1:n+.
JUL 131987 i
In Reply Refer To:
Docket:
50-382 Louisiana Power & Light Company ATTN:
J. G. Dewease, Senior Vice President Nuclear Operations 317 Baronne Street New Orleans, Louisiana 70160 Gentlemen:
The Region IV staff has completed review of the emergency plan changes which you submitted to this office by letter dated June 26, 1987.
The emergency plan changes do not appear to decrease the effectiveness of the Waterford 3 Emergency Plan.
The following areas were clarified and better defined in revision 11 to the Emergency Response Plan.
Under definitions 1.1.17, Emergency Coordinator, you included 0FF-SITE notifications.
Section 3.1.2.1 Emergency Coordination On-Site, you added full authority and responr.ibility.
1 l
Section 5.1.2.2.2, third paragraph, off-site notifications were added to l
of f-site protective action recommendations.
Section 6.6.1.1.b Accountability, paragraph 2 states accountability is performed by procedure for each facility's personnei.
It is evident from review of personnel task assignments for the control room and the TSC that personnel have been assigned responsibility for accountability.
l Section 5.1.2.3.1.a.6., included making off-site notifications.
If there are any questions in regard to this letter please contact Charles A. Hackney at (817) 860-8188.
Sincerely, J. P. Jaudon for J. E. Gagliardo, Chief Reactor Project Branch cc:
(see next page)
+. _..
C:Sh M
RIV: EPA C:NMEP CAHackney;ap WLFisher JPJuidhn
/. C : RPB..
AI 87-233 WEGagl Udo J / k/87 7/l0/87 f lp/87
]/lg87'
'd gr m 818Mr N
F
l
~.
JUL i 31987
~
In Reply Refer To:
Docket:
50-382 Louisiana Power & Light Company ATTN:
J. G. Dewease, Senior Vice President Nuclear Operations 317 Baronne Street New Orleans, Louisiana 70160 i
Gentlemen:
The Region IV staff has completed review of the emergency plan changes which you submitted to this office by letter dated June 26, 1987. The emergency plan changes do not appear to decrease the effectiveness of the Waterford 3 Emergency Plan. The following areas were clarified and better defined in revision 11 to the Emergency Response Plan.
(
Under definitions 1.1.17, Emergency Coordinator, you included 0FF-SITE notifications.
Section 3.1.2.1 Emergency Coordination On-Site, you added full authority and responsibility.
Section 5.1.2.2.a. third paragraph, off-site notifications, were added to off-site protective action recommendations.
Section 6.6.1.1.b Accountability, paragraph P. states accountability is performed by procedure for each facility's personnel.
It is evident from review of personnel task assignments for the control room and the TSC j
l that personnel have been assigned responsibility for accountability.
l Section 5.1.2.3..l.a.6., included making of f-site notifications.
1 If there are any questions in regard to this letter please contact l
Charles A. Hackney at (817) 860-8188.
l l
l Sincerely, j
J. P. Jaudon for l
l J. E. Gagliardo, Chief Reactor Project Branch cc:
(see next page)
~.. - -
RIV:EPAM C:NMED C:.R
, C : RPB.-
A1 87-238
? //e/87 7 /10/87
/ /p/87 g/jys7~jdo CAHackney;ap WLT;isher JPJtidkn
' glEGag'1 J
l eJ wnWa f?%%2 Yg
(
i F
L
d 4
Louisiana Power & Light Company,
cc:
Louisiana Power & Light Company ATTN:
G. E. Wuller, Onsite Licensing Coordinator P. O. Box B Killona, Louisiana 70066 Louisiana Power & Light Company ATTN:
N. S. Carns, Plant Manager P. O. Box B Killona, Louisiana 70066 Middle South Services ATTN:
Mr. R. T. Lally P. O. Box 61000 New Orleans, Louisiana 70161 Louisiana Power & Light Company ATTN:
K. W. Cook, Nuclear Safety and Regulatory Af f airs Manager 317 Baronne Street P. O. Box 60340 l
New Orleans, Louisiana 70160 Louisiana Radiation Control Program Director
'6chtoDMB(A045) bec distrib. by RIV:
RPB DRSP Resident Inspector-OPS R. D. Martin, RA Resident Inspector-CONST.
Section Chief (RPB/C)
RPSB MIS SYSTEM RIV File D. Weiss, RM/ALF
{
RITS Operator R. Pirfo, DGC R. G. Taylor, RPB/C RSB Inspector Section Chief L. A. Yandell R. L. Bangart R. E. Hall l
Project Inspector, RPB l
l J. Wilson, NRR Project Manager G. Bates D. B. Matthews 1
[