Informs That Util Will Submit 120-day Response to GL 97-01 by 970814.Addl Time Required to Determine Insp Scope & Schedule for San Onofre,Units 1 & 2
ML20217G942
Person / Time
Site: San Onofre  
Issue date: 08/06/1997
From: Rainsberry J
SOUTHERN CALIFORNIA EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GL-97-01, GL-97-1, NUDOCS 9708080123
Download: ML20217G942 (1)


Text

_ _ _ _ _ -

0AtIIOR%i A i

l

l. L Raimberry i

Manager, riant !.icensing An LDISON f VTlK% 4 fitn 41'" Omnrany August 6, 1997 U. S. Nuclear Regulatory Commission Attention: Document Control-Desk Washington, D.C..

20555 Gentlemen:

Subject:

Docket Nos. 50-361 and 50-362 120 Day Response to Generic Letter 97-01: " Degradation of Control Rod Drive Mechanism Nozzle and Other Vessel Head Penetrations" San Onofre Nuclear Generating Station Units 2 and 3

)

l Southern California Edison (Edison) requires additional time to finalize the 120-day response to Generic Letter (GL) 97-01 for San Onofre Nuclear GeneratingStation(SONGS)Ur.its2and3.

Edison will submit the 120 day response by August 14, 1997.

The additional time is required to determine the inspection scope and schedule for San Onofre Units 2 and 3.

If you have any questions or would like additional inform: tion, please let.me-know.

Sincerely, MAE For J. L. Rainsberry 0

Manager, Plant Licensing l

cc:

E. W. Merschoff, Regional Administrator, NRC Region-IV K. E. Perkins, Jr., Director, Walnut Creek Field Office, NRC Region IV J. A.-Sloan, NRC Senior Resident Inspector, San Onofre Units 2 & 3 M. B. Fields, NRC Project Manager, San Onofre Units 2 and 3 9700000123 970006 C

PDR ADOCK 05000361 P

PDR

- a ITe uc! car Generating Station

, San Clemente CA 92674-0128 714 368 7420