)ef'1/

DOCKETED UNITED STATES OF AMERICA U3hRC NUCLEAR REGULATORY COMMISSION

% MAR 19 P3 :22 COMMISSIONERS:

OFR -

Shirley Ann Jackson, Chairman g:.-'

~

N'F Greta Dicus Nils J. Diaz -

Edward McGaffigan, Jr.

ggg g 9 9 -

)

In the Matter of

)

)

U.S. ENRICHMENT CORPORATION

) ~ ~ Docket No. 70-7001

)

(Paducah, Kentucky)

)

)

CLI-98-02 MEMORANDUM AND ORDER I. Introduction On December 16,1997, the U.S. Nuclear Regulatory Commission published, in the l

Federal Reaister (62 FR 65823), notice of amendment and partial denial of amendment application to the Certificate of Compliance GDP-1 for the U.S. Enrichment Corporation (USEC), Paducah Gaseous Diffusion Plant (referred to hereafter as Paducah or PGDP),

located in Paducah, Kentucky. USEC, or any person whose interest may be affected and who had submitted written comments in response to the Federal Reaister (62 FR 41101) notice which noticed the amendment request was eligible to file a petition to the Commission requesting review of the Director's Decision within 15 days after publication of the Director's Decision.10 C.F.R. @ 76.62(c).

NRC received one petition for review of the Director's Decision. This memorandum and order addresses the petition for review and the issues raised in the petition. For reasons set forth below, the petition is denied in its entirety.

9903200039 980319 PDR ADOCK 07007001 r1 C

PDR gOp

i 0

2

11. Petition for Review By letter dated December 30,1997, USEC, holder of Certificate of Compliance for the PGDP (GDP-1), petitioned for Commission review of the Director's Decision. The petition was docketed at NRC on December 30,1997.

Ill. Backaround The September U,1995 application from USEC for certification of the PGDP contained an analysis of the potentialimpacts of earthquakes that was based on a 1985 U.S. Department of Energy (DOE) Safety Analysis Report (SAR), DOE was in the process of conducting new studies and analyses to update the 1985 SAR at the time the application was submitted to tac NRC, DOE concluded that two (Buildings C-331 and C-335) of four large processing buildings could suffer structural failure at relatively low seismic demand, beginning at 0.05g peak ground acceleration (PGA). DOE concluded that damage could include roof and floor collapse, and concomitant equipment damage. The principal failure mechanism identified was seismic displacement, beyond tolerance, of sliding beam roof and floor sections supported by rocker arms. DOE considered the potential for large uranium hexafluoride releases coincident with a I

loss of structural confinement to be an unreviewed safety question and outside the existing safety basis for plant authorization. (DOE letter to USEC, September 22,1995.) To address these concems, DOE issued a " Directive for information" to USEC on September 22,1995.

Because DOE considered USEC's initial response to be unacceptable (DOE letter to USEC, October 31,1995), DOE issued a " Directive for Corrective Action and Compensatory Actions for

)

Operations in Buildings C-331 and C-335" to USEC on October 31,1995. This second Directive required USEC to "... develop and initiate action (s) to ensure that the response of the i

3 rocker supported floor sections of each building can withstand the expected seismic demand..."

DOE subsequently performed the seismic analyses and conceptual design of the modifications to the buildings, and is funding activities associated with the seismic upgrades, including installation of the proposed modifications. (USEC letter to NRC, June 30,1997.)

The Commission was informed by the staff in SECY 96-054 and during the March 22, 1996 Commission briefing concerning the status of certification, that DOE had identified structural weaknesses in certain buildings at Paducah and that USEC would implement compensatory measures while carrying out plant structural modifications to raise the seismic capacity of these buildings (hereinafter referred to as " structural modifications"). The Commission was informed that the staff intended to certify on the seismic issue, based on: (1) a firm commitment to upgrade to withstand a postulated 250-year earthquake event; (2) adequate justification for continued operation; (3) continuation of compensatory measures; and (4) reevaluation during future certification reviews. In SECY 96-180 and in a Commission meeting held on August 28,1996, the Commission was informed that the structural modifications were i

scheduled to be completed by late 1997 and that interim compensatory measures would continue until these structural modifications are installed. The Commission was also informed about potential weaknesses in the seismic hazard analysis. The seismic hazard analysis l

performed by DOE to support certification did not use the most recent seismic data in the I

analysis which, if included, could make the resulting evaluation basis earthquake greater than that used by DOE. Therefore, a seismic hazard analysis using updated data was required to be performed. NRC specified that if the new seismic hazard analysis reflected greater hazards than DOE's current analysis, the need for further plant modifications would be subject to backfit evaluation. Because this issue would not be resolved by the time of initial certification, the issue was required to be addressed in the Compliance Plan. DOE agreed and prepared

r l

?

~

4 Compliance Plan issue 36," Seismic Capability of Buildings C-331 and C-335." USEC submitted Compliance Plan issue 36 in a letter dated July 18,1996. The Compliance Plan called for the structural modifications to be completed by December 31,1997, and continuation of interim, compensatory measures. The Compliance Plan also required USEC to submit the final design plans to NRC. The Compliance Plan included a commitment for USEC to perform a new seismic hazard analysis by December 1,1997.

By letter dated April 23,1997, USEC submitted an amendment request to obtain NRC approval of three Unreviewed Safety Questions (USQs) associated with the seismic upgrades and to extend the completion date until 15 months after approval of the amendment request.

On July 31,1997, USEC revised its amendment request to further delay completion of the seismic modifications until 18 months after: (1) USEC submits, and NRC approves, the final design of the structural modifications; (2) NRC completes its review of the three USQs; (3) NRC completes its review of the seismic analysis included in the upgraded Safety Analysis Report (SARUP); and (4) NRC approves an updated seismic hazard analysis. In the July submittal, USEC also requested NRC approval of: 1) the resolution of three USQs it had identified; 2) revising the Compliance Plan to reference only sheltering concerning emergency preparedness;

3) revising the Compliance Plan to reflect that the final design of the modifications is complete; and 4) revising the Compliance Plan to reference a report prepared by Lawrence Livermore National Laboratory (LLNL) entitled "Paducah Gaseous Diffusion Plant Seismic Risk Study (UCRL-ID-126275)", hereinafter referred to as the LLNL report, or the LLNL study. DOE had contracted with LLNL to produce this study of the PGDP seismic risk to verify the justification for continued operation (JCO) on the Compliance Plan seismic issue.

NRC and DOE signed a Memorandum of Understanding (MOU), which was published in t

- the Federal Reaister on November 5,1997 (62 FR 59910). The NRC/ DOE MOU requires that

5 all modifications to the Compliance Plan be approved by DOE before submitting any such changes to NRC. By letter dated October 23,1997, USEC was informed of the need to obtain DOE approval before submitting Compliance Plan changes. However, in that letter, NRC stated that for all pending Compliance Plan amendments, it would coordinate with DOE in lieu of requiring their resubmittal, and delaying consideration of such pending amendments, while USEC sought DOE approval. In accordance with this process, NRC discussed the proposed Compliance Plan changes that resulted from the NRC staff's review of USEC's amendment request with DOE. DOE supported NRC's position on the changes (NRC letter to USEC, December 8,1997) and indicated that it believes that the modifications should be made without further delay. DOE also described the limitations of the LLNL report submitted by USEC.

The Director's Decision on the amendment appeared in the Federal Reoister on December 16,1997 (62 FR 65823). The decision announced the intention to approve in part, and deny in part, USEC's request. The decision approved resolution of the USQs, approved revising the Compliance Plan to reference only sheltering; approved revising the Compliance Plan to reflect that the final design of the modifications is complete; denied revising the Compliance Plan to reference a report prepared by LLNL; and denied delaying completion of the structural modifications until 18 months after the staff completes reviews of all other seismic material requested by USEC. Instead, the staff established a completion date for the structural modifications of June 30,1999 (approximately 18 months after issuance of the Director's Decision).

On December 30,1997, USEC submitted to the Commission a " Petition Requesting l

Commission Review of Director's Decision Denying in Part USEC Certificate Amendment Request Regarding Paducah Plant Seismic Upgrades." In the petition, USEC requested that the Commission review only that portion of the Director's Decision which denied parts of l

l L

I

6 USEC's July 31,1997 application for amendment to its Certificate of Compliance for the PGDP.

Specifically, USEC requested that the Commission extend the deadline for completion of the structural modifications until 18 months after NRC has completed the reviews and approvals described in USEC's July 31,1997 certificate amendment application.

j IV. Analysis and Response to Issues Raised in the USEC Petition J

The USEC petition enumerated five supporting reasons for submitting the petition, which we will refer to as USEC lssues 1 through 5. In USEC issues 2,3,4, and 5, the petitioner

]

requests that NRC complete a review of seismic information submitted by USEC before installation of the modifications is begun. The petitioner requests NRC review of four documents. The effects of a delay in installing the structural modifications, that would result from reviewing all four documents, are addressed in USEC lssue 6, separately from other issue-specific information. USEC issues 1 through 6 are addressed below.

A.

USEC lssue 1: The Structural Modifications Were Originally Ordered by DOE Based on l

l Incomplete Technical Information.

l The petitioner argues that the U.S. Department of Energy (DOE) issued a directive to install the modifications based on work being performed as part of its site-wide Safety Analysis l

Report Upgrade (SARUP) effort before it had performed the SARUP consequence analysis to determine what the impact of such a structural failure might be on workers or the offsite public.

The petitioner further argues that DOE had not yet completed all its planned SARUP structural analyses to fully assess the seismic capacity of the other buildings at the PGDP site before

7 ordering the modifications.. The petitioner believes that, although the result of a seismic hazard analysis, required by NRC, indicates that consequences in excess of the existing Safety Analysis Report (SAR) are possible, they do not justify installation of the structural modifications l

r being planned based on the recently completed seismic risk analysis conducted by LLNL.

The fact that DOE had not completed all of its planned SARUP structural analyses to fully assess the seismic capacity of the other buildings at PGDP, before ordering the modifications, has no bearing on the currently planned modifications. DOE had completed the seismic structural analyses for the buildings in question - C-331 and C-335. The DOE review of the SARUP information indicated that the two buildings would begin to fail at an 0.05g earthquake (approximately 80-year return period) instead of failing at an 0.15g earthquake (with a return period of approximately 250 years)', as assumed in the current SAR. Therefore, DOE issued a Directive to USEC that ordered USEC to modify the buildings. DOE has since completed the SAR upgrade analyses and DOE's belief that these modifications are needed I

remains unchanged (DOE letter to NRC, January 5,1998). It is possible that the NRC review of the SARUP could result in the requirement for modifications to other buildings and equipment at l

PGDP. However, the need for additional structural modifications to other buildings does not I

alter the need for the structural modifications to Buildings C-331 and C-335.

USEC also argues that the LLNL report provides justification for not installing the structural modifications at all. In a January 5,1998 letter to NRC, DOE documented that it i

contracted with LLNL to perform a review of the PGDP seismic analysis to verify the content of 1

l the JCO that was required for the Compliance Plan seismic issue. The review was intended as

' The annual probability of occurrence of an 80-year-return-period earthquake is 1.25 X 10 ; the annual probability of occurrence of a 250-year-return-period earthquake is 2

4 X 1 0.a,

I 8

a scoping analysis to provide a general overall risk perspective and was performed to ensure that PGDP could continue to operate in a safe manner for a limited period of time until the appropriate modifications could be performed. in the letter, DOE states that the LLNL review was never intended to support continued operation for an indefinite period of time without the proposed modifications, and the methodology and rigor used in the study were inconsistent with i

this intention. DOE reviewed the report and identified four limitations. We conclude that the -

l l

LLNL report contains limitations and does not support eliminating installation of the modifications. The LLNL report and its li;nitations are further discussed in Section C, USEC Issue 3.

I We find that the petitioner has not substantiated that DOE's technical basis for ordering the structural modifications was based on incomplete information. Therefore, we reject this i

basis for challenging the Director's Decision.

B.

USEC lssue 2: The Updated Seismic Risk Analysis Which Was Required by NRC Indicates a Higher Evaluation Basis Earthquake (EBE) Than the Modifications are Based Upon.

The petitioner is concerned that NRC may require a level of seismic risk management to be applied to the C-331 and C-335 buildings that will not be met by the planned structural modifications. The planned structural modifications were designed to meet an earthquake with a peak ground acceleration of 0.159, which, at the time of certification, was thought to have a recurrence interval of approximately 250 years. The results of a recently completed USEC seismic hazard study for the Paducah site indicate that a 250-year-recurrence-period l

earthquake has a peak ground acceleration of 0.165g. The petitioner believes that any j

f.

9 l

modifications should await an NRC determination of a final earthquake acceleration value because the cost of backfitting more stringent requirements to these modifications after they are oegun may significantly exceed the cost of incorporating them into the initial design and could force substantial rework.

This issue was already addressed during the certification process. One of NRC's concerns during certification was that DOE had not used the most recent seismic data to conduct the seismic hazard analysis (DOE used the 1985 data -- more recent information after 1985 was not considered). NRC believed that the actual seismic event might be gceater than the 0.15g used by DOE. For this reason, it insisted that the Compliance Plan include a USEC commitment to perform a new seismic hazard analysis by Deceniber 1,1997. During USEC/ DOE discussions of the draft Compliance Plan, USEC suggested delaying the modifications until after the new seismic hazard analysis was complete. Both DOE and NRC found this approach to be unacceptable. NRC agreeo that if the new seismic hazard analysis reflected greater hazards than DOE's current analysis, the need for further plant modifications would be subject to backfit evaluation.

The effect of the delay in installing the structural modifications caused by the additional time required to review the seismic hazard study, in conjunction with all the other seismic documents requested by USEC, is discussed in USEC lssue 6.

Petitioner's concern that the cost of backfitting to a higher earthquake acceleration value, after the current modifications are begun, may exceed the cost of incorporating them into the initial design, is without merit since any modifications necessary to meet an incremental increase in esithquake level, above the compliance level of 0.15g for which the modifications are designed, will be subject to backfit evaluation, in accordance with NRC regulations, where cost -including cost of any rework - will be a factor. Petitioner fears a threat that has yet to

1 10

)

materialize, and may never do so. If, in the future, staff imposes a requirement for additional seismic upgrade work which USEC seeks to contest, USEC will have an opportunity to do so at i

I that time. Therefore, we reject this issue as a basis for challenging the Director's Decision.

C.

USEC issue 3: A Recent Study Shows Actual Health Risks from a Postulated Seismic Event To Be Low.

i i

l The petitioner bc.: eves that the LLNL report that it has submitted calls into question the justification for the planned structural modifications and therefore, before the modifications are l

\\

undertaken, NRC should consider the results of the report and determine whether the expenditure of funds to undertake the modifications is appropriate or necessary. Elsewhere in j

l the petition, the petitioner states ". that it would be compelled to make plant modifications, incurring competing risks identified in the USQs, even though the modifications may be determined to be inadequate or perhaps even unnecessary."2 DOE commissioned the LLNL study to verify the justification for continued operation (JCO) in Compliance Plan issue 36. Compliance Plan Issue 36 required that the modifications i

be installed by December 31,1997. The LLNL report was provided to DOE on March 17,199i, after NRC assumed regulatory oversight. The LLNL report was submitted to NRC, for information, on June 30,1997 - USEC did not, however, request NRC to review the report.

We also note that USEC has not requested the NRC staff to approve elimination of the requirement for the seismic upgrade modifications.

l i

2 Note that the Compliance Evaluation Report (NRC letter to USEC, December 8, 1997) concluded that the risks associated with the USQs would be minimized and acceptable as a result of preventive and mitigative measures that USEC would implement.

l

i l

l 11 The LLNL report concludes, as stated in USEC's petition, that "..even though the i

probability of earthquake damage to Buildings C-331 and C-335 is relatively high in their current condition, the health risk is low." However, the report further concludes that "The risk model includes a very approximate model of the on-site population exposure to UF and therefore, the model is not an accurate predictor of the total risk to the worker. For example, the risk model only includes the risk due to UF release, but the workers in buildings are also exposed to the l

risks from falling structures, which have not been considered." The report also concludes, "If a severe earthquake were to occur, some on-site fatalities are likely because of the concentra: ion of people. The analysis does not indicate this result be :ause it does not model the high concentrations of toxic materials near the point of release, nor is there any consideration given to ' normal' earthquake hazards, such as falling debris."

In a January 5,1998 letter to NRC, DOE documented that it contracted with LLNL to perform a review of the PGDP seismic analysis to verify the content of the JCO that was 4

required for the Compliance Plan seismic issue. The review was intended as a scoping analysis to provide a general overall risk perspective and was performed to ensure that PGDP could continue to operate in a safe manner for a limited period of time until the appropriate modifications could be performed. In the letter, DOE states that the LLNL review was never intended to support continued operation for an indefinite period of time without the proposed modifications, and the methodology and rigor used in the study were inconsistent with this intention. DOE reviewed the report and identified four limitations in the report as follows: 1) the review did not include the full matrix of contributors to risk from all the potential failure modes and effects - only those considered more significant; 2) the review approximated the sliding beam failure with a mcdified S-shaped typical building fragility curve instead of the actual PGDP Building C-331 and C-335 sliding beam fragility curve, which exhibits abrupt failure; 3) the

r l

12 review did not address the risk to all on-site workers; and 4) the review did not address long-l term, ground-hugging releases. (DOE letter to NRC, January 5,1998). DOE concluded, in summary, that the LLNL review was prepared for a specific purpose and would require substantial additional effort to resolve regulatory questions and concerns if applied for uses 1

other than to support a JCO for a short period of time. It should be noted that when the LLNL study was prepared, completion of the modifications was scheduled for December 31,1997.

DOE further concluded that it does not consider the elimination of the proposed seismic upgrades for PGDP as a viable option and that it pursued an accelerated schedule for completion of the modifications when it had regulatory authority over PGDP.

DOE, which requested this report, believes that the LLNL report contains limitations that would prevent its use other than for its intended purpose, to support a JCO for a short period of time. Therefore, we find the report cannot be used to support elimination of the modifications altogether. The seismic modifications needed to meet a 0.15g earthquake are necessary to satisfy the current approved Compliance Plan and are not subject to backfit evaluation.

Regarding the petitioner's concern about the expenditure of funds, modifications needed to resist an earthquake above 0.15g are subject to backfit evaluation where cost -including the cost of any rework --is a consideration. Further, the cost of any modifications necessary to meet a 0.15g earthquake is fully reimbursable by DOE (USEC letter to NRC, June 30,1997)-

and DOE has indicated, in its January 5 letter, that the currently planned structural modifications should be installed.8 I

a in accordance with a Memorandum of Understanding (MOU)(62 FR 59910) with DOE, in mid-November 1997, the staff discussed, with DOE the proposed Compliance Plan changes from USEC's amendment request. DOE supported NRC's position on the changes, as reflected in the staff's Compliance Evaluation Report (CER) on USEC's amendment request.

l I

O

13 i

We find that the limitations in the scope and content of the LLNL report as discussed earlier prevent reliance on this report as a basis for reconsideration of the denial of portions of the amendment to the Compliance Plan. Therefore, we reject this basis for challenging the Director's Decision.

D.

USEC issue 4: NRC Has Not Yet Reviewed or Approved Final Design Information Provided by USEC.

The petitioner believes that final design information submitted by the petitioner should be reviewed by NRC before the modifications are installed. The petitioner believes that there is a significant risk that NRC could later require expensive changes.

USEC correctly states, in its petition, that NRC has not yet reviewed nor approved final design information provided by USEC. The Compliance Plan, as noted by USEC in its petition, does not require the staff to review the final design information before requiring USEC to proceed with actual modifications. NRC, in making an informed safety decision, relies extensively on the technical competence and integrity of licensees and certificate holders.

NRC, in issuing certificates to USEC, has determined that USEC, as the organization responsible for safety at the gaseous diffusion facilities, is competent and has the technical expertise to operate and maintain the facility. Although NRC did not review the final design in detail, DOE performed the initial conceptual design of the structural modifications, before NRC assumed regulatory oversight of the GDPs and is funding USEC's activities associated with the seismic modifications (USEC letter dated June 30,1997).

NRC did require USEC, the certificate holder, to provide the proposed structural modification design information, thus allowing the staff to make a detailed review if the staff's 1

14 initial overview indicated it was warranted. NRC selectively reviews submittals to allow staff to continue to assess the status of safety at a facility. NRC would perform a detailed computational validation for the type of seismic calculations used to implement modifications such as those proposed by USEC, if it were determined that a detailed review were necessary because of readily evident or perceived inadequacies or if the staff concludes that the review is necessary to support its safety decision. NRC, based on a limited overview of the proposed modification, has not raised any concerns with respect to the final design information supplied by USEC, Consequently a detailed prior NRC review of the proposed structural modification was not performed, and is not planned.

Petitioner's request for NRC to review final design information before the modifications are installed because of the risk that NRC may later require expensive changes is without merit.

USEC, as the certificate holder, bears the responsibility for the accuracy of the modifications and, if the modifications contain errors, USEC will be required to correct any errors, regardless of when they are discovered. If the upgraded seismic hazard analysis is eventually found to support an increase above 0.15g and the current modifications are found to be insufficient to resist an earthquake greater than 0.15g, then any additional modifications needed to increase the resistance from 0.15g to the higher value, will be subject to backfit evaluation (see Section B, USEC issue 2). Therefore, we reject this basis for challenging the Director's Decision.

I E.

USEC issue 5: The NRC Has Not Yet Reviewed PGDP Building and Equipment Seismic Capacity Information Submitted by USEC as Part of the Required SAR Update Submittal.

The petitioner believes that the updated SAR (SARUP) information submitted to NRC in

l 15 l

accordance with the requirements of the Compliance Plan should be reviewed by NRC before any seismic modifications proceed. According to USEC, the SARUP information indicates that areas of two other buildings (i.e., two product withdrawal buildings, Buildings C-310 and C-315) are also susceptible to seismic-induced damage. The petitioner argues that the SARUP information shows that the planned modifications are not, by themselves, effective in reducing the seismic risk at PGDP since the C-331 and C-335 failures do not dominate seismic risk at the site. The petitioner asserts that the SAR analysis shows that only a modest risk reduction would be achievable by a comprehensive set of modifications to harden the plant to resist an EBE. The petitioner further states that the LLNL report demonstrates that even onsite consequences of a seismic event constitute a low seismic risk.

It is possible that the staff's review of the SARUP could result in the requirement for modifications to other buildings and equipment; however, this has no bearing on the currently planned modifications. Any requirement for new modifications to other buildings that may result from the staff's review of the SARUP would not change the need for the currently planned structural modifications to Buildings C-331 and C-335. Furthermore, petitioner's assertion that the SARUP analysis demonstrates that the structural modifications in Buildings C-331 and C-335 would not be effective in reducing seismic risk at PGDP, since the C-331 and C-335 failures do not dominate risk, ignores the fact that the SARUP analysis assumes that the seismic upgrades to C-331 and C-335 have already been completed. As stated above, the presence of greater risks from other sources would not obviate the need for the already i

planned upgrades. NRC is reviewing the SARUP analysis and will take actions, as appropriate.

Regarding the petitioner's reliance on the LLNL report, we find that the limitations in the scope i

and content of the LLNL report prevent reliance on this report (see Section C, USEC issue 3).

We find that petitioner's request that the staff review the SARUP information before

16 installation of the modifications, is without merit. There is no linkage between the currently planned modifications and any other future modifications to other buildings. We also find that the limitations in the scope and content of the LLNL report as discussed earlier prevent reliance on this report as a basis for reconsideration of the denial of portions of the amendment to the Compliance Plan. Therefore, we reject this basis for challenging the Director's Decision.

1 F.

USEC issue 6: Public Health and Safety Will Be Protected During the Requested Delay.

The petitioner believes that the actual risk of harm is low, based on the LLNL report.

Further, the petitioner believes that, since NRC approved an 18-month extension to complete installation of the modifications in its CER, an additional 3 to 4 month delay (petitioner estimate) for the staff to review the information requested by the petitioner is acceptable, based on the current JCO.

j According to DOE, the LLNL review "...was intended as a scoping analysis to provide a general overall risk perspective and was performed to ensure that PGDP could continue to operate in a safe manner for a limited period of time until the appropriate modifications could be performed. The LLNL review was never intended to support continued operation for an indefinite period of time without the proposed modifications..." (See Section C, USEC lssue 3 and DOE letter dated January 5,1998.) At the time the LLNL review was being performed, it was expected that the modifications would be completed by December 31,1997, according to the commitment date in the Compliance Plan.

The currently planned modifications, as designed, will substantia ;y improve the seismic resistance of the buildings above the current level of 0.05g, substantially decreasing the risk to the health and safety of the workers, and could begin to be installed immediately. In addressing L

I 17 each of the petitioner's issues above, we have discussed why the reviews requested by the petitioner are not needed prior to beginning the structural modifications.

Moreover, the petitioner's estimate of delay is inaccurate. The delay in completing installation of the modifications resulting from having the staff complete the reviews requested by USEC in the amendment request (i.e., USEC's final design of the structural modifications, seismic analyses in USEC's updated SAR, and the seismic hazard analysis submitted by USEC on December 1,1997) could range from at least several months, if the modifications were found to be acceptable, to several years, if the staff concludes that the modificatioas are not completely accurate, either because of USEC design errors or because a higher earthquake level is appropriate (encompasses the time while new modifications are designed by USEC, reviewed and approved by NRC, and then fabricated and installed by USEC). NRC believes that the risk associated with operating and working in the buildings, in their current condition, warrants beginning the structural modifications without further delay.

The petitioner's characterization that NRC approved an 18-month extension in the absence of structural modifications is inaccurate. The staff approved an 18-month extension to complete the modifications, with the knowledge that the structural resistance of the buildings would gradually improve, over the 18 months, as the modifications are installed.

Petitioner's argument that public health and safety will be protected during the requested delay has not been substantiated. Therefore, we reject this basis for challenging the Director's Decision.

In summary, having addressed the individual arguments of USEC in detail above, the i

Commission finds that USEC has offered no sustainable basis for its request for review of the Director's Decision. The Commission finds that the ir,terest of protecting public and worker health and safety at Paducah dictates that the seismic modifications required by the i

i

e 18 Compliance Plan be implemented without delay as stated in the Director's Decision published in the Federal Reaister on December 16,1997.

For the foregoing reasons:

l The petition for review, dated December 30,1997, from the United States Enrichment Corporation, of Bethesda, Maryland, is denied in its entirety.

It is so ORDERrD.

[g.rsR HEQ For the Commission,'

3 y ..., @

-,Q a

.i) c w e n

' 4{. 'j' / ' h*

\\o C, "$[9[

' OHN C. H6YLE

~

retary of the Commission y s ae*

Dated at,Jiockville, Maryland, j

this /9Way of March 1998.

i 1

l I

' Commissioner Diaz was not available for the affirmation of this Order. Had he been present, he would have affirmed the Order.

p l

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of l

U.S. ENRICHMENT CORPORATION Docket No.(s) 70-7001 l

(Paducah, Kentucky)

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing COMM M&O DENY'G PET.--CLI-98-2 I

have been served upon the following persons by U.S. mail, first class, except as otherwise noted and in accordance with the requirements of 10 CFR Sec. 2.712.

Stuart A. Treby, Esq.

James H. Miller, Vice President Office of the General Counsel Production l

Mail Stop 15 B18 U.S. Enrichment Corporation U.S. Nuclear Regulatory Commission 6903 Rockledge Drive l

Washington, DC 20555 Bethesda, MD 20817 1

Carl J. Paperiello, Director Office of Nuclear Material Safety and Safeguards - Mail Stop T-8 A23 U. S. Nuclear Regulatory Commission 4

Washington, DC 20555 Dated at Rockville, Md. this 19 day of March 1998 Office of the Secretaty of the Commission c