ML20235N925

From kanterella
Jump to navigation Jump to search
Discusses Containment Integrated Leak Rate Test (Cilrt) Schedule,Per Failed May 1987 Test Noted in Insp Rept 50-325/87-15.Util Will Maintain Current Cilrt Interval of 40 +/- 10 Months Unless Two Successive Failures Occur
ML20235N925
Person / Time
Site: Brunswick Duke Energy icon.png
Issue date: 09/29/1987
From: Zimmerman S
CAROLINA POWER & LIGHT CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
NLS-87-199, NUDOCS 8710070113
Download: ML20235N925 (1)


Text

- - - -

p:

.tjA ey CD&L Carolina Power & Light Company SERIAL: NLS-t7-199 -

L' SEP 2 9 337 10CFR50, Appendix J '

1 United States Nuclear R'egulatory Commission -

R ATTENTION: Document Control Desk Washington,'DC 20555 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NO. I DOCKET NO.'50-325/ LICENSE NO. DPR-71

CILRT. SCHEDULE Gentlemen:'

Carolina Power & Light Company (CP&L) performed,a Containment Integrated Leak Rate Test (CILRT)in May 1987 on the Brunswick Steam Electric Plant, Unit No.1

~(BSEP-1).. This test was classified as "falled" in NRC Inspection Report 50-325/324/87-15.. Appendix J, Section Ill.A.6.(a) of 10CFR50 requires NRC review and approval of the schedule'for future CILRT if any Type A test is failed. The Company plans to maintain the current CILRT interval of 40 t 10 months at BSEP-1 unless two successive failures occur, at which time an 18-month, or every refueling outage, interval will begin.

If ou have any questions concerning this submittal, please contact Mr. Stephen D. Floyd at 919) 836-6901.

Yours very truly, 2,u x

. R. Zi imerman 6.ager Nuclear icensing Section SRZ/ BAT /lah. (528B AT) cc: