Lists Actions Described in 870420 Response to NRC Draft SER of Procedure Generation Package Detailed Reviews That Would Be Performed & Enhancements Made to Emergency Operating Procedures (Eop).Eop Changes Will Result from Plant Mods
ML20234F129
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 12/31/1987
From: Shelton D
TOLEDO EDISON CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
1465, NUDOCS 8801110343
Download: ML20234F129 (2)


Text

...

TOLEDO

%s EDISON DONAt D C..SHELTCN v w m -Nue s Docket No. 50-346 W 818 " '388 License No. NPF-3 Serial No. 1465 December 31, 1987 i

United States Nuclear Regulatory Commission Document Control Desk Washington, D. C.

20555

Subject:

Procedure. Generation Package' Preview Schedule Gentleman:

Toledo Edison's response dated April 20, 1987, (Serial 1368) to NRC Draft Safety Evaluation Report of the Davis-Besse Procedure Generation Package (PGP) detailed reviews that would be performed and' enhancements made to our Emergency Operating Procedures (E0P).

The actions es described in our April 20, 1987 submittal:are as follows:

Perform a comparison of the Davis-Besse E0P with the requirements of the B&W generated Technical Basis Document-(TBD).

Feview the Davis-Besse E0P with the revised Writers Guide.

Enhance instructions to operators on the use of hot leg RTDs and incore T/C when. determining subcooling margin.

Enhance instructions to operators on the use of hot and coldeg.

RTDs and incore T/Cs.fcr the determination of natural circu1L_ ion.

Evaluate the use of S/G drains and' Tube Rupture Control Criteria.to

~

maintain the S/G 1evel below the main steam line connection during --

tube rupture.

These actions were originally projected to be completed for~early-1988-revisions. :However, many plant modifications are being implemented at Davis-Besse during the upcoming fifth refueling outage (RF05) scheduled to begin in February 1988. Major E0P changes will result from these modifications'and, combined with.the PGP revisions,Jare significant-changes 8801110343 871231 P

-/.'

l PDR ADOCK 05000346 0

P

-PDn a

1 THE TOLEDO EDISON COMPANY EDISON PLAZA 300 MADISON AVENUE

- TOLEDOf OHIO 43652

-I Docket No. 50-346 License No. NPF-3 Serial No. 1465 Page 2 that will require validation and training at the B&W simulator in Lynchburg. As a result the review, approval, validation and training is I

now scheduled to be completed prior to startup from RF05. This schedule

]

has been discussed with Mr. A. W. DeAgazio of your staff.

l Very tr 3 yours, 4

t JS:bam cc: DB-1 Resident Inspector A. B. Davis, Regional Administrator A. W. DeAgazio 1