly Operating Repts for Nov 1995 for Turkey Point Units 3 & 4.W/undated Ltr ML17353A4441995-10-31031 October 1995 Monthly Operating Repts for Oct 1995 for Turkey Point Units 3 & 4.W/951115 Ltr ML17353A4111995-09-30030 September 1995 Monthly Operating Repts for Sept 1995 for Turkey Point Units 3 & 4.W/951012 Ltr ML17353A3541995-08-31031 August 1995 Monthly Operating Repts for Aug 1995 for Turkey Point Units 3 & 4.W/950912 Ltr 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217L9371999-10-20020 October 1999 Safety Evaluation Supporting Licensee Proposed Alternative from Certain Requirements of ASME Code,Section XI for First 10-Yr Interval Request for Relief for Containment Inservice Insp Program ML17355A4471999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Turkey Point,Units 3 & 4.With 991008 Ltr ML17355A4121999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Turkey Point,Units 3 & 4.With 990909 Ltr ML17355A3981999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Turkey Point,Units 3 & 4.With 990809 Ltr ML17355A3891999-07-20020 July 1999 LER 99-001-00:on 990623,manual Rt from 100% Power Following Multiple Control Rod Drops Was Noted.Caused by Manual Action Taken by Reactor Control Operator.Inspected & Repaired Stationary Gripper Regulating Cards.With 990720 Ltr ML17355A3841999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Turkey Point,Units 3 & 4.With 990713 Ltr ML17355A3681999-06-30030 June 1999 Revised Update to Topical QA Rept, Dtd June 1999 ML17355A3611999-06-30030 June 1999 Refueling Outage ISI Rept. ML17355A3511999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Turkey Point,Units 3 & 4.With 990609 Ltr ML17355A3331999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Turkey Point,Units 3 & 4.With 990511 Ltr ML20217B9871999-04-0808 April 1999 Changes,Tests & Experiments Made as Allowed by 10CFR50.59 for Period Covering 971014-990408 ML17355A2881999-04-0505 April 1999 COLR for Turkey Point Unit 4 Cycle 18. ML17355A2911999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Turkey Point,Units 3 & 4.With 990414 Ltr ML17355A2551999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Turkey Point Nuclear Power Plant,Units 3 & 4.With 990315 Ltr ML17355A2261999-01-31031 January 1999 Monthly Operating Repts for Jan 1999 for Turkey Point,Units 3 & 4.With 990211 Ltr ML17355A2201999-01-20020 January 1999 Refueling Outage ISI Rept. ML17355A1911998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Turkey Point,Units 3 & 4.With 990112 Ltr ML18008A0461998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Turkey Point,Units 3 & 4.With 981209 Ltr ML17354B1921998-11-18018 November 1998 LER 98-007-00:on 981020,containment Purge Supply,Valve Opened Wider than TS Limit.Caused by Improper Setting of Mechanical Stops.Incorporated Improved Standard Method of Measuring Angular Valve Position Into Sp.With 981118 Ltr ML17354B1891998-11-0909 November 1998 Simulatory Certification Update 2. ML17354B1901998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Turkey Point,Units 3 & 4.With 981112 Ltr ML17354B1591998-10-23023 October 1998 COLR for Turkey Point Unit 3 Cycle 17. ML17354B1361998-10-16016 October 1998 LER 98-004-00:on 980921,automatic Reactor Trip Occurred. Caused by Inadequate re-correlation of Intermediate Range Neutron Flux Instrumentation Reactor Trip Bistable. Enhanced Applicable Plant Procedures.With 981016 Ltr ML17354B1311998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Turkey Point Unit 3 & 4.With 981012 Ltr ML17354B0971998-09-0909 September 1998 Part 21 Rept Re Possible Machining Defect in Certain One Inch Stainless Steel Swagelok Front Ferrules,Part Number SS-1613-1.Caused by Tubing Slipping Out of Fitting at Three Times Working Pressure of Tubing.Notified Affected Utils ML17354B0981998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Turkey Points,Units 3 & 4.With 980915 Ltr ML17354B0771998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Turkey Point,Units 3 & 4.W/980810 Ltr ML17354B0341998-07-15015 July 1998 LER 98-003-00:on 980619,discovered That Auxiliary Feedwater Sys Was Inoperable Due to Inadequate Inservice Testing of Valves.Caused by Misunderstanding of Testing Criteria.Util Revised Procedures & Verified Operability of Valves ML17354B0241998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Turkey Point,Units 3 & 4.W/980709 Ltr ML17354B0171998-06-29029 June 1998 Rev 1 to PTN-FPER-97-013, Evaluation of Turbine Lube Oil Fire. ML17354A9841998-06-18018 June 1998 LER 97-007-01:on 970730,automatic Reactor Trip Occurred Due to Closure of B Msiv.Caused by Failed BFD22S Relay.Six Relays on 3A,3B & 3C MSIVs Were Replaced & Implemented Plant Change to Disable Electronic Trip Function on 3 AFW Pumps ML17354A9741998-06-0909 June 1998 LER 98-002-00:on 980513,discovered Potential LOCA-initiated Electrical Fault Which Places ECCS Outside Design Basis. Caused by Inadequate Review of Effect on non-safety Circuit failures.Re-powered PC-*-600A Relays ML17354A9711998-05-31031 May 1998 Monthly Operating Repts for Turkey Point,Units 3 & 4. W/980611 Ltr ML20248F7441998-05-31031 May 1998 Reactor Vessel Working Group,Response to RAI Regarding Reactor Pressure Vessel Integrity ML17354A9231998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Turkey Point,Units 3 & 4.W/980511 Ltr ML17354A8821998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Turkey Point,Units 3 & 4.W/980409 Ltr ML17354A8511998-03-24024 March 1998 LER 97-009-01:on 971114,discovered That CR Console Switch for 3B Sgfp Was Not in Start Position.Caused by Inadequate Procedural Guidance.Revised Procedures 3/4-OP-074,informed Personnel of Event & Performed Walkdown of CR ML17354A8441998-03-18018 March 1998 LER 98-001-00:on 980216,manual Reactor Trip Occurred Due to Loss of Turbine Control Oil Pressure W/Steam Leak in Auxiliary Feedwater Steam Supply Piping.Auxiliary Governor Maint Instructions Will Be revised.W/980318 Ltr ML17354B0001998-03-18018 March 1998 Florida Power & Light Topical Quality Asurance Rept, Dtd June 1998 ML17354A8311998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Turkey Point,Units 3 & 4.W/980311 Ltr ML17354A7871998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Turkey Point,Units 3 & 4.W/980209 Ltr ML17354A7581997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Turkey Point,Unit 3 & 4.W/980112 Ltr ML17354A7361997-12-12012 December 1997 LER 97-009-01:on 971114,identified That CR Console Switch for 3B SG Feedwater Pump Was Not in Start Position.Caused by Inadequate Procedural Guidance.Procedures 3/4-OP-074,SGFP Were revised.W/971212 Ltr ML17354A7381997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Turkey Point,Units 3 & 4.W/971215 Ltr ML17354A7211997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Turkey Point,Units 3 & 4.W/971114 Ltr ML17354A7491997-10-13013 October 1997 SG Insp Rept. ML17354A8851997-10-13013 October 1997 FPL Units 3 & 4 Changes,Tests & Experiments Made as Allowed by 10CFR50.59 for Period Covering 960408-971013. ML17354A6801997-10-0808 October 1997 LER 97-008-00:on 970909,containment Sump Debris Screens Outside Design Basis Due to Stress Damage Was Discovered. Caused by Inadequate Procedural Guidance & Personnel Error. Discrepancies Found on Screens corrected.W/971008 Ltr ML17354A6791997-10-0606 October 1997 COLR Unit 4 Cycle 17, for Turkey Point ML17354A6811997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Turkey Point,Units 3 & 4.W/971009 Ltr 1999-09-30
[Table view] |
Text
. _ _ _ _ _ - _
e AVERAGE DAli,Y UNIT POWER LEVEL -
l DOCKET N0. 50-250 __
UNIT Turkey Point Unit 3 DATE July 15.1987 I C(WLETED BY N.W. Grant TELEPHONE (305) 694-4432 MONTH June 1987 DAY AVERAGE DAILY POWER LEVEL :
(NMe-Ret) 6/ 1/87 -1 6/ 2/87 -1 !
4 6/ 3/87 -1 6/ 4/07 -1 6/ 5/87 -1 6/ 6/87 -1 6/ 7/87 -1 6/ 8/87 -1 6/ 9/87 -1 6/10/97 -1 6/11/87 -1 6/12/87 -1 6/13/87 -1 -)
6/14/87 -1 ;
6/15/87 -1 6/16/87 -1 1 1
6/17/87 -1 6/18/87 -1 6/19/87 -1 !
6/20/87 -1 6/21/87 -1 6/22/87 -1 6/23/87 -1 6/24/87 -1 6/25/87 -1 6/26/87 -1 '
6/27/87 -1 6/28/87 -1 6/29/97 -2
-2 i 6/30/87 B707220320 870615 "
PDR ADOCK 05000250 -
R PDR
._-.-__________a
OPERATING DATA REPORT
. DOCKET HD 50 - 250 DATE 7/14/87 i COMPLETED BY N. W.-GRANT l TELEPHONE 305/694/4432 I OPERATING STATUS
- 1. UNIT NAME! TURKEY POINT UNIT 3 l
- 2. REPORTING PERIOD: JUNE 1987 I 3.. LICENSED THERMAL POWER (MWT)* _____________. 2200 ,
- 4. NAMEPLATE. RATING (GROSS MWE)* ______________ 760 l
- 5. DESIGN ELECTRICAL RATING (NET MWE)* ________ 693 !
- 6. HAXIMUM DEPENDABLE CAPACITY (GROSS MWE)! ___ 699
- HAXIMUM DEPENDABLE CAPACITY (NET'MWE)! _____ 666 !
- 8. IF CHANGES OCCUR IN CAPACITY' RATINGS (ITEMS NUMBER 3 THROUGH 7)
CINCE LAST REPORT, GIVE REASONS! ________________________________________
- 9. POWER LEVEL TO WHICH RESTRICTEDr IF ANY (NET MWE)______________2_________
- 10. REASONS FOR RESTRICTIONS, IF ANY: _______________________________________
MONTHLY -YTD- CUMULATIVE i
- 11. HOURS IN REPORT PERIOD: _________________ 720 4343 127712.6 l
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL _____ 0.0 1428.0 87493.8 1
- 15. REACTOR RESERVE SHUTDOWN HOURS __________ 0.0 0.0 844.4
- 14. HOURS GENERATOR ON-LINE _________________ 0.0 1326.5 86593.9
- 15. UNIT RESERVE SHUTDOWN HOURS _____________ 0 0 121.8
- 16. GROSS THERMAL ENERGY GENERATED (MWH) ____ 0 2761598 179607005 i
- 17. GROSS ELECTRICAL ENERGY GERERATED (MWH) - 0 910710 57545561
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) ___ -1488 856393 54479033
- 19. UNIT SERVICE FACTOR _____________________ 0.0 30,5 67.8
- 20. UNIT AVAILABILITY FACTOR ________________ 0.0 30.5 67.9
- 21. CAPACITY FACTOR (USING MDC NET) _________ 0.0 29.6 65.5
- 22. CAPACITY FACTOR (USING DER NET) _________ 0.0 28.5 61.6 4
- 23. UNIT FORCED OUTAGE RATE _________________ 0 19.9 8.2 1
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS :
?5. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: 7/29/07- .
I l
. - - - - _ _ _ _ _ - . _ - ~ _ _ _ - - . - - _ _ . I
o P . r9 y1 a4 5 r: 6 ra rr s a e e el si N
I
) oe et nF yt r5 ft i t a e) c n c DiR t
rl 0 u 3 e e ni wa ufLE r
orL JN( v c om t s o nonf I
- i t n d c e is r t
EEYE e or r td ue I
- ta e t o MTBM r r t u Gahe r ep A ADO NDEN Caome iR c hl su t i e pSR d br yt 1 T EF &tct d e ipr n1 h e6 E
L L eAn s e eh x r o tnv1 E u v nc EfEE0 rT t C a
P e
r i s a
O md 4 C e n r a .
3 g
- n i
t l i e nu U f o
S N
X . sm) n O
I X mcid i a
T ".3U L aSl r epu C ~ Eg E ct mn U 7 U StaE D R F : lae l mIr E o donnt uu oe R l h R haaut Ct E a C t
eMMA) 4- -
W m PTO {e R MI23945 O l' P -
3 D H T
N A N e S O e e
s N M sn n t
w t
W T e ev p t O R iEc e
D O l R 1 P U E H R S
T I
.EiE g6 i
)
N E%g i n
U 4 la
-_j2j p m n o
E i I t ee s t c
3iE C rut r
i tr liao F R e
e 0 c y EgI tnn e a go r
0 nt
!3f 2 mni
- pt el a el at 7
muifnu s
i i qa e e aEMRR e
,gH S RABCDE 2
1 1
te 3 a
D 0 7
d 8 d leu ed ce nh i t F S
- o. F5 5
N 0 I I llil
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO. 50-250 UNIT Turkey Point Unit #3 DATE July 15, 1987 COMPLETED BY N. W. Grant TELEPHONE (305) 694-4432 REPORT MONTH June 1987 Unit #3 remained shutdown for refueling and scheduled maintenance.
l- .
i AVERAGE DAILY UNIT POWER LEVEL l
DOCKET N0. 50-251 UNIT Turkey Point Unit 4 DATE July 15, 1987 COWLETED BY N.W. Grant TELEPHONE __
(305) 694-4432 MNITH June 1987 DAY AVERAGE DAILY POWER LEVEL (N lie-Ret) 6/ 1/87 -11 6/ 2/87 -7 6/ 3/87 -11 6/ 4/87 -14 3 6/ 5/87 -7 6/ 6/87 -6 ;
6/ 7/87 -5 6/ 8/87 -5 6/ 9/87 ~5 6/10/87 -10 ;
6/11/87 -16 l
'6/12/87 -17 6/13/87 -15 6/14/07 -14 )
6/15/87 -14 6/16/87 -14 6/17/87 -14 .
6/18/87 -14 l 6/19/87 -15 6/20/87 -16 6/21/87 -21 6/22/87 -12 6/23/87 -10 '
6/24/87 -10 6/25/87 -12 6/26/87 -15 6/27/87 -19 6/28/87 -20 6/29/87 -19 6/30/87 -20
-i l
V -
l L i OPERATING DATA-REPORT DOCKET: NO 50 - 251- ,
DATE .
7/14/87 COMPLETED BY . N. W. GRANT:
. TELEPHONE 305/694/4432 OPERATING STATUS-g l
- 1. UNIT NAME*' TURKEY POINT UNIT.4
- 2. REPORTING PERIOD: JUNE 1987
- 3. LICENSED THERMAL POWER (MWT)! ______________ 2200 l 4. NAMEPLATE RATING.(GROSS MWE): ______________ .760
- 5. DESIGN ELECTRICAL RATING (NET MWE)* ________ 693
- 6. NAXIMUM DEPENDABLE CAPACITY (GROSS MWE)* ___- 699
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWE)! _____ 666
- 3. IF CHANGES OCCUR-IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7)
SINCE LAST. REPORT, GIVE REASONS! ________________________________________
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE)________________________
10.' REASONS FOR RESTRICTIONS, IF ANY: __________________. .._,.________________
t MONTHLY -YTD-- CUMULATIVE
- 11. HOURS IN REPORT PERIOD: _________________ 720 4343 121444.0-
- 12. NUMBER - OF- HOURS REACTOR WAS CRITICAL _____ 0.0 1551.9 82235.2
- 13. REACTOR RESERVE SHUTDOWN HOURS __________ 0.0 0.0 166.6
- 14. H0fCF GENERATOR ON-LINE _________________ 0.0 1531 5 79418.6
- 15. UNZT RESERVE SHUTDOWN HOURS _____________ 0 0 32.1 a6. GROSS THERMAL ENERGY: GENERATED (MWH) ____ 0 3237635 168001223-
- 17. GROSS ELECTRICAL ENERGY GERERATED (MWH) _ 0 1064270 53549118
- 18. NET ELECTRICAL ENERGY ~ GENERATED (MWH)
___ -10012 988782 50671494
- 19. UNIT SERVICE FACTOR _____________________ 0.0 35.3 65.4
- 20. UNIT AVAILABILITY FACTOR ________________ O.0 35.3 65.4
- 21. CAPACITY FACTOR (USING'MDC-NET) _________ 0.0 34.2. 64.0
- 22. CAPACITY FACTOR (USING DER NET) _________ 0.0 32.9 60.2
- 23. UNIT FORCED OUTAGE RATE _________________ 100.0 64.7 9.5
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS 3
- 25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: 7/8/87 l
r, S
o ... . . . . . . . . . . . .. .. . - . , . .
_..a
lI m.ljj 4
t .
i tr, -
7 G t
n 3 E _
t n n o
'^>
I da -
R U
,i n = 4 s m-t N e I -
P p y$~
t5 E 9 6 ot n psy a i s ani e e el e
's I
N- t or -
-U 5 1
osm t
gr iDAR t
nt rF oae) e me 0 c S 0
r u
1 3
e e ene ui rh ufIE r orL o e _
L~U
( t MO 5 T v c d snf I m _
i t n oto no Ii tst t a c e dt r S
.EEYE eoe r i a
r ep e o e nd N MTBM r t v d on Gahe i AADO Csa iR ee e n
ern a t
i e pSR t ib TNDEN &t t t .
br yt ipr n8 5
i T EF xnns h T
W EL E L eAc.
e eeee h
EiEE0 xmnv1 t e6 E
s gmi t NU 0 l NT 0 O w
s 7
- i. eo gr e v ad ci t yat i
4 5 C l c uhpa o t e 4 nr ec
- egn d t in a n cpn i i Uapt cie n
. i o
S m t N ,ra i
n c O X X
m aSlaed c id u I
T 3U E r cpue C f P cimnR U 7
- I la StaEi D 8 P :
asmI deu oe rna td E 9 onnt hoe R 1 heaut C L R n *,T0 tMMAO e - - - - -
E n B M123945 W u E uA B O J 3 P
D H N T N
A r S O e et 8
N M s sr i W Y n e veo p m O R c iEe t i
t D O L R a n
T F U E H R im.
u S I T
I N
TIlcEsg g6 )
n s e t 4
i la n in a
U .);j p s
e t
l p
m E mt s It e es t
i u&
c g l
I r
3l7e i e 1 1
l rT u
iao r
r t
s m eneei vI a ol r
m Fec RsyTo tal alp i 0 tnn gr i mu E28 ea t 0 mnnto ,o s nl ptelelat a i mt i i
!E$ 2 :
a, r e
7 ur gemeh muifinu s qa e e pdpt i
F aEMRROAOO e
EC RABCDErGI I 2
1 3
e t
0 7
h 8 J I le du ed t e r
o hc FS 7
)
7 7 0 I' 5 1 N t l
l ll llllllllll
l f
SUMMARY
'OF OPERATING EXPERIENCE '
i
. DOCKET NO. . 50-251 UNIT - Turkey Point Unit #4 DATE- July 15. 1987 COMPLETED BY N. W. Grant l:
' TELEPHONE (305) 694-4432 REPORT MONTH ' June 1987 See the " Unit Shutdown and Power Reductions" report.
-)
,i
\
2 l
_.