Forwards Proposed ACRS Schedule for Reviewing AP600 Design Option 1,per 971028 Discussion W/T Quay of NRR
ML20217B065
Person / Time
Site: 05200003
Issue date: 11/12/1997
From: Larkins J
Advisory Committee on Reactor Safeguards
To: Roe J
NRC (Affiliation Not Assigned)
References
ACRS-GENERAL, NUDOCS 9803250356
Download: ML20217B065 (6)


Text

'

/ 'o UNITED STATES

' 8' g o NUCLEAR REGULATORY COMMISSION y I ADVISORY COMMITTEE ON REACTOR SAFEGUARDS a wAsmuoTow. o. c. mss f

esa,*

i November 12,1997 j J2-3 MEMORANDUM TO: Jack W. Roe, Acting Director Division of Reactor P n1 Man gement, NRR FROM: John T. Larkins, de i!e ire or Advisory Committee on Reactor Safeguards

SUBJECT:

PROPOSED ACRS SCHEDULE FOR REVIEWING THE AP600 DESIGN This memorandum documents the discussion I had with Theodore Quay of your staff on October 28,1997, regarding the proposed ACRS schedule for reviewing the AP600 design. During the October 9,1997 meeting between representatives of the i Westinghouse Electric Corporation and the staff, the issue was raised as to whether the ACRS could complete its review of the AP600 design in less than three months after receiving the proposed Final Safety Evaluation Report (FSER).

The proposed ACRS schedule for completing its review of the AP600 design is given below:

. Ootion 1: if the staff provides the proposed FSER to the ACRS by May 1, 1998, the ACRS will expedite its review and try to issue a final report to the Commission in July 1998.

. Option 2: If the staff provides the proposed FSER to the ACRS by June 17,1998, the ACRS will strive to complete its review and issue a report to the Commission in September 1998. /

/

For ACRS to meet either schedule, the staff must provide a complete and high-quality FSER with no safety-significant open items, and Westinghouse and the staff must provide the necessary support during Subcommittee and fullfommittee meetings. If O 3 there is a delay in providing the FSER, the ACRS review wiri be delayed.

The proposed schedule, for both options, for ACRS meetings to review various chapters of the AP600 Standard Safety Analysis Report (SSAR) and associated draft FSER chapters is included in the attachment. The ACRS plans to

> 1

. 3 v d u '1 9803250356 971112 -

PDR ACRS CENERAL PDR #

t*

2 issue interim reports following its review of SSAR chapters, and a final report following its review of the FSER.

Atttachment: As stated -

cc: L. J. Callan, OEDO J. Mitchell, OEDO J. Hoyle, SECY S. J. Collins, NRR T. Quay, NRR T. Kenyon, NRR

e' .

ATTACHMENT 4

PROPOSED ACRS SCHEDULE FOR REVIEWING THE AP600 DESIGN OPTION 1 ASSUMPTION: The staff's proposed final Safety Evaluation Report (FSER) will be provided to the ACRS by May 1, 1998. The relevant draft FSER chapters will be made available to the ACRS before each Subcommittee meeting.

Advanced Reactor Designs Subcommittee Meetings February 3 - February 4. 1998 Chap. 1: Introduction and General Description of the Plant Chap. 4: Reactor Chap. 5: Reactor Coolant System and Connected Systems Chap. 7: Instrumentation and Controls Chap. 8: Electrical Power Chap. 9: Auxiliary Systems Chap. 11: Radioactive Waste Management Chap. 13: Plant Operations Chap. 17: Quality Assurance i Chap. 18: Human Factors Engineering

[ February 1998 Interim ACRS Report)

March 31 - April 1.1998 Chap. 6: Engineered Safety Features Chap. 9A: Fire Protection Analysis Chap. 10: Steam and Power Conversion System Chap. 12: Radiation Protection  !

Chap. 16: Technical Specifications j

[ April 1998 Interim ACRS Report)

< L-ATTACHMENT d

~May 12-13. 1998 Chap. 2: Site Characteristics Chap. 3: Design of Structures. Components. . Equipment, and Systems.

Chap. 14: Initial Test Program Chap. 15: Accident Analyses Probabilistic Risk Assessment ITAAC RTNSS'

[ June 1998 Interim ACRS Report]

May 14.~1998 - FSER Chapters 1-5 June 17-18, 1998 - FSER Chapters 6-15 July 6-7,1998 - FSEPs Chapters 16-18 and Probabilistic Risk Assessment-July. 8.1998 - Full Committee Review of the FSER July 1998 - Final ACRS Report i

)

1

/ L- j

,o

. . )

ATTACHMENT l 1

PROPOSED ACRS SCHEDULE FOR REVIEWING THE AP600 DESIGN i OPTION 2

)

. ASSUMPTION: The staff's proposed Final Safety Evaluation Report (FSER) will I

-be provided to the ACRS by June 17. 1998. The relevant draft FSER chapters will be made available to the ACRS before each Subcommittee meeting.

Advanced Reactor Designs Subcommittee Meetings February 3-4. 1998 Chap. 1: Introduction and General Description of the Plant Chap. 4: Reactor Chap. 5: Reactor Coolant System and Connected Systems Chap. 7: Instrumentation and Controls Chap. 8: Electrical Power Chap. 9: Auxiliary Systems Chap. 11: Radioactive Waste Management Chap. 13: Plant Operations Chap. 17: Quality Assurance Chap. 18: Human Factors Engineering

[ February 1998 Interim ACRS Report)

March 31-April 1. 1998 >

Chap. 6: Engineered Safety Features Chap. 9A: Fire Protection Analysis Chap. 10: Steam and Power Conversion System Chap. 12: Radiation Protection Chap. 16: Technical Specifications

[ April 1998 Interim ACRS Report)

May 12-13. 1998 Chap. 2: Site Characteristics

. Chap. 3: Design of Structures, Components. Equipment, and Systems Chap. 14: Initial Test Program

a y , s.

' ATTACHMENT Chap.'15: Accident Analyses Probabilistic Risk Assessment ITAAC' RTNSS

[ June 1998 Interim ACRS Report)

July 7.1998 - FSER Chapters 1-5

' July 21-22,1998 - FSER Chapters 6-15 August 31 - September 1.1998 - FSER Chapters 16-18 and Probabilistic Risk Assessment September 2, 1998 - Full Committee Review of the FSER September 1998 - Final ACRS Report

)