ML20216E790

From kanterella
Jump to navigation Jump to search
Insp Rept 50-341/98-05 on 980320-0406.Violations Noted: Failure to Demonstrate Reactor Protection Sys Trip Function Units & Isolation Actuation Trip Units within Response Time Limit of at Least Once Per 18 Months
ML20216E790
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 04/10/1998
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20216E774 List:
References
50-341-98-05, 50-341-98-5, NUDOCS 9804160298
Download: ML20216E790 (5)


See also: IR 05000341/1998005

Text

O

O

U.S. NUCLEAR REGULATORY COMMISSION

REGIONlil

Docket No:

50-341

License No:

NPF-43

Report No:

50-341/98005(DRS)

Licensee:

Detroit Edison Company (DECO)

Facility:

Enrico Fermi, Unit 2

Location:

6400 N. Dixie Hwy

Newport, MI 48166

Dates:

March 20 - April 6,1998

Inspectors:

R. A. Westberg, Reactoi L, gineer, Rill

Approved by:

John M. Jacobson , Chief, Lead Engineers Branch

Division of Reactor Safety

l

t

9804160298 980410

PDR

ADOCK 05000341

PDR

G

<

,

r

~

O

.

EXECUTIVE SUMMARY

Enrico Fermi, Unit 2

NRC inspection Report 50-341/98005

This inspection reviewed and assessed a generic concern with the apparent inappropriate

removal of Response Time Testing from the Technical Specifications for sensors in the ECC,

-

isolation actuation, and RP systems via the 50.59 process.

.

l

l

l

Failure to demonstrate that reactor protection system trip function units were within their

.

l

response time limit at least once per 18 months was an apparent violation of TS 4.3.1.3

l

(Section E8.1).

Failure to demonstrate that isolation actuation trip units were within their response time

{

.

limit at least once per 18 months was an apparent violation of TS 4.3.2.3 (Section E8.1).

i

Failure to demonstrate that isolation emergency core cooling system trip units were

.

l

within their response time limit at least once per 18 months was an apparent violation of

'

TS 4.3.3.3 (Section E8.1).

.

Removal of response time testing for sensors in the reactor protection, emergency core

.

cooling, and isolation actuation systems from the technical specifications, without prior

i

NRC approval, was an apparent violation of 10 CFR 50.59 (Section E8.1).

l

,

4

l

.

2

L

.

.

Report Details

Engineering

E8

Miscellaneous Engineering issues

E8.1

(Closed) Unresolved item 50-341/97011-01: Generic concem with removal of response

time testing from the technical specifications (TS) for sensors in the emergency core

cooling system (ECCS), isolation actuation, and reactor protection system (RPS) via the

50.59 process.

On June 29,1994, the NRC issued Amendment 100 to the Fermi 2 Operating License,

consisting of a TS revision to relocate the response time limit tables to the updated final

safety analysis report (UFSAR).

On August 22,1994, the licensee relocated response time tables for the ECCS, RPS,

and isolation actuation instrumentation from the TS to the UFSAR to allow RTT limits to

be controlled in accordance with provisions of 10 CFR 50.59 in Licensing Change

Request 94-054-UFS.

On January 26,1996, the licensee prepared Safety Evaluation 95-0053 Revision 0, to

revise the UFSAR and technical requirements manual to eliminate RTT for selected

instruments.

On February 6,1996, the onsite review organization approved Safety Evaluation

95-0053.

On February 29,1996, the licensee issued Licensing Change Request 95-113-UFS to

eliminate selected RTT requirements from the UFSAR.

On June 26,1996, the licensee did not perform RTT procedures 44.010.009,010,023,

and 024; 44.020.011,014,045, & 046; and 44.030.261, and 262 prior to their critical

performance date.

On June 28,1996, the licensee did not perform RTT procedure 44.030.308 prior to its

critical performance date

On July 16,1996, the licensee did not perform RTT procedure 44.030.307 prior to its

critical performance date.

a.

Technical Specification 4.3.1.3 requires that the reactor protection system response

i

time of each reactor trip functional unit shall be demonstrated to be within its limit at

least once per 18 months.

3

r

1

l

.

k

l

l

1

!

Technical Specification 1.33 defines reactor protection system response time to be the

time interval from when the monitored parameter exceeds its trip setpoint at the channel

'

sensor until deenergization of scram pilot valve solenoids. The response time may be

measured by any series of sequential, overlapping or total steps such that the entire

response tim'e is measured.

As of March 19,1997, the licensee had not demonstrated that each reactor trip

functional unit was within its response time limit at least once per 18 months, because

the sensor v!as not included in the demonstration of response time. Specifically, the

licensee performed measurements in 1996 which were not in accordance with the above

technical specification requirements, in that the measurements did not include the time

interval for sensor response in the reactor protection system reesponse time

measurement. Instead, the licensee qualitatively confirmed sensor response to an

input, which did not demonstrate that the response time limits required by the technical

,

specifications were met. The affected reactor trip functional units are Reactor Vessel

Steam Dome Pressure - High and Reactor Vessel Low Water Level- Level 3.

Failure to demonstrate that these RPS trip function units were within their response time

limit at least once per 18 months is an apparent violation of TS 4.3.1.3 (eel

50-341-98005-01)

'

b.

Technical Specification 4.3.2.3 requires that the isolation system response time of each

isolation trip function shall be demonstrated to be within its limit at least once per 18

months.

J

Technical Specification 1.16 defines isolation system response time to be the time

interval from when the monitored parameter exceeds its isolation actuation setpoint at

the channel sensor until the isolation valves travel to their required positions. The

response time may be measured by any series of sequential, overlapping or total steps

such that the entire response time is measured.

As of March 19,1997, the licensee had not demonstrated that each isolation trip

function was within its response time limit at least once per 18 months, because the

sensor and related instruments were not included in the demonstration of response

time. Specifically, the licensee performed measurements in 1996 which were not in

accordance with the above technical specification requirements, in that the

measurements did not include the time interval for sensor and related instrument

response in the isolation system response time measurement. Instead, the licensee

qualitatively confirmed sensor and related instrument response to an input, which did

not demonstrate that the response time limits required by the technical specifications

were met. The affected primary containment isolation trip functions were Reactor

Vessel Low Water LeveJ - Level 1 and Main Steam Line Flow - High.

<

Failure to demonstrate that these isolation trip functions were within their response time

!

limit at least once per 18 months is an apparent violation of TS 4.3.2.3 (eel

'

50-341-98005-02)

c.

Technical Specification 4.3.3.3 requires that the ECCS response time of each ECCS trip

function shall be demonstrated to be within its limit at least once per 18 months.

4

l

!

l

1

.

l

TS 1.11 defined the ECCS response time as that time interval from when the monitored

parameter exceeded its actuation setpoint at the channel sensor until the ECCS

l

!

equipment was capable of performing its safety function, i.e., the valves traveled to their

l

required positions, pump discharge pressures reached their required values, etc. Times

l

included diesel generator starting and sequence loading delays, where applicable. The

l

response time might be measured by any series of sequential, overlapping or total steps

!

such that the entire response is measured.

i

As of March 19,1997, the licensee had not demonstrated that each ECCS trip function

was within its response time limit at least once per 18 months, because the actuation

l

instrumentation was not included in the demonstration of response time. Specifically,

the licensee performed measurements in 1996 which were not in accordance with the

above technical specification requirements, in that the measurements did not include the

time interval for actuation instrumentation response in the ECCS response time

measurement. Instead, the licensee qualitatively confirmed actuation instrumentation

response to an input, which did not demonstrate that the response time limits required

)

by the technical specifications were met. The affected ECCS trip functions were

l

Reactor Vessel Low Water Level - Level 1, Drywell Pressure - High, and Reactor Vessel

Low Water Level - Level 2.

Failure to demonstrate that these ECCS trip functions were within their response time

l

limit at least once per 18 months is an apparent violation of TS 4.3.3.3 (eel

50-341-98005-03)

d.

10 CFR 50.59 states, in part, that a licensee may make changes in procedures as

described in the safety analysis report without prior Commission approval, unless the

proposed change involves a change in the technical specifications incorporated into the

license.

In February 1996, the licensee made changes to Procedure Nos. 44.010.009-12;

44.010.021-024; 44.020.011-014; 44.020.043-046; 44.030.259-262; and 44.030.307-

'

310, which are described in the safety analysis report, to eliminate RTT for trip

functional units in the RPS and for trip units in the isolation and core cooling systems.

Prior Commission approval was not sought and these changes had the effect of

changing technical specification requirements. This is considered an apparent violation

of 10 CFR 50.59 (eel 50-341-98005-04).

V. Management Meetings

X1

Exit Meeting Summary

The inspectors conveyed the NRC's conclusion regarding four apparent violations involving

inappropriate elimination of response time testing from the technical specifications via the 50.59

process to licensee representatives during a telephonic exit on April 6,1998. The licensee

'

acknowledged the findings and did not indicate that any materialr examined during the

inspection should be considered proprietary.

,

5

1

I

E