} One First National Plaza. Chicago. Illinois Commonwealth Edison
/
r I
J) ~ddress Reply to: Post Office Box 767
'\\
' ~ '
L/ Chicago, Illinois 60690 0767 FeDruary 22, 1989 4
Dr. Thomas E. Murley, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555
Subject:
Quad Cities Station Unit 1
" Transmittal of Guidelines for Neutron Radioassay Measurement at Quad Cities Unit 1 Spent Fuel Storage Pool" U RC Doc k e t lip _,._,50-2 54 Reference Letter from M.S. Turbak to A.B. Davis dated July 22, 1987.
Dear Dr. Murley:
In the above referenced letter, Commonwealth Edison provided information to your staff regarding the Reload High Density Fuel Racks in the Quad Cities Unit 1 Fuel Pool.
This transmittal was made in response to Boroflex degradation observed at the Point Beach Nuclear Power Station.
Attached, please find a copy of the " Quad Cities Neutron Radioassay Measurement Guidelines", dated January 1989 for your information.
Commonwealth Edison plans to begin employing the program guidelines sometime during the first quarter of 1989. The results from the neutron radioassay measurements should be available during the second quarter of 1989.
Commonwealth Edison is willing to provide this information to your staff for their information at that time.
Please direct any questions you may have regarding this matter to this office.
V
'rh ygo r I
d. hg/A -
hg4 I. E P
PNU Nuclear Licensing administrator 1m Attachment cc:
A.B.
Davis - Regional Administrator, RIII (w/o Att.)
T.
Ross - Project Manager, NRR Quad Cities Senior Resident Inspector (w/o Att.)
0I l
0 5549K l {